Permit Information
Permit NumberBLD17-02178
StatusFinaled
Name DAUBY CONSTRUCTION MGMT
Site Address 1111 W JEFFERSON ST Unit: STE 510
Project NameNorthwestern Mutual TI
Customer Number 
ePlanReviewYes
Description
(Northwestern Mutual TI) Scope of work includes renovation of existing tenant space to include demolition and construction of interior partition walls to create two separate open office areas, two offices, storage room, and enclosed admin area in a different suite of the same tenant. This building is fully fire sprinklered any alteration or modification to the sprinkler system shall be per NFPA#13 as regulated by the fire department. *RmH*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/24/201711/30/2017 DONE
This permit finaled on the web by Justin Dauby
First Notice 11/10/201711/14/2017 DONE
Mailed 11-15-17
BLD-Final10/30/201710/31/201710/31/2017APASS
DetailsDave Hannah
Please call Eric Jensen 1/2-hour prior to inspection to escort for the final, thank you. ###-#### Phone #: ###-#### Inspection requested via web by Justin Dauby
Print Occupancy Form  10/31/2017 DONE
Permanent Occupancy  10/31/2017 DONE
FIRE-Final Inspection10/17/201710/18/201710/18/2017APASS
DetailsJim Page
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher is mounted with a current inspection tag. Final life fire safety inspection for area of work passed/complete.
BLD-Ceiling Grid Inspection9/14/20179/15/20179/15/2017PPASS
DetailsDave Hannah
Mark Phone #: ###-####
BLD-Framing/Rough-in8/22/20178/22/20178/22/2017PPART
DetailsBrandon Shaw
Ok to insulate and cover walls
Inspection Record Card- Bld  8/16/2017 DONE
Issue PAID IN FULL permit  8/16/2017 DONE
Plan assigned to (RMH)8/4/20178/4/20178/4/2017 PASS
DetailsRon Hill
Plan assigned to (JAR)7/7/20177/7/20178/4/2017 DEFR
DetailsJulie Romig
07/20 (08/03) - L2 Northwestern Mutal TI
Defered to Ron Hill
Routing - PLAN CHECK7/7/2017 8/4/2017 PASS
DetailsRon Hill
1st review completed  8/4/2017 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/4/2017 DONE
Permit Ready to Issue  8/4/2017 DONE
need GC and rev cert of val
Routing - Addressing7/7/2017 7/11/2017 PASS
DetailsLaura Hunter
Routing - FIRE7/7/20177/7/20177/7/2017 PASS
DetailsKatie Marron
Separate Fire Permits will be required. Horizontal sliding doors are permitted in rooms serving an occupant load of 10 or less. No report attached.
Intake Approval  7/7/2017 PASS
DetailsAdele J Schaffeld-Griffin
Julie completed pre screen
Routing - PUBLIC WORKS7/7/2017 7/7/2017 PASS
DetailsBeverly Mountain
Application received  6/30/2017 DONE
Application submitted via PDS Online on Jun 30 2017 9:48AM