Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD17-02285
StatusFinaled
Name VERTICAL CORP
Site Address 816 W BANNOCK ST
Project NameGarro/Carrolls Bldg Remodel
Customer Number 
ePlanReviewYes
Description
(GARRO/CARROLLS BUILDING - SHELL AND CORE REMODEL) **This building is sprinklered to allow 5th floor. Permit is for improvements to the shell and core of an existing historic building. Work to include: painting exterior of building, construction of new solid canopy on Bannock Street; demolition of stair connecting 1st floor and basement, remodel of 1st floor exterior entry; new office tenant exterior entry; demolition of interior non-bearing partitions in 1st floor and basement tenant spaces; remodeled electrical, mechanical, and plumbing; and new interior finishes on all floors. Interior finishes in compliance with chapter 8 of the 2012 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. NO OCCUPANCY TO REMODELED TENANT SPACES IS ALLOWED UNDER THIS PERMIT. RELOCTED/FUTURE TENANTS SHALL APPLY FOR PERMIT PRIOR TO OCCUPYING THE SPACE. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  9/7/2018 DONE
BLD-Final5/9/20185/10/20185/10/2018APASS
DetailsDave Hannah
Travis Phone #: ###-####
FIRE-Final Inspection5/9/20185/10/20185/10/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.

Travis Phone #: ###-####
Letter of compliance/Occupancy  5/10/2018 DONE
BLD-Aging Inspection4/27/20184/27/20185/1/2018 PEND
DetailsDave Hannah
BLD-Ceiling Grid Inspection3/9/20183/9/20183/9/2018PPASS
DetailsJim Sly
Please call Travis regarding partial ceiling grid inspection. Phone #: ###-#### Inspection requested via web by Todd Weltner
BLD-Framing/Rough-in12/5/201712/5/201712/14/2017PPASS
DetailsDave Hannah
Travis Phone #: ###-####
Issue PAID IN FULL permit  11/6/2017 DONE
Inspection Record Card- Bld  11/6/2017 DONE
Plan assigned to (JAR)7/12/20177/12/201710/30/2017 DONE
DetailsJulie Romig
**1st Rev Comp - 3rd Rec'd 10/26 - L3 Garro Building
Routing - Design Review10/27/2017 10/30/2017 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK10/30/2017 10/30/2017 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  10/30/2017 DONE
Permit Ready to Issue  10/30/2017 DONE
Need
GC - Met
Rev cert of val - Met
Routing - PLAN CHECK10/26/2017 10/27/2017 FAIL
DetailsJulie Romig
Routing - PLAN CHECK9/14/2017 9/22/2017 FAIL
DetailsJulie Romig
Corrections Required per ePlanReview.
Route to Impact Fee Review8/31/20179/3/20179/1/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - Design Review7/12/2017 9/1/2017 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK7/12/2017 8/31/2017 FAIL
DetailsJulie Romig
1st review completed  8/31/2017 DONE
DetailsJulie Romig
Routing - FIRE7/12/20177/12/20177/13/2017 PASS
DetailsKatie Marron
Comments attached to case.
Routing - Erosion and Sediment7/12/2017 7/13/2017 PASS
DetailsAndy J. Long
No ESC permit required. Minimal earth disturbance
Routing - Addressing7/12/2017 7/13/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS7/12/2017 7/12/2017 PASS
DetailsBeverly Mountain
Plan Reviewer's activity  7/12/2017 DONE
Spoke with architect, Lindsay Erb. Owner has made change to project and she has sheets to change out. Told her to work with the Plans Examiner assigned to the project regarding changes. Application is for building shell/core, she will be submitting separate application for tenant.
Intake Approval  7/12/2017 PASS
DetailsAdele J Schaffeld-Griffin
Julie approved pre screen
Intake Approval  7/10/2017 FAIL
DetailsJulie Romig
Need:
1. Structural calcs for exterior canopy.
2. Lighting COMcheck for new lighting.
Application received  7/7/2017 DONE
Application submitted via PDS Online on Jul 7 2017 3:16PM