Third Notice | | 9/12/2018 | 10/8/2018 | | DONE |
|
|
|
|
Print Statement | | | 10/8/2018 | | DONE |
|
|
|
|
Third Notice | | 8/12/2018 | 9/7/2018 | | DONE |
|
|
|
mailed 9-10-18 sent 2nd letter
|
Third Notice | | 7/16/2018 | 8/7/2018 | | DONE |
|
|
|
mailed 8-10-18 sent letter
|
Third Notice | | 6/16/2018 | 7/11/2018 | | DONE |
|
|
|
mailed 7-12-18
|
Third Notice | | 5/16/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
Second Notice | | 4/20/2018 | 5/11/2018 | | DONE |
|
|
|
mailed 5-14
|
First Notice | | 3/23/2018 | 4/10/2018 | | DONE |
|
|
|
mailed 4-11-18
|
BLD-Final | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | PASS |
Dave Hannah
|
|
|
Dave, this needs finaled now that the shell and core is done so they can have permanent occupancy. Let me know if there are any problems. Thanks, Angie Brosious ###-####.
|
FIRE-Final Inspection | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection complete.
|
Permanent Occupancy | | | 3/13/2018 | | DONE |
|
|
|
|
Temporary Occupancy | 3/5/2018 | 6/3/2018 | 3/5/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason B ok'd ext good for 90 days starting on March 7th, 2018
|
BLD-Aging Inspection | 2/14/2018 | 2/14/2018 | 2/20/2018 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Dave Hannah
|
|
|
WIll Phone #: ###-#### ok for temp occ ok for perm after bldg is signed off and other trades go perm and rest room sinks are finished
|
FIRE-Final Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection for area of work complete, fire alarm inspection for area of work complete, fire extinguishers are mounted with current inspection tags. Final life fire safety complete for area of work. Tenant space will remain in TCO status until core and shell is complete and finaled. Tenant space can be finaled when core and shell is complete and finaled.
|
BLD-Conference | 12/6/2017 | 12/6/2017 | 12/7/2017 | P | DONE |
Dave Hannah
|
|
|
Will Phone #: ###-####
|
Temporary Occupancy | 12/7/2017 | 3/7/2018 | 12/7/2017 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Conference | 12/5/2017 | 12/5/2017 | 12/5/2017 | P | DONE |
Dave Hannah
|
|
|
Will Phone #: ###-####
|
FIRE-Conference | 12/4/2017 | 12/5/2017 | 12/5/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete.
|
BLD-Framing/Rough-in | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Dave Hannah
|
|
|
rick Phone #: ###-####
|
BLD-Framing/Rough-in | 11/8/2017 | 11/9/2017 | 11/17/2017 | A | PEND |
Dave Hannah
|
|
|
Rick Phone #: ###-#### need engineering
|
BLD-Energy code compliance | 11/15/2017 | 11/15/2017 | 11/15/2017 | A | PASS |
Dave Hannah
|
|
|
perimeter insulation // Rick ###-####
|
BLD-Framing/Rough-in | 11/13/2017 | 11/13/2017 | 11/15/2017 | P | PART |
Dave Hannah
|
|
|
Rick Phone #: ###-#### need engineering on beam to beam conections the rest is ok
|
BLD-Energy code compliance | 11/13/2017 | 11/13/2017 | 11/15/2017 | P | CANC |
Dave Hannah
|
|
|
Rick Phone #: ###-####
|
BLD-Other | 11/14/2017 | 11/14/2017 | 11/15/2017 | P | CANC |
Dave Hannah
|
|
|
perimeter insulation // Rick ###-####
|
BLD-Framing/Rough-in | 11/8/2017 | 11/8/2017 | 11/9/2017 | P | PART |
Dave Hannah
|
|
|
Rick Phone #: ###-#### ok to inasulate ext walls need engineer to look at beam to beam connections and beam to coulmn connections
|
BLD-Framing/Rough-in | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | PART |
Dave Hannah
|
|
|
Will Phone #: ###-#### ok to cover upper ceiling area
|
Issue PAID IN FULL permit | | | 9/18/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 9/18/2017 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/11/2017 | | 9/15/2017 | | PASS |
Carl Westfall
|
|
|
Jared Bauder (CH2M Hill)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/15/2017 | | DONE |
|
|
|
Need:Final early start permit Bld17-02617 when this permit is issued
GC Form-MET
Revised cert of value-MET
|
Plan assigned to (CJW) | 7/17/2017 | | 9/15/2017 | | PASS |
Carl Westfall
|
|
|
(3rd done) (Aug 4 - 15 days) (28 sheets) Form and Function
|
Plan resubmittals received | | | 9/11/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/11/2017 | | 9/11/2017 | | PASS |
Carl Westfall
|
|
|
Approved pending structural.
|
Plan resubmittals requested | | | 9/8/2017 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/5/2017 | | 9/7/2017 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (CH2M Hill)
|
Routing - PLAN CHECK | 9/1/2017 | | 9/5/2017 | | PEND |
Carl Westfall
|
|
|
Approved pending structural.
|
Plan resubmittals received | | | 9/1/2017 | | DONE |
|
|
|
Resubmitted on a Friday. Monday was a holiday, Tuesday Sept. 5 the drawings were routed.
|
Route to Impact Fee Review | 8/16/2017 | 8/19/2017 | 8/17/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 8/16/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 8/16/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/17/2017 | | 8/16/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 7/17/2017 | | 7/24/2017 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (CH2M Hill)
|
Routing PW Environmental | 7/17/2017 | | 7/19/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 7/17/2017 | 7/17/2017 | 7/18/2017 | | PASS |
Scott Arellano
|
|
|
Attached review comments to case.
|
Routing - Erosion and Sediment | 7/17/2017 | | 7/18/2017 | | PASS |
Andy J. Long
|
|
|
No ESC permit required. Active permit for entire building under ESC15-00762
|
Routing - PLUMBING | 7/17/2017 | | 7/18/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 7/17/2017 | | 7/18/2017 | | PASS |
Doug Chausow
|
|
|
Address is 511 W Broad Street
|
Routing - PUBLIC WORKS | 7/17/2017 | | 7/17/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 7/17/2017 | | 7/17/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 7/17/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Javier approved per screen CDH applications signed and uploaded by applicant.
|
Intake Approval | | | 7/12/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following:
• Previous request not addressed, Please provide a signed and stamped plan sheet E202 by an Idaho licensed electrical engineer
|
Intake Approval | | | 7/3/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following:
•Please provide a completed Central District Health Food Establishment License application found at this website https://www.cdhd.idaho.gov/eh-food-forms.php
• Please provide a completed Central District Health Approval form found at this website https://www.cdhd.idaho.gov/eh-food-forms.php
• Please provide the missing cover sheet G001 that contains the vicinity map, the key plan, table of contents and the code analysis of the structure.
• Please show portable fire extinguisher locations
• Please provide a completed Form #310 – Statement of Special Inspections completed by the design engineer (form can be found on our website at http://pds.cityofboise.org/home/documents/apps/300/
• Please provide a signed and stamped plan sheet E202 by an Idaho licensed electrical engineer
|
Application received | | | 6/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 29 2017 5:53PM
|