Permit Information
Permit NumberBLD17-02341
StatusFinaled
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 3003 W MAIN ST Unit: STE 110
Project NameDeliberate Directions Ste 110
Customer Number 
ePlanReviewYes
Description
(DELIBERATE DIRECTIONS – SUITE #110) Permit for new 1,738 sq. ft. business use tenant in a vacant shell space. Approval is contingent upon adhering to the approved plans on file. Work to include: new concrete slab, new construction of interior non-bearing walls to create (3) offices, a conference room, hallways and a reception area, new door/door frames, millwork, interior windows, select new suspended acoustic ceiling, new light fixtures, electrical work, plumbing work, mechanical work and interior finishes in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 10/28/201710/24/2017 DONE
This permit finaled on the web by Brian McCoy
BLD-Final10/17/201710/18/201710/18/2017APASS
DetailsDave Hannah
Please call 30min prior for access - Jamie Phone #: ###-####
Permanent Occupancy  10/18/2017 DONE
BLD-Final10/12/201710/12/201710/12/2017PPEND
DetailsDave Hannah
Please contact Jamie 30 min prior for access please
###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy ok for tco ok for perm after they finish installing glass
FIRE-Final Inspection10/11/201710/12/201710/12/2017APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguisher is in place with a current nispection tag. Final life fire safety inspection passed/complete.
BLD-Ceiling Grid Inspection9/27/20179/27/20179/27/2017PPASS
DetailsJim Sly
please call 30 min prior / Jamie Phone #: ###-####
BLD-Framing/Rough-in8/25/20178/25/20178/25/2017PPASS
DetailsDave Hannah
As late as possible and call half hour before to meet // Jamie Phone #: ###-#### ok to cover after plumbing rough in
Plan assigned to (JG)7/26/20177/26/20178/24/2017 PASS
DetailsJavier Guzman
1st rev comp, 8/08 L2 Deliberate Directions ePlan
Routing - PLAN CHECK8/24/2017 8/24/2017 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  8/24/2017 DONE
Permit Ready to Issue  8/24/2017 DONE
DetailsChristina Prado
Need:
GC Form
Revised Certificate of Value
Issue PAID IN FULL permit  8/24/2017 DONE
Print Occupancy Form  8/24/2017 DONE
Routing - PLAN CHECK8/21/2017 8/22/2017 FAIL
DetailsJavier Guzman
Routing - MECHANICAL8/21/2017 8/22/2017 PASS
DetailsTroy James
Route to Impact Fee Review8/8/20178/11/20178/9/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK7/26/2017 8/8/2017 FAIL
DetailsJavier Guzman
1st review completed  8/8/2017 FAIL
DetailsJavier Guzman
Routing - Addressing7/26/2017 7/28/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS7/26/2017 7/26/2017 PASS
DetailsRachael Beierle
Intake Approval  7/26/2017 PASS
DetailsJavier Guzman
Routing - MECHANICAL7/26/2017 7/26/2017 FAIL
DetailsTroy James
Intake Approval  7/14/2017 FAIL
DetailsJavier Guzman
Please provide and upload the following:
• Please provide a wall sections detail to include the new interior wall bracing method at top of new wall
• Please provide a finish schedule
• Please provide mechanical plans stamped and signed by an Idaho licensed engineer where any new mechanical duct work is being installed
Application received  7/11/2017 DONE
Application submitted via PDS Online on Jul 11 2017 4:37PM