Print Statement | | | 9/25/2017 | | DONE |
|
|
|
|
First Notice | | 9/18/2017 | 9/19/2017 | | DONE |
|
|
|
sent in mail 9-20-17
|
BLD-Final | 9/7/2017 | 9/8/2017 | 9/8/2017 | P | PASS |
Brandon Shaw
|
|
|
Abel Phone #: ###-####
|
DOC - Permit Finaled | 9/8/2017 | 9/8/2017 | 9/8/2017 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection for area of work passed/complete.
|
Permanent Occupancy | | | 9/8/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete, modifications will be required to the fire sprinkler system due to ceiling being removed. Exit discharge illumination will be required at both exits. Painted fire sprinkler heads will need to be replaced.
|
Issue PAID IN FULL permit | | | 8/21/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/21/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 7/20/2017 | 7/20/2017 | 8/17/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) (Aug 9 - 15 days) (1 sheet)
|
Routing - PLAN CHECK | 7/20/2017 | | 8/17/2017 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
1st review completed | | | 8/17/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/17/2017 | | DONE |
|
|
|
need
GC
rev cert of val
|
Routing - FIRE | 7/20/2017 | 7/20/2017 | 7/25/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Intake Approval | | | 7/20/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie approved per screen, Javier notified applicant this change in occupancy will be routed as Major TI
|
Routing - Addressing | 7/20/2017 | | 7/20/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/20/2017 | | 7/20/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 7/14/2017 | | FAIL |
Julie Romig
|
|
|
NEED: Lighting plan per the checklist showing fixture locations as well as switching requirements including daylight area switching.
|
Application received | | | 6/28/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 28 2017 3:19PM
|