Zoning Approval | 8/1/2018 | 8/1/2018 | 8/1/2018 | | DONE |
Andrea Tuning
|
|
|
Approved per Cody Riddle and Hal Simmons
|
Permanent Occupancy | | | 8/1/2018 | | DONE |
|
|
|
|
BLD-Aging Inspection | 7/2/2018 | 7/2/2018 | 7/2/2018 | | PEND |
Mike Jordan
|
|
|
|
Temporary Occupancy | 5/3/2018 | 8/1/2018 | 5/3/2018 | | DONE |
Tisha Gallop
|
|
|
Permanent occupancy pending approval by Planning & Zoning.
|
PubWorks Occupancy Approval | 5/3/2018 | 5/3/2018 | 5/3/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 5/1/2018 | 5/2/2018 | 5/2/2018 | A | PASS |
Mike Jordan
|
|
|
Public Works final scheduled for 8:30 am. Will obtain occupancy signature on sign-off card. Phone #: ###-#### Inspection requested via web by David Scaggs. OK for temp occ. Will be ok for perm occ. once zoning signs perm.
|
Zoning Approval Temp | 5/1/2018 | 5/1/2018 | 5/1/2018 | | DONE |
Andrea Tuning
|
|
|
90 day temporary
|
FIRE-Final Inspection | 4/25/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Smoke alarms tested.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
Print Occupancy Form | | | 4/23/2018 | | DONE |
|
|
|
|
BLD-Energy code compliance | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Framing/Rough-in | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Framing/Rough-in | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | NR |
Mike Jordan
|
|
|
Please accommodate a 10 o''clock inspection Phone #: ###-#### Inspection requested via web by David Scaggs. All framing corrections not yet completed.
|
BLD-Energy code compliance | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | NR |
Mike Jordan
|
|
|
Please accommodate a 10 o''clock inspection Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Wall Bracing | 1/24/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Framing/Rough-in | 1/23/2018 | 1/24/2018 | 1/24/2018 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Repair all holes in fire partition in atic. Install all missing h2.5. Install headers over bathroom entries on joist fi. Fire block wall at upstairs mech. rooms. Correction notice issued. ok to insulate.
|
BLD-Wall Bracing | 1/15/2018 | 1/16/2018 | 1/16/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 11/30/2017 | 12/1/2017 | 12/1/2017 | A | PASS |
Mike Jordan
|
|
|
Interior footings, Concrete scheduled for 10am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Foundation | 11/19/2017 | 11/20/2017 | 11/20/2017 | P | PASS |
Mike Jordan
|
|
|
Concrete scheduled for 3pm Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 10/31/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Mike Jordan
|
|
|
2:00 pm inspection with concrete scheduled for 3:00 pm Phone #: ###-#### Inspection requested via web by Marty Short
|
Issue PAID IN FULL permit | | | 10/23/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/23/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/19/2017 | | |
|
|
|
|
Plan assigned to (JAR) | 7/26/2017 | 7/26/2017 | 10/19/2017 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 506 Cimarron Apartments - 1303
|
Routing PW Sewer Rating | 10/19/2017 | | 10/19/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 10/16/2017 | | 10/19/2017 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 10/16/2017 | | 10/19/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/19/2017 | | DONE |
|
|
|
NEED
ACHD
Revised Cert of Value - MET
RP - MET
GC Form - MET
|
Routing - PLAN CHECK | 10/3/2017 | | 10/10/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 10/3/2017 | | 10/10/2017 | | FAIL |
Julie Romig
|
|
|
2nd Review - AHJ
|
Routing - FIRE | 10/3/2017 | 10/3/2017 | 10/6/2017 | | PASS |
Scott Arellano
|
|
|
IFC plan review report attached to BLD17-02417.
|
Routing PW Sewer Design | 10/4/2017 | | 10/5/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Passed per ePlanReview and main permit BLD17-02410 by KSR
|
Routing - PUBLIC WORKS | 10/3/2017 | | 10/4/2017 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 9/20/2017 | 9/23/2017 | 9/21/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing PW Solid Waste | 7/27/2017 | | 9/21/2017 | | PASS |
|
|
|
|
Routing - MECHANICAL | 7/26/2017 | | 9/21/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING Land Div | 7/26/2017 | | 9/21/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Drainage | 7/27/2017 | | 9/21/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 7/26/2017 | | 9/20/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
1st review completed | | | 9/20/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 7/26/2017 | | 8/10/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
Routing - Erosion and Sediment | 7/26/2017 | | 8/7/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan submitted and approved under main site ESC/GRD permit, see GRD17-00007/ESC17-00102. Need to designate valid RP. (not Jerry Fairbank - no longer onsite)
|
Routing - Design Review | 7/26/2017 | | 8/4/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Addressing | 7/26/2017 | | 7/31/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Street Lights | 7/27/2017 | | 7/31/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - FIRE | 7/26/2017 | 7/26/2017 | 7/28/2017 | | FAIL |
Scott Arellano
|
|
|
See BLD17-02410 for plan review report.
|
Routing PW Sewer Design | 7/27/2017 | | 7/28/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Need to include civil sheets showing connections to public sewer.
|
Routing - PLUMBING | 7/26/2017 | | 7/28/2017 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - PLANNING | 7/26/2017 | | 7/27/2017 | | PASS |
Cody Riddle
|
|
|
|
Routing - PUBLIC WORKS | 7/26/2017 | | 7/27/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 7/26/2017 | | PASS |
|
|
|
|
Application received | | | 7/14/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 14 2017 1:22PM
|
First Notice | | 8/11/2018 | | | |
|
|
|
|
Routing PW Sewer Rating | 7/27/2017 | | | | FAIL |
Beverly Mountain
|
|
|
No dimensioned site plan
|