BLD-Final | 11/15/2017 | 11/16/2017 | 11/16/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Latter
|
DOC - Permit Finaled | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 8/24/2017 | 8/25/2017 | 8/26/2017 | P | PASS |
Tony Young
|
|
|
Request to cover post electrical, plumbing, and mechanical inspections pass Phone #: ###-#### Inspection requested via web by Michele Latter
|
BLD-Conference | 8/18/2017 | 8/24/2017 | 8/24/2017 | P | PASS |
Tony Young
|
|
|
Request to cover post electrical, plumbing, and mechanical inspections pass Phone #: ###-#### Inspection requested via web by Michele Latter
|
Routing Walk-In (BLD) | 7/11/2017 | 7/11/2017 | 7/11/2017 | P | DONE |
Josh Bogle
|
|
|
|
1st review completed | | | 7/11/2017 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/11/2017 | | 7/11/2017 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 7/11/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 7/11/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 7/11/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/11/2017 | | DONE |
|
|
|
|
Application received | | 7/11/2017 | | | |
|
|
|
|