BLD-Final | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman,, seal fitrewall,, then ok
|
DOC - Permit Finaled | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/15/2018 | 2/15/2018 | 2/16/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/14/2018 | 2/14/2018 | 2/15/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 10/3/2017 | 10/3/2017 | 10/3/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 9/29/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall Bracing | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
Plan Modification Accepted | | | 9/18/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 9/18/2017 | | 9/18/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 9/14/2017 | 9/15/2017 | 9/15/2017 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman,, need nails or ok from architect
|
BLD-Foundation | 7/12/2017 | 7/13/2017 | 7/13/2017 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress
|
BLD-Footing | 7/11/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 7/10/2017 | 7/11/2017 | 7/11/2017 | P | NR |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 6/29/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 6/9/2017 | 6/9/2017 | 6/29/2017 | | DONE |
Brian McGowan
|
|
|
6/22 sfd L1 ePlan
|
Routing - PLANNING | 6/9/2017 | | 6/29/2017 | | PASS |
Sue Cummings
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/29/2017 | | DONE |
|
|
|
all met
|
1st review completed | | | 6/28/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/9/2017 | | 6/28/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 6/9/2017 | | 6/14/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 6/9/2017 | 6/12/2017 | 6/12/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 6/9/2017 | | 6/12/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/9/2017 | | 6/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/9/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/9/2017 | | DONE |
|
|
|
|
Application received | | | 6/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 8 2017 3:31PM
|