BLD-Final | 3/30/2018 | 3/30/2018 | 3/30/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 3/30/2018 | 3/30/2018 | 3/30/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen Inspection cancelled from web by: Braxton Hansen
|
BLD-Wall cover | 11/22/2017 | 11/24/2017 | 11/24/2017 | A | PASS |
Brandon Shaw
|
|
|
Exterior soffit can light Inspection
|
BLD-Energy code compliance | 11/21/2017 | 11/22/2017 | 11/22/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 11/21/2017 | 11/22/2017 | 11/22/2017 | P | PASS |
Brandon Shaw
|
|
|
Corrections sat.
|
BLD-Framing/Rough-in | 11/17/2017 | 11/20/2017 | 11/20/2017 | A | FAIL |
Brandon Shaw
|
|
|
See correction notice
OK to insulate
|
BLD-Wall Bracing | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | PASS |
Brandon Shaw
|
|
|
Braxton Phone #: ###-####
|
BLD-Foundation | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Brandon Shaw
|
|
|
Doug Phone #: ###-####
|
BLD-Footing | 9/20/2017 | 9/21/2017 | 9/21/2017 | A | PEND |
Brandon Shaw
|
|
|
Compaction test required, built up corner front right side of house OK to pour pending MTI
|
BLD-Footing | 9/20/2017 | 9/20/2017 | 9/20/2017 | P | CANC |
Brandon Shaw
|
|
|
DOug Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/8/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/8/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/5/2017 | | |
|
|
|
|
1st review completed | | | 9/5/2017 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 9/5/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan assigned to (M_H) | 8/31/2017 | | 9/5/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 7/26/2017 | | 9/5/2017 | | PASS |
Brian McGowan
|
|
|
For MH
|
1st review completed | | | 9/1/2017 | | FAIL |
Michael Hanson
|
|
|
Provide WUI zone A details and material requirements.
|
Plan assigned to (BJM) | 7/26/2017 | 7/26/2017 | 8/31/2017 | | DEFR |
Brian McGowan
|
|
|
7/28 sfd ePlan Level 2
|
Plan Reviewer's activity | | | 8/31/2017 | | DONE |
Michael Hanson
|
|
|
1st review completed waiting for response
|
Routing PW Flood Plain | 7/26/2017 | | 8/1/2017 | | PASS |
Jason C. Taylor
|
|
|
No review required as project is outside floodplain limits. JCT
|
Routing - Addressing | 7/26/2017 | | 7/28/2017 | | PASS |
Doug Chausow
|
|
|
|
Route to Impact Fee Review | 7/26/2017 | 7/29/2017 | 7/27/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 7/26/2017 | | 7/27/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 7/26/2017 | | 7/27/2017 | | PASS |
David Moser
|
|
|
|
Routing - MECHANICAL | 7/26/2017 | | 7/27/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 7/26/2017 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/26/2017 | | DONE |
|
|
|
|
Application received | | | 7/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 11 2017 3:51PM
|