Telephone call | | | 12/5/2017 | | DONE |
|
|
|
talked to Lisa Gute-she needs a 302 form filled out after Infintiy Designs gets us a letter stating they did not finish the job. She wants to be the GC
|
BLD-Aging Inspection | 11/29/2017 | 11/29/2017 | 11/30/2017 | | PEND |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 7/18/2017 | 7/18/2017 | 7/18/2017 | P | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 6/29/2017 | 6/29/2017 | 6/29/2017 | P | PART |
Mike Jordan
|
|
|
Matt-please call 30 minutes prior to meet Phone #: ###-####. Footing in basement. 30"x30"X10" with four #4 eachway. No city approved plans on site. Need to verify on next inspection.
|
Issue PAID IN FULL permit | | | 6/26/2017 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 6/15/2017 | 6/15/2017 | 6/23/2017 | | PASS |
Josh Bogle
|
|
|
1st. done - need more info
|
Routing - PLAN CHECK | 6/23/2017 | | 6/23/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2017 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 6/23/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/15/2017 | | 6/21/2017 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 6/21/2017 | | FAIL |
Josh Bogle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/15/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/15/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/15/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/14/2017 | | FAIL |
Christina Prado
|
|
|
Please provide updated proposed floor plan detailing existing walls, rooms labeled & proposed beam location
|
Application received | | | 6/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 8 2017 1:00PM
|