BLD-Framing/Rough-in | 6/25/2020 | 6/26/2020 | 6/26/2020 | P | PART |
Tony Young
|
|
|
screened // David Phone #: ###-####// ok to cover upstairs closet area
|
BLD-Framing/Rough-in | 5/19/2020 | 5/22/2020 | 5/22/2020 | A | PART |
Tony Young
|
|
|
homeowner - screened // David Phone #: ###-####// new stair area ok pending electrical pass
|
BLD-Conference | 12/5/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Tony Young
|
|
|
I would like to have a conference to update the progress and get the project and permit back on track. The last conference was just before putting up the drywall in the bathroom. I am now working on the stairwell/hall area and would like have a quick review of this aspect of the project. Thanks. Phone #: ###-#### Inspection requested via web by David Snyderman// working on stair area now,, ok
|
Routing Walk-In (BLD) | 7/12/2019 | 7/12/2019 | 7/12/2019 | A | FAIL |
Josh Bogle
|
|
|
person left prior to review
|
BLD-Aging Inspection | 3/8/2019 | 3/8/2019 | 3/13/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 10/25/2018 | 10/25/2018 | 10/26/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 10/24/2018 | 10/24/2018 | 10/25/2018 | | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/18/2018 | 7/19/2018 | 7/19/2018 | P | NR |
Tony Young
|
|
|
Possible a final (?) plumbing inspection. Phone #: ###-#### Inspection requested via web by David Snyderman,, conf only,, wanted a plumbing inspection,, called the office and set it up for him..
|
BLD-Aging Inspection | 6/11/2018 | 6/11/2018 | 6/12/2018 | | PASS |
Tony Young
|
|
|
|
BLD-Conference | 5/21/2018 | 5/22/2018 | 5/22/2018 | A | PART |
Tony Young
|
|
|
I would like a consult on my partially done framing for my basement bathroom renovation. Thanks Phone #: ###-#### Inspection requested via web by David Snyderman,, walk through on framing,, ok so far on the bathroom area
|
BLD-Framing/Rough-in | 3/14/2018 | 3/16/2018 | 3/17/2018 | P | NR |
Dave Hannah
|
|
|
I need a quick consult on framing and header needed for a pocket door for my basement bathroom renovation. The best time to meet would be from 12:30 - 5 pm if possible as I work in the morning and it is difficult to get off before noon. Thank you. Phone #: ###-#### Inspection requested via web by David Snyderman
|
BLD-Conference | 2/22/2018 | 2/23/2018 | 2/24/2018 | P | DEFR |
Tony Young
|
|
|
Plumbing inspection for revamped shower drainage and vent system.
note: 12:30-5 pm please as I may not be able to make it home from work before 12:30 pm. Thanks. Phone #: ###-#### Inspection requested via web by David Snyderman
|
BLD-Conference | 1/17/2018 | 1/19/2018 | 1/22/2018 | P | DONE |
Tony Young
|
|
|
I would like to have the plumbing inspector come and review my plumbing set up for the new shower drain, vent and pump.
Note: I will be at the house/job site from 1 pm on (1 - 5 pm). Unfortunately I work in the morning and will not be available. Thanks. Phone #: ###-#### Inspection requested via web by David Snyderman
|
BLD-Framing/Rough-in | 10/25/2017 | 10/27/2017 | 10/27/2017 | A | NR |
Tony Young
|
|
|
I have some framing questions and would like a consult before work is done.
Please call me before arriving if possible as I need to run one errand in the morning and will be away from the site for about 45 minutes. Phone #: ###-#### Inspection requested via web by David Snyderman,,, ?s on frame only
|
Issue PAID IN FULL permit | | | 7/26/2017 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 7/24/2017 | 7/24/2017 | 7/24/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 7/24/2017 | | 7/24/2017 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 7/24/2017 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 7/24/2017 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 7/24/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/24/2017 | | DONE |
|
|
|
|
Telephone call | | | 7/24/2017 | | DONE |
|
|
|
called David and left message permit is ready and fee due
|
Routing Walk-In (BLD) | 7/21/2017 | 7/21/2017 | 7/21/2017 | P | PASS |
Brian McGowan
|
|
|
Took in plans, I could not finish the permit before our meeting. BJM
|
Routing Walk-In (BLD) | 7/7/2017 | 7/7/2017 | 7/7/2017 | P | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 7/7/2017 | | FAIL |
Josh Bogle
|
|
|
applicant needed structural & dimension details JAB
|
Routing - PLAN CHECK | 7/7/2017 | | 7/7/2017 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 7/7/2017 | | | |
|
|
|
|