Letter of compliance/Occupancy | | | 4/19/2018 | | DONE |
|
|
|
|
BLD-Final | 3/21/2018 | 3/22/2018 | 3/22/2018 | P | PASS |
Jim Storey
|
|
|
Sam Phone #: ###-####
|
DOC - Permit Finaled | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 1/2/2018 | 1/3/2018 | 1/3/2018 | A | PASS |
Jim Storey
|
|
|
Sam Phone #: ###-####
|
BLD-Framing/Rough-in | 12/27/2017 | 12/27/2017 | 12/27/2017 | P | PART |
Jim Storey
|
|
|
Sam Phone #: ###-#### get timberlock or alt for 3 ply in the grage/ trimers for bearing header at warm wall/ web bracing 2 floor 08
|
BLD-Framing/Rough-in | 12/20/2017 | 12/21/2017 | 12/21/2017 | A | CANC |
Jim Storey
|
|
|
Sam Phone #: ###-####
|
BLD-Wall Bracing | 11/27/2017 | 11/27/2017 | 11/27/2017 | P | PART |
Jim Storey
|
|
|
Sam Phone #: ###-#### c/n ok to cover exterior can see at framing
|
BLD-Wall Bracing | 11/21/2017 | 11/22/2017 | 11/22/2017 | P | NR |
Jim Storey
|
|
|
shear // sam Phone #: ###-#### no plans on site
|
BLD-Footing | 9/12/2017 | 9/13/2017 | 9/13/2017 | P | PASS |
Brandon Shaw
|
|
|
Daryl Phone #: ###-####
|
OVERRIDE | | | 9/5/2017 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/5/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/5/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
1st review completed | | | 8/30/2017 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2017 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 8/28/2017 | | 8/30/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 8/28/2017 | | 8/30/2017 | | PASS |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 7/10/2017 | | 8/30/2017 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 8/29/2017 | | FAIL |
Michael Hanson
|
|
|
Contacted client with list of defciencies 8-29-2017. Missing energy efficiency compliance method
Need additional structural information for window seat.
***MDH***
|
Plan assigned to (BJM) | 7/10/2017 | 7/10/2017 | 8/28/2017 | | DEFR |
Brian McGowan
|
|
|
7/21 sfd Level 1 ePlan
|
Plan Reviewer's activity | | | 8/28/2017 | | DONE |
Michael Hanson
|
|
|
|
Route to Impact Fee Review | 7/10/2017 | 7/13/2017 | 7/14/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/10/2017 | | 7/12/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 7/10/2017 | | 7/11/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2017 | | 7/10/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 7/10/2017 | | 7/10/2017 | | PASS |
Sue Cummings
|
|
|
|
Intake Approval | | | 7/10/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/10/2017 | | DONE |
|
|
|
|
Application received | | | 6/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2017 9:12AM
|
Intake Approval | | | 6/30/2017 | | FAIL |
|
|
|
Need Manual J and plan sheets uploaded individually, named correctly and in Drawings folder
|