BLD-Final | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | DONE |
Bob Archibald
|
|
|
Scope of work completed. No fire inspection required.
|
DOC - Permit Finaled | | | 11/20/2017 | | DONE |
|
|
|
|
BLD-Final | 9/11/2017 | 9/12/2017 | 9/12/2017 | P | PEND |
Mike Jordan
|
|
|
Please call Steve Nail at ###-#### prior to going to property. Thank you!!! Phone #: ###-#### Inspection requested via web by Kris Nevers. Needs fire life/safety final first.
|
BLD-Other | 7/17/2017 | 7/25/2017 | 7/25/2017 | P | DONE |
Mike Jordan
|
|
|
Status of stair repairs? 50 treads ordered per Steven Nail. Should be in by this friday. contractor noted thre to four days for install and then would call in for inspection.
|
Issue PAID IN FULL permit | | | 7/5/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/24/2017 | 6/27/2017 | 6/28/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 6/28/2017 | | DONE |
Christina Prado
|
|
|
Need GC form only
|
Inspection Record Card- Bld | | | 6/28/2017 | | DONE |
|
|
|
|
Telephone call | | | 6/28/2017 | | DONE |
|
|
|
called Brilliant Servies and left message for Steve permit is ready and need to fill out GC form and cert of value
|
Plan assigned to (CDM) | 6/22/2017 | 6/22/2017 | 6/24/2017 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/22/2017 | | 6/24/2017 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 6/24/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2017 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/24/2017 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/22/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/22/2017 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/22/2017 | | DONE |
|
|
|
|
Application received | | 6/22/2017 | | | |
|
|
|
|