BLD-Final | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 2/13/2018 | 2/13/2018 | 2/13/2018 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen needs hand rail
|
Elevation Cert Rec'd-Final | | | 2/13/2018 | | DONE |
|
|
|
Approved LOMR on File. No floodplain review required. JCT
|
BLD-Final | 2/7/2018 | 2/8/2018 | 2/9/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Other | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PASS |
Jim Sly
|
|
|
Broken truss inspection Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Wall cover | 11/15/2017 | 11/15/2017 | 11/15/2017 | P | PASS |
Brandon Shaw
|
|
|
WUI zone soffit Inspection for can lights Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Energy code compliance | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PART |
Brandon Shaw
|
|
|
Need engineering for broken truss at familly room ceiling
OK to cover all but ceiling in family room
|
BLD-Framing/Rough-in | 11/8/2017 | 11/9/2017 | 11/9/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Wall Bracing | 10/13/2017 | 10/16/2017 | 10/16/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Foundation | 9/15/2017 | 9/15/2017 | 9/18/2017 | P | PASS |
Brandon Shaw
|
|
|
Wall // Surgeo Phone #: ###-####
|
BLD-Footing | 9/12/2017 | 9/13/2017 | 9/13/2017 | A | PASS |
Brandon Shaw
|
|
|
Sergio Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/5/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 7/26/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 6/19/2017 | 6/19/2017 | 7/26/2017 | | DONE |
Brian McGowan
|
|
|
6/30 sfd Level 1 ePlan
|
Routing - PLAN CHECK | 6/19/2017 | | 7/26/2017 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 7/26/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/26/2017 | | DONE |
|
|
|
met
|
Routing - MECHANICAL | 7/21/2017 | | 7/21/2017 | | PASS |
Troy James
|
|
|
|
Routing PW Flood Plain | 6/19/2017 | | 6/26/2017 | | PASS |
Jason C. Taylor
|
|
|
Two Elevation Certificates will be required; one prior to receiving a framing inspection, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval.
|
Elevation Cert Rec'd-Prelim | | | 6/26/2017 | | DONE |
|
|
|
Two Elevation Certificates will be required; one prior to receiving a framing inspection, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval.
|
Routing - MECHANICAL | 6/19/2017 | | 6/21/2017 | | FAIL |
Troy James
|
|
|
emailed correction to legends mech
|
Route to Impact Fee Review | 6/19/2017 | 6/22/2017 | 6/20/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 6/19/2017 | | 6/19/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/19/2017 | | 6/19/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/19/2017 | | 6/19/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 6/19/2017 | | FAIL |
|
|
|
Needs elevation certificate
|
Plans ACCEPTED BY PLAN TECH | | | 6/19/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/19/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/19/2017 | | DONE |
|
|
|
|
Application received | | | 6/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 12 2017 12:47PM
|