Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-02121
StatusFinaled
Name ARTISAN HOME RENOVATIONS LLC
Site Address 1750 W STATE ST
Project NameCloud 9 Brewery - Expansion
Customer Number 
ePlanReviewYes
Description
(CLOUD 9 BREWERY & RESTAURANT – EXPANSION INTO ADJACENT SPACE) This building has a fire sprinkler system. To expand an existing 1,290 square foot tenant space into an adjacent 1,290 square foot space. After the expansion, this tenant space will have a total floor area of about 2,580 square feet. Portions of an interior nonbearing common wall located between the two spaces will be removed. Work is to include interior nonbearing walls, a toilet room accessible to the disabled, two Type I grease hood and duct systems, a Type II dishwasher hood and duct system, suspended acoustical ceilings, gypsum board ceiling, kitchen equipment, and finishes. Early start permit BLD17-02961 was prepared to allow interior nonstructural work to be started but not covered. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  4/19/2019 DONE
sent 1st late notice
Print Statement  12/27/2018 DONE
Print Statement  7/2/2018 DONE
Second Notice 5/20/20186/11/2018 DONE
mailed 6-12
First Notice 4/23/20185/10/2018 DONE
mailed 5-11-18
BLD-Final4/13/20184/16/20184/13/2018ADONE
DetailsTony Young
Maggie Phone #: ###-####
Permanent Occupancy  4/13/2018 DONE
BLD-Framing/Rough-in4/10/20184/10/20184/10/2018PPASS
DetailsTony Young
Maggie Lake Phone #: ###-####
BLD-Conference4/6/20184/10/20184/10/2018APEND
DetailsTony Young
Maggie-please call to meet Phone #: ###-####,, check on status
BLD-Conference4/5/20184/6/20184/6/2018APART
DetailsTony Young
Maggie-please call to meet Phone #: ###-####,, work in progress on rear office,, needs electrical permit..
BLD-Final3/12/20183/13/20183/13/2018PPART
DetailsTony Young
Magie-PW inspection will be done AM Phone #: ###-####,, temp occ ok,, needs to finish office area,, take down exit sign
FIRE-Final Inspection3/12/20183/13/20183/13/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in place with current inspection tags, commercial hood fire suppression inspection complete (FIR17-00500). Final life fire safety inspection for area of work complete.
Temporary Occupancy3/13/20186/11/20183/13/2018 DONE
DetailsTiffany Carson-Herker
Print Occupancy Form  3/2/2018 DONE
Print Occupancy Form  1/19/2018 DONE
Print Occupancy Form  1/19/2018 DONE
BLD-Framing/Rough-in1/5/20181/5/20181/5/2018PPASS
DetailsJim Sly
Maggie Phone #: ###-####
Print Occupancy Form  10/30/2017 DONE
Issue PAID IN FULL permit  10/30/2017 DONE
Plan resubmittals requested  10/27/2017 DONE
Plan resubmittals received  10/27/2017 DONE
Routing - PLAN CHECK10/27/2017 10/27/2017 PASS
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  10/27/2017 DONE
Permit Ready to Issue  10/27/2017 DONE
Need
Revised Cert of Value
GC Form
DO Not issue without BLD17-02961 (early start)
Plan assigned to (CJW)8/4/2017 10/27/2017 PASS
DetailsCarl Westfall
(2nd done) (Aug 24 - 15 days) (25 sheets) Cloud 9 Brewery
Routing PW Sewer Rating10/19/2017 10/26/2017 PASS
DetailsBeverly Mountain
Routing - MECHANICAL10/19/2017 10/26/2017 PASS
DetailsChad Schwendiman
Plan changed and move redline to most recent version
Plan resubmittals received  10/19/2017 DONE
Routing - PLAN CHECK10/19/2017 10/19/2017 FAIL
DetailsCarl Westfall
Weight and support of grease hoods not addresssed
Route to Impact Fee Review9/9/20179/12/20179/11/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK8/4/2017 9/9/2017 FAIL
DetailsCarl Westfall
Structural analysis of roof required
1st review completed  9/9/2017 DONE
Plan resubmittals requested  9/9/2017 DONE
Routing PW Environmental8/4/2017 8/29/2017 PASS
DetailsRick Christenson
Routing - FIRE8/4/20178/4/20178/14/2017 PASS
DetailsScott Arellano
Attached plan review comments to plans and case.
Routing PW Sewer Rating8/4/2017 8/9/2017 FAIL
DetailsBeverly Mountain
Need signed agreement for brewery portion. bam
Routing - PLUMBING8/8/2017 8/8/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing - Erosion and Sediment8/4/2017 8/8/2017 PASS
DetailsAndy J. Long
No ESC permit required. Interior work only described in project scope.
Routing - MECHANICAL8/4/2017 8/7/2017 PASS
DetailsChad Schwendiman
Routing - PLUMBING8/4/2017 8/7/2017 FAIL
DetailsBill VanDegrift
ISPC 418.4, 801.1 and 1002.1-- floor drains are not allowed in walk-in coolers, floor drain traps must be vented.
Routing - Addressing8/4/2017 8/4/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/4/2017 8/4/2017 PASS
DetailsRachael Beierle
Sewer rating not approved
Routing - Design Review8/4/2017 8/4/2017 PASS
DetailsSarah Schafer
No review required. No within a Design Review overlay. Expansion of the brewery allowed through CUP17-00007.
Intake Approval  8/4/2017 PASS
DetailsAdele J Schaffeld-Griffin
pre screen approved by Javier, recieved CDH approval
Plan Reviewer's activity  7/7/2017 DONE
waiting to route till all documents recieved that was missed at pre screen
Plan Reviewer's activity  7/7/2017 DONE
email sent to Jim 7/7/17
Jim, I have not heard back on the email below. I am holing off routing until we receive the information needed. Do you have a time frame when we might get the documents or the approval?

Thanks for your assistance.

Adele

Plan Reviewer's activity  6/28/2017 DONE
DetailsJavier Guzman
From: Javier Guzman
Sent: Wednesday, June 28, 2017 1:22 PM
To: office@grboise.com
Cc: Adele Schaffeld-Griffin ; Carl Madsen
Subject: ePlan BLD17-02121

Mr. Rockwell
I just passed the project above but we need a completed Food Establishment License application and Food Establishment Plan Review and Approval form for this project can you please email these completed forms back to me so that when received and fees are paid we can continue in the routing of this project. Just so that you are aware we will not route this project for review until the forms are sent to us

Thanks,
Javier Guzman
City of Boise
Plans Examiner II
###-####
jguzman@cityofboise.org

Application received  6/27/2017 DONE
Application submitted via PDS Online on Jun 27 2017 3:09PM