Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-02187
StatusFinaled
Name KC GARDNER RIVERWOODS LC
Site Address 101 S CAPITOL BLVD Unit: STE 800
Project NamePCA 8th floor
Customer NumberBLD17-02612
ePlanReviewYes
Description
(PCA)(US BANK BUILDING)(8THFLOOR) This building is sprinklered to comply with high-rise requirements. Permit for tenant improvement design for PCA in the US Bank Building on the entire 8th floor 14,600 sq ft. Scope of work to include interior nonbearing demolition and framing of new floor plan per approved drawings. New mechanical, electrical and plumbing shall be permitted separately. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  2/22/2018 DONE
First Notice 1/20/20182/12/2018 DONE
mailed 2-13-18
Permanent Occupancy  1/10/2018 DONE
BLD-Final1/9/20181/9/20181/9/2018PPASS
DetailsDave Hannah
Larren Novak Phone #: ###-####
BLD-Final12/29/201712/29/201712/29/2017PNR
DetailsDave Hannah
Larren Phone #: ###-####
FIRE-Final Inspection12/27/201712/28/201712/28/2017PPASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
FIRE-Final Inspection12/18/201712/19/201712/19/2017ACANC
DetailsJim Page
Fire sprinkler inspection failed, life fire safety inspection cancelled.
BLD-Framing/Rough-in9/28/20179/28/20179/29/2017PPART
DetailsBrandon Shaw
OK to cover
Place hold on job9/8/2017 9/12/2017 DONE
DetailsCandy A. Nichols
must issue Bld17-02187 & 02612 together
Permit Ready to Issue  9/12/2017 DONE
Print Occupancy Form  9/12/2017 DONE
Issue PAID IN FULL permit  9/12/2017 DONE
Plan assigned to (AJS)8/11/20178/11/20179/8/2017 PASS
DetailsAdele J Schaffeld-Griffin
8/18 L2 PCA 8th and 9th floor ePlan
Routing - PLAN CHECK9/8/2017 9/8/2017 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  9/8/2017 DONE
Permit Ready to Issue  9/8/2017 DONE
DO NOT ISSUE WITHOUT Bld17-02612
CHANGE STATUS TO (FEE)  9/8/2017  
Route to Impact Fee Review8/28/20178/31/20178/30/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  8/28/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK8/7/2017 8/28/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Plan assigned to (JG)8/7/20178/7/20178/11/2017 DEFR
DetailsJavier Guzman
8/18 L2 PCA 8th and 9th floor ePlan
Routing - PUBLIC WORKS8/7/2017 8/8/2017 PASS
DetailsRachael Beierle
Routing - Addressing8/7/2017 8/8/2017 PASS
DetailsDoug Chausow
Ste 800
Routing - MECHANICAL8/7/2017 8/7/2017 PASS
DetailsTroy James
Routing - PLUMBING8/7/2017 8/7/2017 PASS
DetailsDaryl Spivey
Intake Approval  8/7/2017 PASS
DetailsJavier Guzman
Intake Approval  7/31/2017 FAIL
DetailsJulie Romig
To complete your application, please provide the following:

1. Door and window schedule missing - indicated on checklist as sheet A631 but not uploaded.
2. Lighting COMcheck missing - indicated on checklist as Sheets E210 and E211, but not uploaded.
3. Mechanical COMcheck missing - indicated on checklist as Sheets M001, M210, M211, but not uploaded.
Intake Approval  7/27/2017 FAIL
DetailsJulie Romig
1. Door and window schedule missing - indicated on checklist as sheet A631 but not uploaded.
2. Lighting COMcheck missing - indicated on checklist as Sheets E210 and E211, but not uploaded.
3. Mechanical COMcheck missing - indicated on checklist as Sheets M001, M210, M211, but not uploaded.
Application received  6/30/2017 DONE
Application submitted via PDS Online on Jun 30 2017 12:11PM