Letter of compliance/Occupancy | | | 11/30/2017 | | DONE |
|
|
|
|
BLD-Final | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells
|
DOC - Permit Finaled | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 11/22/2017 | 11/27/2017 | 11/27/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Needs electrical final and install handrails.
|
BLD-Energy code compliance | 10/10/2017 | 10/10/2017 | 10/10/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells
|
BLD-Framing/Rough-in | 10/10/2017 | 10/10/2017 | 10/10/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells
|
BLD-Framing/Rough-in | 10/9/2017 | 10/9/2017 | 10/9/2017 | P | DEFR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Will inspect on energy code.
|
BLD-Framing/Rough-in | 10/7/2017 | 10/9/2017 | 10/9/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Foam seal complete. Still needs to correct hangar issues. Ok to insulate.
|
BLD-Framing/Rough-in | 10/5/2017 | 10/6/2017 | 10/6/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Nail off simpson hangars in garage on LVL's. Provide correct hangars on 2 of the LVL's in the garage. Complete the airseal on plumbing penetrations on the main level. Correction notice issued. Ok to insulate.
|
BLD-Wall Bracing | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PASS |
Jim Sly
|
|
|
Shear // Zane Phone #: ###-####
|
BLD-Foundation | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | PASS |
Jim Sly
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 8/30/2017 | 8/31/2017 | 8/31/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
Issue PAID IN FULL permit | | | 8/30/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 8/28/2017 | | |
|
|
|
|
Telephone call | | | 8/28/2017 | | DONE |
Christina Prado
|
|
|
Called Tom to advise permit is ready and gave fees due
|
Plan assigned to (M_H) | 8/24/2017 | | 8/28/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 8/24/2017 | | 8/28/2017 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 8/28/2017 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 8/28/2017 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/28/2017 | | DONE |
Michael Hanson
|
|
|
|
Inspection Record Card- Bld | | | 8/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/28/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/19/2017 | | 8/28/2017 | | PASS |
Brian McGowan
|
|
|
for MH
|
Plan assigned to (BJM) | 7/12/2017 | 7/12/2017 | 8/24/2017 | | DEFR |
Brian McGowan
|
|
|
7/25 sfd paper
|
Plan Reviewer's activity | | | 8/24/2017 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 7/13/2017 | | 7/19/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 7/12/2017 | 7/15/2017 | 7/13/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 7/13/2017 | | 7/13/2017 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 7/12/2017 | | 7/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/12/2017 | | 7/13/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/12/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/12/2017 | | DONE |
|
|
|
|
Intake Approval | | | 7/12/2017 | | PASS |
|
|
|
|
Application received | | 7/12/2017 | | | |
|
|
|
|