DOC - Permit Finaled | | | 9/7/2018 | | DONE |
|
|
|
|
BLD-Final | 5/9/2018 | 5/10/2018 | 5/10/2018 | A | PASS |
Dave Hannah
|
|
|
Travis Phone #: ###-####
|
FIRE-Final Inspection | 5/9/2018 | 5/10/2018 | 5/10/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
Travis Phone #: ###-####
|
Letter of compliance/Occupancy | | | 5/10/2018 | | DONE |
|
|
|
|
BLD-Aging Inspection | 4/27/2018 | 4/27/2018 | 5/1/2018 | | PEND |
Dave Hannah
|
|
|
|
BLD-Ceiling Grid Inspection | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Jim Sly
|
|
|
Please call Travis regarding partial ceiling grid inspection. Phone #: ###-#### Inspection requested via web by Todd Weltner
|
BLD-Framing/Rough-in | 12/5/2017 | 12/5/2017 | 12/14/2017 | P | PASS |
Dave Hannah
|
|
|
Travis Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/6/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/6/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/12/2017 | 7/12/2017 | 10/30/2017 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 3rd Rec'd 10/26 - L3 Garro Building
|
Routing - Design Review | 10/27/2017 | | 10/30/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 10/30/2017 | | 10/30/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/30/2017 | | DONE |
|
|
|
Need
GC - Met
Rev cert of val - Met
|
Routing - PLAN CHECK | 10/26/2017 | | 10/27/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/14/2017 | | 9/22/2017 | | FAIL |
Julie Romig
|
|
|
Corrections Required per ePlanReview.
|
Route to Impact Fee Review | 8/31/2017 | 9/3/2017 | 9/1/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - Design Review | 7/12/2017 | | 9/1/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 7/12/2017 | | 8/31/2017 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 8/31/2017 | | DONE |
Julie Romig
|
|
|
|
Routing - FIRE | 7/12/2017 | 7/12/2017 | 7/13/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - Erosion and Sediment | 7/12/2017 | | 7/13/2017 | | PASS |
Andy J. Long
|
|
|
No ESC permit required. Minimal earth disturbance
|
Routing - Addressing | 7/12/2017 | | 7/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/12/2017 | | 7/12/2017 | | PASS |
Beverly Mountain
|
|
|
|
Plan Reviewer's activity | | | 7/12/2017 | | DONE |
|
|
|
Spoke with architect, Lindsay Erb. Owner has made change to project and she has sheets to change out. Told her to work with the Plans Examiner assigned to the project regarding changes. Application is for building shell/core, she will be submitting separate application for tenant.
|
Intake Approval | | | 7/12/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie approved pre screen
|
Intake Approval | | | 7/10/2017 | | FAIL |
Julie Romig
|
|
|
Need:
1. Structural calcs for exterior canopy.
2. Lighting COMcheck for new lighting.
|
Application received | | | 7/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 7 2017 3:16PM
|