BLD-Final | 11/8/2018 | 11/9/2018 | 11/8/2018 | A | PASS |
Tony Young
|
|
|
Call PJ Smith 208 559 0588 I''ll meet Tony Young at property! Inspection requested via web by PJ Smith
|
DOC - Permit Finaled | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 11/7/2018 | 11/8/2018 | 11/8/2018 | P | CANC |
Tony Young
|
|
|
Call PJ Smith with time 208 559 0588 Phone #: ###-#### >> Inspection requested via web by PJ Smith Inspection cancelled from web by: PJ Smith
|
PubWorks Occupancy Approval | 11/5/2018 | 11/5/2018 | 11/5/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 10/19/2018 | 10/22/2018 | 10/22/2018 | P | NR |
Tony Young
|
|
|
Call PJ Smith 208 559 0588 He will meet inspector at house
Have a great week! Phone #: ###-#### Inspection requested via web by PJ Smith,, walk through only,, needs hillside public works,, fire caulking,, ele. final
|
BLD-Aging Inspection | 9/5/2018 | 9/5/2018 | 9/7/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 9/4/2018 | 9/4/2018 | 9/5/2018 | | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 4/23/2018 | 4/23/2018 | 4/23/2018 | P | PASS |
Tony Young
|
|
|
Interior insulate done ready to cover- Call PJ Smith w questions. 208 559 0588 Have a great week! Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Wall cover | 4/23/2018 | 4/23/2018 | 4/23/2018 | P | CANC |
Tony Young
|
|
|
Insulation in ready for cover- Call PJ Smith 208 559 0588 w questions Have a great week! Phone #: ###-#### >> Inspection requested via web by PJ Smith Inspection cancelled from web by: PJ Smith
|
BLD-Wall cover | 4/17/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Tony Young
|
|
|
This is for a Soffit / fire code compliance - Call PJ Smith w questions 208 559 0588 Have a great week! Inspection requested via web by PJ Smith
|
BLD-Framing/Rough-in | 4/17/2018 | 4/18/2018 | 4/18/2018 | A | PASS |
Tony Young
|
|
|
Call PJ Smith w questions 208 559 0588 Have a great week! Inspection requested via web by PJ Smith,, ok to insulate
|
BLD-Conference | 4/16/2018 | 4/17/2018 | 4/17/2018 | A | PART |
Tony Young
|
|
|
This is for a Sophet / fire code compliance - Call PJ Smith w questions 208 559 0588 Have a great week! Inspection requested via web by PJ Smith,, soffit work in progress,, need vents
|
BLD-Framing/Rough-in | 4/13/2018 | 4/13/2018 | 4/13/2018 | P | PART |
Tony Young
|
|
|
Asking for a framing "conference" at job sight.... PJ Smith 208 559 0588 Phone #: ###-#### Inspection requested via web by PJ Smith,, walk through,, needs trades,, seal pack,, see paint
|
BLD-Framing/Rough-in | 4/12/2018 | 4/13/2018 | 4/13/2018 | A | DEFR |
Tony Young
|
|
|
Asking for a framing "conference" at job sight.... PJ Smith 208 559 0588 Phone #: ###-#### Inspection requested via web by PJ Smith,, out of time,, move to pm,,
|
BLD-Wall Bracing | 3/26/2018 | 3/27/2018 | 3/27/2018 | A | PASS |
Tony Young
|
|
|
Call PJ Smith w question 208 559 0588 Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Foundation | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Dave Hannah
|
|
|
Please call ahead for access - Eric Phone #: ###-####
|
BLD-Foundation | 1/2/2018 | 1/3/2018 | 1/3/2018 | P | NR |
Tony Young
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 12/27/2017 | 12/27/2017 | 12/27/2017 | P | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####. Please call when completed to let know if ok.
|
BLD-Footing | 12/26/2017 | 12/27/2017 | 12/27/2017 | A | NR |
Mike Jordan
|
|
|
Eric Phone #: ###-####. rescheduled for this afternoon.
|
PubWorks Subgrade Approval | 12/27/2017 | 12/27/2017 | 12/27/2017 | | DONE |
Jason C. Taylor
|
|
|
**Upper -Mid, and Lower Levels***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 12/22/2017 | 12/26/2017 | 12/26/2017 | A | CANC |
Tony Young
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 12/20/2017 | 12/22/2017 | 12/22/2017 | A | NR |
Tony Young
|
|
|
Eric Phone #: ###-####,, need soils report
|
BLD-Foundation | 12/6/2017 | 12/7/2017 | 12/8/2017 | P | PART |
Dave Hannah
|
|
|
Eric Phone #: ###-#### basement foundation ok
|
BLD-Footing | 12/1/2017 | 12/4/2017 | 12/4/2017 | P | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, lower basement area ok
|
PubWorks Subgrade Approval | 11/29/2017 | 11/29/2017 | 11/29/2017 | | DONE |
Jason C. Taylor
|
|
|
***BASEMENT AND LOWER LEVEL ONLY****A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 11/3/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/13/2017 | | |
|
|
|
|
Telephone call | | | 10/13/2017 | | DONE |
|
|
|
called Phillip to let know permit is ready and how much is owed
|
Inspection Record Card- Bld | | | 10/13/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2017 | | DONE |
|
|
|
all met
|
Plan assigned to (BJM) | 7/19/2017 | 7/19/2017 | 10/12/2017 | | DONE |
Brian McGowan
|
|
|
8/04 sfd Level 2 paper - sent back through PW, ESC
|
Routing - PLAN CHECK | 7/25/2017 | | 10/12/2017 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 10/12/2017 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 10/12/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - FIRE | 10/3/2017 | 10/3/2017 | 10/4/2017 | | PASS |
Scott Arellano
|
|
|
No change
|
Routing - FIRE | 10/4/2017 | 7/19/2017 | 10/4/2017 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - Erosion and Sediment | 10/2/2017 | | 10/3/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan with site map approved. Valid PD and RP. Site preparation inspection is required.
|
Routing - PLANNING | 10/2/2017 | | 10/2/2017 | | PASS |
Sue Cummings
|
|
|
No chage to setbacks. Called the applicant to make sure he understood. Redlined again
|
Routing PW Grading-Hillside | 9/25/2017 | | 10/2/2017 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PUBLIC WORKS | 10/2/2017 | | 10/2/2017 | | PASS |
Morgan Webb
|
|
|
|
Plan resubmittals received | | | 8/9/2017 | | DONE |
|
|
|
Three copies of full set of plans 13 sheets. Taken to Brian Mc
|
Routing - MECHANICAL | 7/24/2017 | | 7/26/2017 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 7/25/2017 | | DONE |
|
|
|
Three copies of sheets 1. taken to Brian Mc
|
Routing - PLANNING | 7/24/2017 | | 7/24/2017 | | PASS |
Sue Cummings
|
|
|
See redlines. Needs 10 ft. side setback at south side of home.
|
Routing - PUBLIC WORKS | 7/24/2017 | | 7/24/2017 | | FAIL |
Rachael Beierle
|
|
|
failed hillside.
|
Routing PW Grading-Hillside | 7/20/2017 | | 7/24/2017 | | FAIL |
Jason C. Taylor
|
|
|
No grading plans were submitted with this packet. Please submit 3 full size sheets of the grading plan to the PDS counter for review by PW. Jason Taylor
|
Route to Impact Fee Review | 7/19/2017 | 7/22/2017 | 7/21/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Sewer Rating | 7/20/2017 | | 7/20/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/19/2017 | | DONE |
|
|
|
|
Intake Approval | | | 7/19/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/19/2017 | | DONE |
|
|
|
|
Routing - Addressing | 7/19/2017 | | 7/19/2017 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 7/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 5 2017 1:14PM
|