BLD-Final | 6/6/2018 | 6/7/2018 | 6/7/2018 | P | PASS |
Dave Hannah
|
|
|
Charlie Phone #: ###-####
|
DOC - Permit Finaled | 6/7/2018 | 6/7/2018 | 6/7/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 6/5/2018 | 6/6/2018 | 6/6/2018 | A | NR |
Dave Hannah
|
|
|
Gorge Phone #: ###-####
|
BLD-Framing/Rough-in | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PASS |
Dave Hannah
|
|
|
Charlie--for the garage Phone #: ###-####
|
BLD-Footing | 4/4/2018 | 4/5/2018 | 4/5/2018 | A | PASS |
Dave Hannah
|
|
|
11 am Please- Geroge Phone #: ###-####
|
BLD-Energy code compliance | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | PASS |
Dave Hannah
|
|
|
George Phone #: ###-####
|
BLD-Framing/Rough-in | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PASS |
Dave Hannah
|
|
|
Geroge Phone #: ###-####
|
BLD-Wall Bracing | 1/9/2018 | 1/10/2018 | 1/10/2018 | A | PASS |
Dave Hannah
|
|
|
George Phone #: ###-####
|
Plan Modification Accepted | | | 1/9/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/9/2018 | | 1/9/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Conference | 11/15/2017 | 11/15/2017 | 11/16/2017 | P | DONE |
Dave Hannah
|
|
|
Customer complaint about plastic fence falling down and no sign (ESC) post for construction.
|
BLD-Foundation | 11/7/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Dave Hannah
|
|
|
Jenny Phone #: ###-####
|
BLD-Footing | 11/3/2017 | 11/6/2017 | 11/6/2017 | A | PASS |
Dave Hannah
|
|
|
Sebastian Phone #: ###-####
|
BLD-Foundation | 11/6/2017 | 11/6/2017 | 11/6/2017 | A | CANC |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 10/27/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/13/2017 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/13/2017 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 10/13/2017 | | DONE |
|
|
|
Spoke with George informing him that his permit is ready to be picked up and the fee amount due for issuance
|
Routing - PLAN CHECK | 7/24/2017 | | 10/13/2017 | | PASS |
Brian McGowan
|
|
|
|
Plan assigned to (M_H) | 8/17/2017 | | 10/13/2017 | | DONE |
Michael Hanson
|
|
|
1st review completed waiting for response - 9/17/17 received 5 out of 7 deficiencies. Emailed back for remaining 2 deficiencies. MH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2017 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/13/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 10/13/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan resubmittals received | | | 10/12/2017 | | DONE |
|
|
|
Received two copies full set of plans; given to Michael Hanson
|
1st review completed | | | 8/29/2017 | | FAIL |
Michael Hanson
|
|
|
Contacted client with list of deficiencies 8/17. ***MDH***
|
Plan assigned to (BJM) | 7/18/2017 | 7/18/2017 | 8/17/2017 | | DEFR |
Brian McGowan
|
|
|
7/31 sfd paper
|
Plan Reviewer's activity | | | 8/17/2017 | | |
Michael Hanson
|
|
|
|
Routing - PLANNING | 8/10/2017 | | 8/11/2017 | | PASS |
Ted Vanegas
|
|
|
Revised plans show increased rear setback to 10'.
|
Plan resubmittals received | | | 8/10/2017 | | DONE |
|
|
|
received two full size copies of site plan and one reduced size site plan; taken to Brian McGowan
|
Routing - MECHANICAL | 7/28/2017 | | 7/28/2017 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | | | 7/24/2017 | | FAIL |
Troy James
|
|
|
emailed corrections to Idaho HVAC
|
Route to Impact Fee Review | 7/18/2017 | 7/21/2017 | 7/21/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 7/18/2017 | | 7/19/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/18/2017 | | 7/19/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/18/2017 | | DONE |
|
|
|
|
Intake Approval | | | 7/18/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/18/2017 | | DONE |
|
|
|
|
Application received | | 7/18/2017 | | | |
|
|
|
|
Routing - PLANNING | 7/19/2017 | | | | FAIL |
|
|
|
The garage location does not provide the required 22' of backup space.
|