First Notice | 8/17/2017 | 8/17/2017 | 8/22/2017 | | DONE |
Dave Hannah
|
|
|
This permit finaled on the web by Ami Tracy
|
BLD-Final | 8/14/2017 | 8/17/2017 | 8/17/2017 | A | PASS |
Dave Hannah
|
|
|
Call Jason Phone #: ###-#### Inspection requested via web by Ami Tracy
|
DOC - Permit Finaled | 8/17/2017 | 8/17/2017 | 8/17/2017 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 8/17/2017 | 8/17/2017 | 8/17/2017 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, fire alarm work completed under FIR16-00222 and will be included in the as-builts, fire extinguisher is in common area with a current inspection tag. Final life fire safety inspection for area of work passed/complete.
|
Plan assigned to (RMH) | 6/15/2017 | 6/15/2017 | 8/9/2017 | | DONE |
Ron Hill
|
|
|
|
BLD-Framing/Rough-in | 6/29/2017 | 6/29/2017 | 6/29/2017 | P | PASS |
Dave Hannah
|
|
|
Jason Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/23/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/23/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/15/2017 | | 6/19/2017 | | PASS |
Ron Hill
|
|
|
|
1st review completed | | | 6/19/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 6/19/2017 | | DONE |
|
|
|
***Met 6-22-17 CAN***Need revised cert of value and GC form
|
Routing - FIRE | 6/15/2017 | 6/15/2017 | 6/16/2017 | | PASS |
Scott Arellano
|
|
|
FIre alarm modifications are indicated and fire sprinkler work MAY be required. PDS Fire Inspector to verify new wall do not affect sprinkler spacing. Separate permit are required.
|
Intake Approval | | | 6/15/2017 | | PASS |
|
|
|
|
Pending Assignment by CDM | 6/15/2017 | | 6/15/2017 | | DONE |
Carl D Madsen
|
|
|
|
Application received | | | 6/13/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 13 2017 10:56AM
|
Intake Approval | | | 6/13/2017 | | FAIL |
Julie Romig
|
|
|
Need: 1. Door and door hardware schedule for new door.
|