Permit Information
Permit NumberBLD17-02032
StatusFinaled
Name WOODHAVEN PROPERTIES
Site Address 5313 W WYLIE LN
Project NameWylie Lane Shop w/ADU
Customer Number 
ePlanReviewYes
Description
Flood Plain - Modification - Letter added to file detailing requirements for moving forward 9-6-18 **JAB** MODIFICATION - SLIGHT CHANGE TO FLOOR PLAN - 1/2 BATH IS ONLY PERMITTED PLUMBING DOWNSTAIRS PER PLANNING APPROVAL **jab** 6/25/18 - Permit to build a 1,200sq' detached Shop Building-with a 564sq' ADU above. All work per plans & local code. Separate electrical, plumbing & mechanical permits required. **JAB** NOTE: Two Elevation Certificates will be required; one prior to receiving a framing inspection, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor 208-608-7171
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/23/20197/24/20197/24/2019APASS
DetailsDave Hannah
Jeffrey Phone #: ###-####
DOC - Permit Finaled7/24/20197/24/20197/24/2019PPASS
DetailsDave Hannah
Elevation Cert Rec'd-Final  6/13/2019 DONE
Received final elevation certificate. Project may be approved for occupancy. Jason Taylor ###-####
Routing PW Flood Plain6/13/2019 6/13/2019 PASS
DetailsJason C. Taylor
Received final elevation certificate. Project may be approved for occupancy. Jason Taylor ###-####
Routing - PLANNING5/14/2019 5/14/2019 FAIL
DetailsNicolette Womack
Driveway required to be paved prior to any occupancy.
BLD-Other5/14/20195/14/20195/13/2019ADONE
DetailsNicolette Womack
Planning Site Inspection. Building conforms with plans. Drivewa required to be paved prior to occupancy.
BLD-Final5/8/20195/8/20195/8/2019PNR
DetailsTony Young
Jeffrery Phone #: ###-####- Please call for access,, needs zoning,, address or signage from Wylie,, hard surface driveway,, verify flood cert
CHANGE STATUS TO (ISS)  11/14/2018 DONE
no fees due-drawings are in paper not threw e plan and are on the counter behind the permit techs
(F) Reprint permit  11/14/2018 DONE
Plan assigned to (JAB) Josh9/5/20189/5/20189/6/2018 PASS
DetailsJosh Bogle
Routing - PLANNING9/6/2018 9/6/2018 PASS
DetailsCeline Acord
Modification approved per attached letter
Routing - PLAN CHECK9/6/2018 9/6/2018 PASS
DetailsJosh Bogle
see clarification letter detailing requirements (DOC_Modification 9-6-18)
Case Summary (BLD)  9/6/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  9/6/2018 DONE
DetailsJosh Bogle
no Plan Review fee
Permit Ready to Issue  9/6/2018 DONE
Telephone call  9/6/2018 DONE
called Rob to advise plan mod is ready to issue
Plan Modification Accepted  9/5/2018 DONE
Meeting  8/14/2018 DONE
Clarence Pond in office to discuss why inspector 415 ok to insulate but not cover. Insp. out of office to unable to find out what issue is. Told him approved plans need to be onsite that show redlines washer/dryer removed from project and only (1) 1/2 bath allowed in downstars.
BLD-Conference8/2/20188/3/20188/3/2018APEND
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review and planner out to site,, took plan review and a planner to see property
BLD-Conference7/31/20188/1/20188/2/2018PDEFR
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review and planner out to site
BLD-Conference7/27/20187/30/20187/31/2018PPEND
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review and planner out to site
BLD-Conference7/25/20187/26/20187/27/2018APART
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review out to site,, took Rob P. out
BLD-Conference7/24/20187/25/20187/25/2018ANR
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review out to site
BLD-Conference7/23/20187/24/20187/24/2018APEND
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review out to site
BLD-Conference7/20/20187/23/20187/23/2018ANR
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####/// take plan review out to site
BLD-Framing/Rough-in7/20/20187/20/20187/20/2018PPART
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####,, see prior notes,, ok to insulate,, no cover until issues on the plans are resolved
BLD-Framing/Rough-in7/19/20187/20/20187/20/2018AFAIL
DetailsTony Young
Please call to let him know if he passed // Rob Phone #: ###-####,, needs to comply with the plans,, ok to insulate to keep moving forward
Inspection Record Card- Bld  7/19/2018 DONE
CHANGE STATUS TO (ISS)  7/19/2018 DONE
plan mod
Plan assigned to (JAB) Josh4/25/20184/25/20186/25/2018 PASS
DetailsJosh Bogle
Plan Mod - Modifying existing floor plan only
Routing - PLANNING6/25/2018 6/25/2018 PASS
DetailsCeline Acord
Authorized, with conditions. (see redlines) No washer/dryer downstairs. Remove third sink.
Routing - PLAN CHECK6/25/2018 6/25/2018 PASS
DetailsJosh Bogle
two hour Modification fee
PLANS/APPL TAKEN TO FRONT DESK  6/25/2018 DONE
DetailsJosh Bogle
Override - Parcel Holds  6/25/2018  
Permit Ready to Issue  6/25/2018 DONE
plan mod so please do not re issue and remove the prcel hold
Routing Walk-In (BLD)6/15/20186/15/20186/15/2018AFAIL
DetailsJosh Bogle
talked about the Plan Modification process
Routing - PLAN CHECK6/13/2018 6/13/2018 FAIL
DetailsJosh Bogle
modification resubmittal show multiple floors plans - review not possible
Telephone call  6/1/2018 DONE
Spoke with Rob, Woodhaven Properties, that no inspections can be scheduled until they bring in plans and have approved. Failed on 5/11 and haven't been back in since.
Routing - PLAN CHECK5/4/2018 5/11/2018 FAIL
DetailsJosh Bogle
no Plan Review - Planning failed, design may change
Routing - PLANNING5/4/2018 5/4/2018 FAIL
DetailsCeline Acord
Mod plans do not match the original ADU approval (CAA17-00225). Either match original approved plans or go through PUD application process in order to keep the 2.5 bathrooms proposed.
Intake Approval  5/1/2018 FAIL
Intake for plan mod failed. Nothing was uploaded.
BLD-Framing/Rough-in4/27/20184/30/20184/30/2018AFAIL
DetailsTony Young
Rob Phone #: ###-####,, need the reviewed plans on site
Elevation Cert Rec'd-Midconst  4/27/2018 DONE
Routing PW Flood Plain4/27/2018 4/27/2018 PASS
DetailsJason C. Taylor
Elevation Certificate #2 approved. JCT
Plan Modification Accepted  4/25/2018 DONE
DetailsChristina Prado
Modifying existing floor plan only, Route to Planning. (Brian Oliver is contact
BLD-Framing/Rough-in4/24/20184/24/20184/24/2018PFAIL
DetailsTony Young
Rob Phone #: ###-####,, need flood elevation approved by public works,, need plans and truss engineering,, need to verify how many dwelling units are under this roof
BLD-Framing/Rough-in4/17/20184/18/20184/18/2018AFAIL
DetailsTony Young
Rob Phone #: ###-####,, needs elevation cert,, need plans
BLD-Conference4/11/20184/11/20184/11/2018PFAIL
DetailsTony Young
complaint not building per plans. Adding rooms and bathrooms not approved.,, correction notice posted to see plan review and get approval for changes,, needs a mid flood elevation cert. also
BLD-Conference4/10/20184/11/20184/11/2018ADEFR
DetailsTony Young
complaint not building per plans. Adding rooms and bathrooms not approved.
Plan Modification Accepted  4/11/2018 DONE
revised acca report
Routing - MECHANICAL4/11/2018 4/11/2018 PASS
DetailsChad Schwendiman
revised acca report
BLD-Wall Bracing3/19/20183/20/20183/20/2018PPEND
DetailsBrandon Shaw
Work in progress
BLD-Wall Bracing3/19/20183/19/20183/19/2018PNR
DetailsTony Young
Rob Phone #: ###-####,, see paint marks
BLD-Foundation12/6/201712/6/201712/6/2017PFAIL
DetailsJim Storey
James Phone #: ###-#### placed with out insp.
BLD-Footing12/5/201712/5/201712/5/2017PPASS
DetailsTony Young
James Phone #: ###-####
Issue PAID IN FULL permit  11/3/2017 DONE
Route to Impact Fee Review11/1/201711/6/201711/1/2017 PASS
DetailsMatt Brookshier
this is an new ADU above a new garage with a new address
Plan assigned to (JAB) Josh10/19/201710/19/201711/1/2017 PASS
DetailsJosh Bogle
1st done - need more info, notes in E-plan
Permit Ready to Issue  11/1/2017 DONE
Need
RP
Met-make sure impact fees have been signed off before issuing (could be more fees)
Routing - PLAN CHECK11/1/2017 11/1/2017 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  11/1/2017 DONE
DetailsJosh Bogle
ESC yes - Energy yes - Plan mod fees yes
Routing - PLAN CHECK10/31/2017 10/31/2017 FAIL
DetailsJosh Bogle
same issues unresolved
Routing - MECHANICAL10/30/2017 10/30/2017 PASS
DetailsTroy James
Routing - PLAN CHECK10/30/2017 10/30/2017 FAIL
DetailsJosh Bogle
still missing same structural details JAB
Routing - MECHANICAL10/25/2017 10/26/2017 FAIL
DetailsTroy James
Still need manual j report
Routing - PLAN CHECK10/25/2017 10/26/2017 FAIL
DetailsJosh Bogle
lacks needed details JAB
Routing - PLANNING10/26/2017 10/26/2017 PASS
DetailsCeline Acord
CAA17-00225
Routing - PLANNING10/25/2017 10/25/2017 FAIL
DetailsCeline Acord
Floor layout and elevations need to match site plan and other plans
Routing Walk-In (BLD)10/20/201710/20/201710/20/2017AFAIL
DetailsJosh Bogle
Routing - PLAN CHECK10/19/2017 10/20/2017 FAIL
DetailsJosh Bogle
Routing PW Flood Plain10/19/2017 10/20/2017 PASS
DetailsJason C. Taylor
NOTE:
Two Elevation Certificates will be required; one prior to receiving a framing inspection, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####
1st review completed  10/20/2017 FAIL
DetailsJosh Bogle
Routing - MECHANICAL10/19/2017 10/19/2017 FAIL
DetailsTroy James
Need manual j report. Talked to Clarence Pond and informed him to provide manual j report.
Routing - PLANNING10/19/2017 10/19/2017 FAIL
DetailsCeline Acord
Drawings need to match (site plan, floor plan, elevations, etc.)
Routing - Addressing10/19/2017 10/19/2017 PASS
DetailsDoug Chausow
ADU Address: 5313 W Wylie Ln
Routing - PUBLIC WORKS10/19/2017 10/19/2017 PASS
DetailsMorgan Webb
Plans ACCEPTED BY PLAN TECH  10/19/2017 DONE
Intake Approval  10/19/2017 PASS
Override - Parcel Holds  10/19/2017  
Recd Pcfee & Taken To Pln CK  10/19/2017 DONE
Meeting  10/16/2017 DONE
DetailsJosh Bogle
Meeting  10/12/2017 DONE
DetailsJosh Bogle
just chatting
Meeting  10/11/2017 FAIL
DetailsDoug Chausow
meeting with addressing. Must go through application process before an ADU address can be issued.
Meeting  10/11/2017 FAIL
DetailsRachael Beierle
Meeging with Public Works. NEED TO SUBMIT PROPER ADU APPLICATION AND PLANS. SWR PERMIT MUST BE ATTACHED AFTER ADDRESS IS ISSUED.
Intake Approval  9/29/2017 FAIL
Need CAA17-00225 for ADU approved before can submit for building permit
Intake Approval  9/28/2017 FAIL
Need CAA17-00225 for ADU approved before can submit for building permit
Meeting  9/19/2017 DONE
DetailsJosh Bogle
Intake Approval  9/13/2017 FAIL
Needs ADU planning and zoning approval before building permit submittal.
Intake Approval  9/8/2017 FAIL
Sent Clarence an email (personal and eplan), voicemail box was full, informing his that we can not take this in until he applies with zoning for an ADU and everything has been approved with them.
Intake Approval  9/7/2017 FAIL
Still missing ADU App/Approval, no case with zoning for adu either
Intake Approval  6/21/2017 FAIL
DetailsChristina Prado
Need ADU App/Planning approval & Flood plain elevation certificate
Application received  6/20/2017 DONE
Application submitted via PDS Online on Jun 20 2017 7:59PM