BLD-Framing/Rough-in | 12/20/2017 | 12/22/2017 | 12/22/2017 | A | PASS |
Tony Young
|
|
|
Doug Phone #: ###-####,, insulation ok,, ok to cover
|
BLD-Framing/Rough-in | 12/5/2017 | 12/6/2017 | 12/6/2017 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 11/8/2017 | 11/9/2017 | 11/9/2017 | A | PASS |
Tony Young
|
|
|
Russel Phone #: ###-####,, new engineering ok
|
BLD-Wall Bracing | 11/2/2017 | 11/2/2017 | 11/2/2017 | P | FAIL |
Brandon Shaw
|
|
|
Not as per plans, submit revised engineering for back garage wall, window openings added.
|
BLD-Foundation | 10/9/2017 | 10/10/2017 | 10/10/2017 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
BLD-Footing | 10/6/2017 | 10/10/2017 | 10/10/2017 | A | PASS |
Brandon Shaw
|
|
|
Jim-as early as possible please Phone #: ###-####. Informed contractor he could proceed with concrete placement and to leave stringlines in place. Geotech letter received/approved by PW.
|
PubWorks Subgrade Approval | 10/6/2017 | 10/6/2017 | 10/6/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 10/5/2017 | 10/5/2017 | 10/5/2017 | P | NR |
Jim Storey
|
|
|
Doug Cobb Phone #: ###-#### need pw signoff
|
BLD-Footing | 10/4/2017 | 10/5/2017 | 10/5/2017 | A | CANC |
Brandon Shaw
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
Issue PAID IN FULL permit | | | 10/3/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/21/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/13/2017 | 6/13/2017 | 9/21/2017 | | PASS |
Josh Bogle
|
|
|
1st. done - needs engineering and fire details
|
Telephone call | | | 9/21/2017 | | DONE |
|
|
|
Left a message for Doug informing him that this permit is ready and the fee amount due for issuance
|
Routing - PLAN CHECK | 9/21/2017 | | 9/21/2017 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 9/21/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 9/21/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 9/21/2017 | | DONE |
|
|
|
All Met
|
Routing - PLAN CHECK | 9/20/2017 | | 9/20/2017 | | FAIL |
Josh Bogle
|
|
|
resubmittal still missing engineering and details of WUI ratings JAB
|
Plan resubmittals received | | | 9/14/2017 | | DONE |
|
|
|
Resiubmittals received 2 of each sheet 1, 2, 3 & took Josh Bogle
|
Routing - PLAN CHECK | 6/13/2017 | | 6/16/2017 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 6/16/2017 | | FAIL |
Josh Bogle
|
|
|
Foothills/WUI - needs engineering for foundation & tall walls, needs 1hr fire-rated wall assemblies
|
Routing - Erosion and Sediment | 6/13/2017 | | 6/15/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid PD and RP. Site preparation inspeciton required.
|
Routing Walk-In (Zoning) | 6/13/2017 | 6/13/2017 | 6/13/2017 | A | DONE |
|
|
|
doesn't meet R-1B setbacks for a 640 sq, ft. detached garage.
|
Routing Walk-In (PW Hillside) | 6/13/2017 | 6/13/2017 | 6/13/2017 | A | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (Zoning) | 6/13/2017 | 6/13/2017 | 6/13/2017 | A | PASS |
Sue Cummings
|
|
|
Changes made setbacks met!
|
Application received | | 6/13/2017 | | | |
|
|
|
|