First Notice | | 12/30/2017 | 1/11/2018 | | DONE |
|
|
|
Mailed 1-12-18
|
BLD-Final | 12/20/2017 | 12/20/2017 | 12/21/2017 | P | PASS |
Dave Hannah
|
|
|
No need to go out (ok for temp occ needs alarm finals Per david h 12/1/17) (alarm passed) just need a pass
|
Print Occupancy Form | | | 12/20/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/20/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/15/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Jim Page
|
|
|
Fire alarm modifications/inspection complete, final life fire safety inspection for areas of work complete.
|
BLD-Final | 11/30/2017 | 12/1/2017 | 12/1/2017 | P | PART |
Dave Hannah
|
|
|
Greg Phone #: ###-#### ok for temp occ needs alarm finals
|
FIRE-Final Inspection | 12/1/2017 | 12/1/2017 | 12/1/2017 | P | PART |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire extinguishers are in place with current inspection tags, fire alarm modifications are required and will be installed under FIR17-00702, TCO for life fire safety is authorized for 30 days per conversation with Scott Arellano pending fire alarm inspection when work is completed.
|
BLD-Final | 11/27/2017 | 11/28/2017 | 11/28/2017 | A | NR |
Tony Young
|
|
|
Greg Phone #: ###-####,, needs others 1st
|
FIRE-Final Inspection | 11/22/2017 | 11/27/2017 | 11/27/2017 | A | FAIL |
Jim Page
|
|
|
Provide fire alarm modifications to accommodate remodelled areas.
|
BLD-Final | 11/22/2017 | 11/27/2017 | 11/27/2017 | P | CANC |
Tony Young
|
|
|
CANC PER Greg on 11-27-17 Phone #: ###-####
|
BLD-Conference | 11/20/2017 | 11/21/2017 | 11/21/2017 | A | DONE |
Dave Hannah
|
|
|
Greg Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/13/2017 | 11/14/2017 | 11/14/2017 | P | PASS |
Dave Hannah
|
|
|
Greg Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/9/2017 | 11/13/2017 | 11/13/2017 | A | FAIL |
Dave Hannah
|
|
|
Greg Phone #: ###-####
|
BLD-Other | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | CANC |
Dave Hannah
|
|
|
sound insulation // Greg Olsen Phone #: ###-####
|
BLD-Framing/Rough-in | 9/26/2017 | 9/26/2017 | 9/26/2017 | P | PART |
Tony Young
|
|
|
Greg Phone #: ###-####,, walls ok
|
Issue PAID IN FULL permit | | | 8/23/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/23/2017 | | DONE |
|
|
|
|
Telephone call | | | 8/22/2017 | | DONE |
|
|
|
emailed Duncan Goundry fees due
|
Route to Impact Fee Review | 8/20/2017 | 8/23/2017 | 8/21/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 8/21/2017 | | DONE |
Christina Prado
|
|
|
Need:
GC Form-MET
Revised Cert of Value-MET
|
Plan assigned to (JAR) | 7/7/2017 | 7/7/2017 | 8/20/2017 | | DONE |
Julie Romig
|
|
|
07/20 (08/03) - L2 ISIF Lobby & Breakroom
|
Routing - PLAN CHECK | 7/7/2017 | | 8/20/2017 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 8/20/2017 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2017 | | DONE |
|
|
|
|
Routing - Addressing | 7/7/2017 | | 7/11/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - MECHANICAL | 7/7/2017 | | 7/10/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 7/7/2017 | | 7/10/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - FIRE | 7/7/2017 | 7/7/2017 | 7/7/2017 | | PASS |
Katie Marron
|
|
|
Separate Fire Permits WILL BE REQUIRED. No comments attached.
|
Intake Approval | | | 7/7/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie accepted pre screen
|
Routing - PUBLIC WORKS | 7/7/2017 | | 7/7/2017 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 6/28/2017 | | FAIL |
Julie Romig
|
|
|
|
Application received | | | 6/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 23 2017 3:25PM
|