Permit Information
Permit NumberBLD17-02030
StatusFinaled
Name WOODHAVEN PROPERTIES
Site Address 5307 W WYLIE LN
Project NameWylie Lane Home
Customer Number 
ePlanReviewYes
Description
MODIFICATION - UPSTAIRS OFFICE & LIVING COMBINED INTO ONE ROOM - AFFECTED WALLS ARE NON-BEARING **jab** Permit for the construction of a new 2334 sq. ft., two story (first story 1528 sq. ft., second story 806 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 144 sq. ft. of covered patio/porch and a 449 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. All work per plans & local code. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Elevation Cert Rec'd-Final  1/8/2020 DONE
BLD-Final1/29/20191/30/20191/30/2019APASS
DetailsTony Young
Please call ahead for access -
Jeffrey Phone #: ###-####// c of o issued,, blower door is 3.9
DOC - Permit Finaled1/30/20191/30/20191/30/2019PPASS
DetailsTony Young
BLD-Other1/29/20191/29/20191/29/2019PDONE
DetailsBob Archibald
Received recorded easment
Elevation Cert Rec'd-Final  1/10/2019  
BLD-Final1/9/20191/9/20191/9/2019PNR
DetailsTony Young
Doug Phone #: ###-####,, needs trades passed,, sewer line issues,, c/n posted to resolve sewer line easment or reroute adjacent property owners sewer line with approvals from under this home. will also need a blower door test result
BLD-Energy code compliance6/8/20186/8/20186/8/2018PPASS
DetailsDave Hannah
Rob Phone #: ###-####
BLD-Framing/Rough-in6/4/20186/5/20186/5/2018APASS
DetailsTony Young
Rob Phone #: ###-####,, front house meets plans now,, ok to insulate
BLD-Conference6/4/20186/4/20186/4/2018PFAIL
DetailsTony Young
Rob Phone #: ###-####,, met with contractor,, he had reviewed plans,, needs to get approval from olan review and get ok as built.. remove or get approval as built or remove 220 in kitchen upstairs
BLD-Framing/Rough-in6/1/20186/4/20186/4/2018AFAIL
DetailsTony Young
Rob Phone #: ###-####,, no plans,, needs to remove 220 v circuit all the way out unless approved by the plan review
Routing Walk-In (BLD)6/4/20186/4/20186/4/2018PPASS
DetailsJosh Bogle
PLAN MOD - EASY/QUICK - NO FEE
Override - Parcel Holds6/4/20181/1/19006/4/2018  
not adu
Elevation Cert Rec'd-Midconst  5/23/2018 DONE
BLD-Conference5/16/20185/17/20185/17/2018AFAIL
DetailsTony Young
Rob Phone #: ###-####,, walk through only,, need plans,, elevation cert,, take out added ADU components
BLD-Framing/Rough-in5/9/20185/9/20185/9/2018PFAIL
DetailsTony Young
- Rob Phone #: ###-####,, need city set of plans
Override - Parcel Holds5/9/20181/1/19005/9/2018  
not for adu
BLD-Conference5/4/20185/4/20185/7/2018PFAIL
DetailsBrandon Shaw
Need to provide city approved set of plans
BLD-Framing/Rough-in4/27/20184/30/20184/30/2018AFAIL
DetailsTony Young
Rob Phone #: ###-####,, need the reviewed plans on site
BLD-Framing/Rough-in4/24/20184/24/20184/24/2018PFAIL
DetailsTony Young
Rob Phone #: ###-####,, need plans and truss engineering,, need to verify how many dwelling units are under one roof
BLD-Framing/Rough-in4/17/20184/18/20184/18/2018AFAIL
DetailsTony Young
Rob Phone #: ###-####,, need plans
Plan Modification Accepted  4/11/2018 DONE
revised acca report
Routing - MECHANICAL4/11/2018 4/11/2018 PASS
DetailsChad Schwendiman
revised acca report
BLD-Wall Bracing3/19/20183/20/20183/20/2018PPEND
DetailsBrandon Shaw
Work in progress
Walked through with framer- Hold down, edge, and field nailing to be fixed by framing inspection
BLD-Wall Bracing3/19/20183/19/20183/19/2018PNR
DetailsTony Young
Rob Phone #: ###-####,, see paint marks
BLD-Foundation12/6/201712/6/201712/6/2017PFAIL
DetailsJim Storey
James Phone #: ###-#### placed with out insp.
BLD-Footing12/5/201712/5/201712/5/2017PPASS
DetailsTony Young
James Phone #: ###-####
Issue PAID IN FULL permit  9/12/2017 DONE
Inspection Record Card- Bld  9/12/2017 DONE
OVERRIDE  9/7/2017  
Routing Walk-In (BLD)9/7/20179/7/20179/7/2017ADONE
DetailsJosh Bogle
Plan assigned to (JAB) Josh7/26/20177/26/20179/7/2017 PASS
DetailsJosh Bogle
1st done - corrections required, floor joists, foundation/floor details to match flood elevations
Routing - Addressing6/21/2017 9/7/2017 PASS
DetailsDoug Chausow
Routing - PLAN CHECK9/7/2017 9/7/2017 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  9/7/2017 DONE
DetailsJosh Bogle
ESC yes - Energy yes
Permit Ready to Issue  9/7/2017 DONE
DetailsChristina Prado
All requirements met
Routing - PLAN CHECK8/17/2017 8/17/2017 FAIL
DetailsJosh Bogle
Elevation Cert Rec'd-Prelim  8/15/2017 DONE
Routing PW Flood Plain8/15/2017 8/15/2017 PASS
DetailsJason C. Taylor
Routing - PLANNING8/10/2017 8/10/2017 PASS
DetailsNicolette Womack
ROS17-00049 Finalized
Plan resubmittals received  7/31/2017 DONE
received the floor plain cert-scanned it in and emailed to to BJM & JAB-customer said she also gave a copy to JCT
Plan assigned to (BJM)6/21/20176/21/20177/26/2017 DEFR
DetailsBrian McGowan
7/04 sfd L2 ePlan
Routing - PLAN CHECK6/21/2017 7/26/2017 FAIL
DetailsJosh Bogle
1st review completed  7/26/2017 FAIL
DetailsJosh Bogle
Routing PW Flood Plain6/21/2017 6/28/2017 FAIL
DetailsJason C. Taylor
see changemarks in eplan. JCT
Route to Impact Fee Review6/21/20176/24/20176/22/2017 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL6/21/2017 6/22/2017 PASS
DetailsChad Schwendiman
Routing - PLANNING6/21/2017 6/22/2017 FAIL
DetailsSue Cummings
Need proof this is a legal lot, created prior to 1965
Routing - PUBLIC WORKS6/21/2017 6/21/2017 PASS
DetailsRachael Beierle
Intake Approval  6/21/2017 PASS
Recd Pcfee & Taken To Pln CK  6/21/2017 DONE
Application received  6/20/2017 DONE
Application submitted via PDS Online on Jun 20 2017 4:06PM