Zoning Approval | 8/1/2018 | 8/1/2018 | 8/1/2018 | | DONE |
Andrea Tuning
|
|
|
Approved per Cody Riddle and Hal Simmons
|
Permanent Occupancy | | | 8/1/2018 | | DONE |
|
|
|
|
Temporary Occupancy | 7/30/2018 | 8/2/2018 | 7/30/2018 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 7/30/2018 | | DONE |
|
|
|
|
BLD-Final | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp occ. Will be ok for perm occ. once zoning signs perm.
|
FIRE-Final Inspection | 6/26/2018 | 6/27/2018 | 6/27/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | FAIL |
Jim Page
|
|
|
Only 1 smoke detector in the unit 102 would sound when test buttons was pushed, smoke detectors in the units all need to sound when smoke detection audible is activated.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Final | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | NR |
Mike Jordan
|
|
|
Fire Final called in for PM as well. Phone #: ###-#### Inspection requested via web by David Scaggs. Needs fire/life/safety fialfirst.
|
FIRE-Final Inspection | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | FAIL |
Troy Cobbley
|
|
|
102 smoke alarms did not ring back. 104 head under stairs issue.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
PubWorks Occupancy Approval | 5/22/2018 | 5/22/2018 | 5/22/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 5/15/2018 | 5/15/2018 | 5/15/2018 | | DONE |
Andrea Tuning
|
|
|
|
Print Occupancy Form | | | 4/23/2018 | | DONE |
|
|
|
|
BLD-Energy code compliance | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Framing/Rough-in | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Wall Bracing | 2/28/2018 | 2/28/2018 | 2/28/2018 | A | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Marty Short
|
BLD-Footing | 1/15/2018 | 1/16/2018 | 1/16/2018 | A | PASS |
Mike Jordan
|
|
|
Interior footings, concrete scheduled for 10am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Energy code compliance | 1/1/2018 | 1/2/2018 | 1/2/2018 | A | PART |
Mike Jordan
|
|
|
Foundation insulation Phone #: ###-#### Inspection requested via web by Marty Short. Noted to contractor that prior to backfill operations, areas to be backfilled must be free of snow and ice and not be frozen. Baclfill materials also to not be frozen.
|
BLD-Foundation | 12/26/2017 | 12/27/2017 | 12/27/2017 | P | PASS |
Mike Jordan
|
|
|
Concrete scheduled for 1pm Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 12/20/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Mike Jordan
|
|
|
Concrete scheduled for 2pm Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 12/17/2017 | 12/18/2017 | 12/18/2017 | A | CANC |
Mike Jordan
|
|
|
Concrete scheduled for 12pm Phone #: ###-#### Inspection requested via web by Marty Short
|
Issue PAID IN FULL permit | | | 10/23/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/23/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/19/2017 | | |
|
|
|
|
Plan assigned to (JAR) | 7/26/2017 | 7/26/2017 | 10/19/2017 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 506 Cimarron Apartments - 1285
|
Routing PW Sewer Rating | 10/19/2017 | | 10/19/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 10/16/2017 | | 10/19/2017 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 10/16/2017 | | 10/19/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/19/2017 | | DONE |
|
|
|
NEED
ACHD
Revised Cert of Value - MET
RP - MET
GC Form - MET
|
Routing - PLAN CHECK | 10/3/2017 | | 10/10/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 10/3/2017 | | 10/10/2017 | | FAIL |
Julie Romig
|
|
|
2nd Review - AHJ
|
Routing - FIRE | 10/3/2017 | 10/3/2017 | 10/6/2017 | | PASS |
Scott Arellano
|
|
|
IFC plan review report attached to BLD17-02417.
|
Routing PW Sewer Design | 10/4/2017 | | 10/5/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Passed per ePlanReview and main permit BLD17-02410 by KSR
|
Routing - PUBLIC WORKS | 10/3/2017 | | 10/4/2017 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 9/20/2017 | 9/23/2017 | 9/21/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - MECHANICAL | 7/26/2017 | | 9/21/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 7/26/2017 | | 9/21/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Drainage | 7/27/2017 | | 9/21/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Solid Waste | 7/27/2017 | | 9/21/2017 | | PASS |
|
|
|
|
1st review completed | | | 9/20/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 7/26/2017 | | 9/20/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
Routing Off Site - STRUCTURAL | 7/26/2017 | | 8/10/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
Routing - Erosion and Sediment | 7/26/2017 | | 8/7/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan submitted and approved under main site ESC/GRD permit, see GRD17-00007/ESC17-00102. Need to designate valid RP. (not Jerry Fairbank - no longer onsite)
|
Routing - Design Review | 7/26/2017 | | 8/4/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Addressing | 7/26/2017 | | 7/31/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Street Lights | 7/27/2017 | | 7/31/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - FIRE | 7/26/2017 | 7/26/2017 | 7/28/2017 | | FAIL |
Scott Arellano
|
|
|
See BLD17-02410 for plan review report.
|
Routing PW Sewer Design | 7/27/2017 | | 7/28/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Need to include civil sheets showing connections to public sewer.
|
Routing - PLUMBING | 7/26/2017 | | 7/28/2017 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - PLANNING | 7/26/2017 | | 7/27/2017 | | PASS |
Cody Riddle
|
|
|
|
Routing - PUBLIC WORKS | 7/26/2017 | | 7/27/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 7/26/2017 | | PASS |
|
|
|
|
Application received | | | 7/14/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 14 2017 1:22PM
|
First Notice | | 8/11/2018 | | | |
|
|
|
|
Routing PW Sewer Rating | 7/27/2017 | | | | FAIL |
Beverly Mountain
|
|
|
No dimensioned site plan
|