BLD-Final | 5/9/2018 | 5/10/2018 | 5/10/2018 | A | PASS |
Mike Jordan
|
|
|
There is a lock box on the right side of the house attached to the gas meter. The code is 2056 Phone #: ###-#### Inspection requested via web by keith bucher
|
DOC - Permit Finaled | 5/10/2018 | 5/10/2018 | 5/10/2018 | P | PASS |
Mike Jordan
|
|
|
All issues are resolved.
|
BLD-Final | 5/6/2018 | 5/7/2018 | 5/7/2018 | P | CANC |
Mike Jordan
|
|
|
Lock box on right side of house attached to gas meter. Code is 2056 Phone #: ###-#### >> Inspection requested via web by keith bucher Inspection cancelled from web by: keith bucher
|
BLD-Final | 5/3/2018 | 5/4/2018 | 5/4/2018 | P | CANC |
Mike Jordan
|
|
|
Lock box on side of house attached to gas meter. Code is 2056 Phone #: ###-#### >> Inspection requested via web by keith bucher Inspection cancelled from web by: keith bucher
|
BLD-Final | 5/3/2018 | 5/4/2018 | 5/3/2018 | A | CANC |
Mike Jordan
|
|
|
Lock box on right side of house attached to gas meter. Code is 2056 Phone #: ###-#### >> Inspection requested via web by keith bucher Inspection cancelled from web by: keith bucher
|
BLD-Final | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | FAIL |
Mike Jordan
|
|
|
Key located in lock box on right side of house attached to gas meter. Code is 2056 Inspection requested via web by keith bucher. Provide code comp;iant handrail, cable guards at stairs require engineering. provide code compliant landings in back. Insulate crawl space. Step from bathroom to garage landing exceeds the 7.75 nch max. provide blower door test and required energy cert. Correction notice was posted.
|
BLD-Energy code compliance | 1/23/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by keith bucher
|
BLD-Framing/Rough-in | 1/24/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by keith bucher
|
BLD-Energy code compliance | 1/22/2018 | 1/23/2018 | 1/23/2018 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by keith bucher. All fraing issues not yet corrected.
|
BLD-Energy code compliance | 1/22/2018 | 1/23/2018 | 1/22/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by keith bucher Inspection cancelled from web by: keith bucher
|
BLD-Framing/Rough-in | 1/19/2018 | 1/22/2018 | 1/22/2018 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by keith bucher. Complete lateral bracing and truss fix, install floor to floor straps. ok to insulate.
|
BLD-Framing/Rough-in | 1/18/2018 | 1/19/2018 | 1/19/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by keith bucher. Provide truss engineering, provide engineering for the lateral design. Complete all fireblocking on furdowns, Provide mech connection at all beam to column connections. Provide header over door wat on in terior bearing wall. Block all panel edges on shear walls. crawl space acess? Correction notice posted. not able to do complete framing or wall bracing inspection due to missing engineering.
|
Plan Modification Accepted | | | 1/3/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/3/2018 | | 1/3/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Footing | 10/9/2017 | 10/10/2017 | 10/10/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
Issue PAID IN FULL permit | | | 9/29/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/29/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/6/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 9/6/2017 | | DONE |
|
|
|
all met
|
Plan assigned to (BJM) | 6/28/2017 | 6/28/2017 | 9/1/2017 | | DONE |
Brian McGowan
|
|
|
1st review complete - FAIL- 7/11 sfd ePlan Level 1
|
Routing - PLAN CHECK | 9/1/2017 | | 9/1/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/1/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 8/14/2017 | | 8/14/2017 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 8/3/2017 | | FAIL |
Brian McGowan
|
|
|
Structure issues
|
Routing - PLAN CHECK | 6/28/2017 | | 8/3/2017 | | FAIL |
Brian McGowan
|
|
|
Structure issues
|
Telephone call | | | 8/2/2017 | | DONE |
|
|
|
Keith Bucher emailed me, wanting to know when the permit would be ready-I spoke to Brian he'll try and have it done by Friday but the manual j's failed and we still have not received the corrections-i emailed Keith bqack with this info
|
Route to Impact Fee Review | 6/28/2017 | 7/1/2017 | 7/4/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/28/2017 | | 6/30/2017 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 6/28/2017 | | 6/28/2017 | | PASS |
Sue Cummings
|
|
|
Max. driveway width in front setback is 33 ft. Small home occupation is allowed.
|
Routing - Addressing | 6/28/2017 | | 6/28/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/28/2017 | | 6/28/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/28/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/28/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/28/2017 | | DONE |
|
|
|
|
Application received | | | 6/26/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 26 2017 12:18PM
|
Meeting | | | 6/26/2017 | | DONE |
|
|
|
waiting for customer to email me the building cross section-then i will approve the preescreen
|