BLD-Final | 6/1/2018 | 6/4/2018 | 6/4/2018 | A | PASS |
Tony Young
|
|
|
Vedad Phone #: ###-####
|
DOC - Permit Finaled | 6/4/2018 | 6/4/2018 | 6/4/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 5/25/2018 | 5/29/2018 | 5/29/2018 | A | FAIL |
Mike Jordan
|
|
|
Vedad---Please call 30 mins before Phone #: ###-####. Needs to provide guard at west side of house at retaining wall. Provide blower door test result and post.
|
PubWorks Occupancy Approval | 5/25/2018 | 5/25/2018 | 5/25/2018 | | DONE |
Jason C. Taylor
|
|
|
|
Elevation Cert Rec'd-Final | | | 5/25/2018 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 4/16/2018 | 4/17/2018 | 4/17/2018 | A | PEND |
Tony Young
|
|
|
Call for access // Vedad Phone #: ###-####,, ceiling insulation,, just need to see the insulation self certification sticker at the final
|
BLD-Ceiling Grid Inspection | 4/16/2018 | 4/16/2018 | 4/16/2018 | P | DEFR |
Jim Storey
|
|
|
Call for access // Vedad Phone #: ###-#### to tony am tue
|
Elevation Cert Rec'd-Midconst | | | 4/16/2018 | | DONE |
|
|
|
|
BLD-Wall cover | 1/26/2018 | 1/29/2018 | 1/29/2018 | A | PASS |
Tony Young
|
|
|
Vedad Phone #: ###-####
|
BLD-Wall cover | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | NR |
Tony Young
|
|
|
Vedad Phone #: ###-####,, need to replace missing insulation where it has blown out and need to build chases
|
BLD-Energy code compliance | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | PART |
Tony Young
|
|
|
Vedad Phone #: ###-####,, replace blown out insulation,, fire block new chases when they are built
|
BLD-Framing/Rough-in | 1/19/2018 | 1/22/2018 | 1/22/2018 | A | PASS |
Tony Young
|
|
|
Call half hour before to meet /// Vedad Phone #: ###-####
|
OVERRIDE | | | 1/19/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 11/8/2017 | 11/8/2017 | 1/19/2018 | | DONE |
Brian McGowan
|
|
|
FAIL -plan mod
|
CHANGE STATUS TO (ISS) | | | 1/19/2018 | | DONE |
Christina Prado
|
|
|
Plan Mod approved, no fees due
|
Routing PW Flood Plain | 1/19/2018 | | 1/19/2018 | | PASS |
Jason C. Taylor
|
|
|
JCT requested I sign off for him.
|
Permit Ready to Issue | | | 1/19/2018 | | DONE |
|
|
|
Plan Mod approved, no fees due
|
Routing - PLAN CHECK | 1/16/2018 | | 1/16/2018 | | PASS |
Brian McGowan
|
|
|
|
CHANGE STATUS TO (REV) | | | 1/16/2018 | | DONE |
|
|
|
changed to fee status by mistake
|
Plan Reviewer's activity | | | 12/14/2017 | | |
Brian McGowan
|
|
|
Talked to Vedad. I explained that he needs to show how he replaced the anchor bolts.
|
Routing - PLAN CHECK | 11/8/2017 | | 11/13/2017 | | FAIL |
Brian McGowan
|
|
|
Plan Mod to update engineering. Need more specific engineering. Not just holddown substitutes.
|
Plan Modification Accepted | | | 11/8/2017 | | DONE |
Christina Prado
|
|
|
Plan mod to update stem wall
|
BLD-Wall Bracing | 11/6/2017 | 11/7/2017 | 11/7/2017 | A | FAIL |
Brandon Shaw
|
|
|
Need revised Engineering- stem wall was wrong height, builder cut approx 12" off stem wall elevation. No hold downs in place at time of inspection
|
Elevation Cert Rec'd-Midconst | | | 10/3/2017 | | DONE |
|
|
|
|
Routing PW Flood Plain | 10/3/2017 | | 10/3/2017 | | PASS |
Jason C. Taylor
|
|
|
Two Elevation Certificates will be required; one prior to receiving a framing inspection, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####
|
BLD-Foundation | 9/19/2017 | 9/20/2017 | 9/20/2017 | A | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo ,, work in progress
|
BLD-Footing | 9/18/2017 | 9/19/2017 | 9/19/2017 | P | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo ,, work in progress
|
Issue PAID IN FULL permit | | | 9/15/2017 | | DONE |
|
|
|
|
Place hold on job | 9/15/2017 | | 9/15/2017 | | DONE |
Tiffany Carson-Herker
|
|
|
Need signed permit, see Tiffany
|
Inspection Record Card- Bld | | | 9/15/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/14/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 6/26/2017 | 6/26/2017 | 9/14/2017 | | DONE |
Brian McGowan
|
|
|
1st review complete - FAIL - 7/7 sfd ePlan Level 1
|
Routing - PLAN CHECK | 9/14/2017 | | 9/14/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/14/2017 | | DONE |
|
|
|
All Met
|
Routing - PLANNING | 8/21/2017 | | 9/14/2017 | | PASS |
Sue Cummings
|
|
|
Driveway not to exceed 33' wide within the front setback.
|
Routing PW Flood Plain | 9/7/2017 | | 9/7/2017 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to receiving a framing inspection, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####
|
Routing PW Flood Plain | 8/25/2017 | | 8/25/2017 | | FAIL |
Jason C. Taylor
|
|
|
See changemarks in ePlan. JCT
|
1st review completed | | | 8/11/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering for tall walls and wall bracing required
|
Routing - PLAN CHECK | 6/26/2017 | | 8/11/2017 | | FAIL |
Brian McGowan
|
|
|
Engineering for tall walls and wall bracing required
|
Routing - PLANNING | 7/6/2017 | | 7/6/2017 | | PASS |
Sue Cummings
|
|
|
Comply with PW for flood requirements
|
Route to Impact Fee Review | 6/26/2017 | 6/29/2017 | 7/4/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Flood Plain | 6/26/2017 | | 6/28/2017 | | FAIL |
Jason C. Taylor
|
|
|
A portion of the property is within the floodplain. Comply with Boise Floodplain Ordinance (B.C.C. 11-08). Elevation Certificate and elevations need to be placed on site plan, foundation plan, and cross section plans. Jason Taylor ###-####
|
Plans ACCEPTED BY PLAN TECH | | | 6/26/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/26/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/26/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 6/26/2017 | | 6/26/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/26/2017 | | 6/26/2017 | | FAIL |
|
|
|
Needs floodplain review
|
Routing - Addressing | 6/26/2017 | | 6/26/2017 | | LDH |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/26/2017 | | 6/26/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 6/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2017 8:24AM
|