Permit Information
Permit NumberBLD17-02294
StatusFinaled
Name ESI
Site Address 13681 W CHINDEN BLVD
Project NameStarbucks Building Shell
Customer Number 
ePlanReviewYes
Description
(STARBUCKS – BUILDING SHELL) (CUP17-00031) (DRH17-00280) (2-28-18 PLAN MODIFICATION TO REVISE THE DRAWINGS TO SHOW THE ACTUAL FINAL CONDITIONS. WORK INCLUDES SOME STRUCTURAL CHANGES AND ROOF TOP EQUIPMENT.) This building does not have a fire sprinkler system. To construct a new 2,437 square foot restaurant building shell (about 1,895 square feet within the thermal envelope) with a drive through. The floor area includes the covered patio and the covered HVAC equipment area but not the roof eaves. The projected roof area is about 3,113 square feet. The tenant improvement work will be done under permit BLD17-02900. This shell permit is not intended to establish a Certificate of Occupancy for any portion of the building. Work is to include concrete footings, concrete foundations, concrete slab on grade, steel columns, steel beams, wood headers, masonry walls, wood stud walls, wood shear walls with hold downs, engineered wood roof trusses, wood roof sheathing, exterior windows, exterior doors, exterior wall finishes, roof insulation installed on top of the roof deck, and a roof covering. A masonry trash enclosure with steel gates and a drive through pergola will also be constructed. Special Inspection is required for soils, concrete, anchors post-installed in hardened concrete and masonry, hold down anchors for shear walls, seismic resistance, bolting, welding, masonry, and EIFS. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  4/3/2018 DONE
DetailsChristina Prado
per all passing inspections
Letter of compliance/Occupancy  4/3/2018 DONE
PubWorks Occupancy Approval4/2/20184/2/20184/2/2018 DONE
DetailsTiffany Lowery
CHANGE STATUS TO (ISS)  3/26/2018 DONE
CHANGE STATUS TO (ISS)  3/26/2018 DONE
Zoning Approval3/20/20183/20/20183/20/2018 DONE
DetailsAndrea Tuning
OVERRIDE  2/28/2018  
Plan assigned to (CJW)2/20/20182/20/20182/28/2018 PASS
DetailsCarl Westfall
x plan mod
PLANS/APPL TAKEN TO FRONT DESK  2/28/2018 DONE
Permit Ready to Issue  2/28/2018  
PLEASE DO NOT RE ISSUE
Routing Off Site - STRUCTURAL2/26/2018 2/27/2018 PASS
DetailsCarl Westfall
Ashley Thompson (KPFF)
Routing - Design Review2/26/2018 2/27/2018 PASS
DetailsAndrea Tuning
Routing - PLUMBING2/26/2018 2/27/2018 PASS
DetailsBill VanDegrift
BLD-Final2/26/20182/27/20182/26/2018APASS
DetailsJim Sly
Tim Phone #: ###-####
Shell/core Final OK.
Zoning Approval Temp2/26/20182/26/20182/26/2018 DONE
DetailsAndrea Tuning
Routing - PLAN CHECK2/20/2018 2/26/2018 PASS
DetailsCarl Westfall
Pending structural
BLD-Conference2/22/20182/22/20182/23/2018PDONE
DetailsJim Sly
Tim Phone #: ###-####
FIRE-Final Inspection2/21/20182/22/20182/22/2018APASS
DetailsTroy Cobbley
Life safety passed

Tim Phone #: ###-####
Plan Modification Accepted  2/20/2018 DONE
DetailsChristina Prado
Plan Mod for misc updates - east wall framing, drive thru pergola, mechanical equipment clarification, roof penetration, remove floor sink and update electrical panel
BLD-Footing2/15/20182/16/20182/16/2018APART
DetailsJim Sly
Tim Phone #: ###-####
Pergola footings......Terracon special inspection.
BLD-Conference1/18/20181/19/20181/19/2018ADONE
DetailsJim Sly
Tim Phone #: ###-####
BLD-Energy code compliance12/28/201712/29/201712/29/2017APASS
DetailsJim Sly
Tim Phone #: ###-####
BLD-Framing/Rough-in12/27/201712/27/201712/27/2017PPASS
DetailsJim Sly
Tim Phone #: ###-####
BLD-Framing/Rough-in12/12/201712/13/201712/13/2017PPART
DetailsJim Sly
Tim Phone #: ###-####
Exterior Shear nailing only....OK.
BLD-Footing11/8/201711/9/201711/9/2017APEND
DetailsJim Sly
Tim Phone #: ###-####
Many clearance issues......Terricon on site. OK pending Terricon special inspection, tests and approvals.
BLD-Footing11/8/201711/8/201711/8/2017PPART
DetailsJim Storey
Tim Phone #: ###-#### ufer ground in place/ si taracon need min bar clearance.
Issue PAID IN FULL permit  11/6/2017 DONE
Inspection Record Card- Bld  11/6/2017 DONE
OVERRIDE  10/26/2017  
Plan assigned to (CJW)8/9/20178/9/201710/26/2017 PASS
DetailsCarl Westfall
(3rd done) (Sept 11 - 25 days) (35 sheets) Starbucks Shell
PLANS/APPL TAKEN TO FRONT DESK  10/26/2017 DONE
Permit Ready to Issue  10/26/2017 DONE
Need
RP- Met
Routing Off Site - STRUCTURAL10/19/2017 10/25/2017 PASS
DetailsCarl Westfall
Ashley Thompson (KPFF)
Routing - Design Review10/19/2017 10/19/2017 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK10/18/2017 10/19/2017 PASS
DetailsCarl Westfall
Pending structural
Plan resubmittals received  10/18/2017 DONE
Plan resubmittals requested  10/9/2017 DONE
Routing Off Site - STRUCTURAL10/2/2017 10/9/2017 FAIL
DetailsCarl Westfall
Ashley Thompson (KPFF)
Routing - Design Review10/2/2017 10/5/2017 FAIL
DetailsAndrea Tuning
Routing PW Sewer Design10/2/2017 10/5/2017 PASS
DetailsKyle S. Rosenmeyer
Approved under GRD17-00040.
Routing - PLUMBING10/2/2017 10/3/2017 PASS
DetailsDaryl Spivey
per plans and ISPC
Routing - MECHANICAL10/2/2017 10/2/2017 PASS
DetailsChad Schwendiman
Routing - PLAN CHECK9/29/2017 10/2/2017 PASS
DetailsCarl Westfall
pending structural
Plan resubmittals received  9/29/2017 DONE
Route to Impact Fee Review9/20/20179/23/20179/22/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  9/20/2017 DONE
Plan resubmittals requested  9/20/2017 DONE
Routing - PLAN CHECK8/9/2017 9/20/2017 FAIL
DetailsCarl Westfall
Routing PW Environmental8/10/2017 9/15/2017 PASS
DetailsRick Christenson
Per 1500 Gallon Exterior Grease Interceptor
Routing - FIRE8/9/20178/9/20178/23/2017 PASS
DetailsScott Arellano
Attached comments to plans.
Routing Off Site - STRUCTURAL8/9/2017 8/23/2017 FAIL
DetailsCarl Westfall
Ashley Thompson (KPFF)
Routing - Addressing8/9/2017 8/21/2017 PASS
DetailsDoug Chausow
Corrected address to 13681 W Chinden Blvd
Routing PW Solid Waste8/10/2017 8/21/2017 PASS
DetailsEvan Carpenter
Solid waste enclosure must be built according to the site plan (C3) and not the architectural site plan (A1.0). The enclosure on A1.0 does not allow for adequate collection vehicle access.
Routing PW Street Lights8/10/2017 8/16/2017 PASS
DetailsTom Marshall
Routing - Erosion and Sediment8/14/2017 8/14/2017 PASS
DetailsAndy J. Long
ESC project narrative approved. Vertical Construction will need to provide valid RP.
Routing PW Sewer Design8/10/2017 8/10/2017 FAIL
DetailsKyle S. Rosenmeyer
Show connection to public sewer.
Routing - PUBLIC WORKS8/9/2017 8/10/2017 PASS
DetailsRachael Beierle
Routing PW Drainage8/10/2017 8/10/2017 PASS
DetailsBrian Murphy
PAD ENGINEER LETTER
Routing - MECHANICAL8/9/2017 8/10/2017 FAIL
DetailsTroy James
Need to provide mechanical com check
Routing - PLUMBING8/9/2017 8/10/2017 PASS
DetailsBill VanDegrift
See redline notes
Per plan and ISPC.
Routing - PLANNING8/9/2017 8/10/2017 PASS
DetailsBrent Moore
Routing - PLANNING Land Div8/9/2017 8/10/2017 PASS
DetailsTodd Tucker
Routing - Design Review8/9/2017 8/9/2017 FAIL
DetailsAndrea Tuning
The site plan and landscape plan will be required to match one another.
Install a landscape planter island in the western row of parking that is a minimum of 8-feet in width (interior dimensions) and includes the required Class II or Class III tree with low shrubs or other vegetative groundcover.
c. Provide a minimum of 17 parking spaces on the site.
d. Provide a total of 2 bicycle parking spaces. The spaces shall be conveniently located, a minimum of 6 feet long and 2.5 feet wide, have an overhead clearance of 7 feet, provide a 4 foot wide aisle is required between rows of bicycle parking spaces and installed on a non-permeable surfaces and anchored to the ground.
Comply with the requirements of the Public Works Division in regard to the size and location of the trash enclosure.
Install weather protection that is a minimum of 3-feet in depth on the south and east elevations.
Install a dense landscaping to screen the entire north facing façade.
Intake Approval  8/9/2017 PASS
Plan Reviewer's activity  8/8/2017 PASS
The applicant finished his task on August 3 (Thursday). Carl J. Westfall was on vacation on August 2, 3, and 4 but worked on August 5 (Saturday). ePlanReview was unavailable to route drawings because of an upgraded. The plan intake review was approved on Tuesday, August 8.
Intake Approval  7/28/2017 FAIL
(7-28-17) Please upload the heating and cooling load calculations and the ESC narrative. CJW
Intake Approval  7/26/2017 FAIL
(7-26-17) Please upload those documents into GRD17-00040 that are noted as being provided under that permit. Please provide the other items circled in the plan intake checklist that are not part of GRD17-00040. If you have questions, call me. CJW
Intake Approval  7/12/2017 FAIL
Please complete and sign the Plan Intake Checklist Form 502. Please provide the items that have been circled in that checklist. Note that the file names for the drawings uploaded in ePlanReview were changed to reflect the ePlanReview standards adopted by the City of Boise. CJW
Application received  7/10/2017 DONE
Application submitted via PDS Online on Jul 10 2017 8:03AM