Second Notice | | 11/24/2017 | 11/30/2017 | | DONE |
|
|
|
This permit finaled on the web by Justin Dauby
|
First Notice | | 11/10/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
BLD-Final | 10/30/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Dave Hannah
|
|
|
Please call Eric Jensen 1/2-hour prior to inspection to escort for the final, thank you. ###-#### Phone #: ###-#### Inspection requested via web by Justin Dauby
|
Print Occupancy Form | | | 10/31/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/31/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/17/2017 | 10/18/2017 | 10/18/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher is mounted with a current inspection tag. Final life fire safety inspection for area of work passed/complete.
|
BLD-Ceiling Grid Inspection | 9/14/2017 | 9/15/2017 | 9/15/2017 | P | PASS |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 8/22/2017 | 8/22/2017 | 8/22/2017 | P | PART |
Brandon Shaw
|
|
|
Ok to insulate and cover walls
|
Inspection Record Card- Bld | | | 8/16/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/16/2017 | | DONE |
|
|
|
|
Plan assigned to (RMH) | 8/4/2017 | 8/4/2017 | 8/4/2017 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (JAR) | 7/7/2017 | 7/7/2017 | 8/4/2017 | | DEFR |
Julie Romig
|
|
|
07/20 (08/03) - L2 Northwestern Mutal TI
Defered to Ron Hill
|
Routing - PLAN CHECK | 7/7/2017 | | 8/4/2017 | | PASS |
Ron Hill
|
|
|
|
1st review completed | | | 8/4/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/4/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/4/2017 | | DONE |
|
|
|
need GC and rev cert of val
|
Routing - Addressing | 7/7/2017 | | 7/11/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - FIRE | 7/7/2017 | 7/7/2017 | 7/7/2017 | | PASS |
Katie Marron
|
|
|
Separate Fire Permits will be required. Horizontal sliding doors are permitted in rooms serving an occupant load of 10 or less. No report attached.
|
Intake Approval | | | 7/7/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie completed pre screen
|
Routing - PUBLIC WORKS | 7/7/2017 | | 7/7/2017 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 6/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2017 9:48AM
|