Zoning Approval | 11/26/2018 | 11/26/2018 | 11/26/2018 | | DONE |
Brent Moore
|
|
|
|
Permanent Occupancy | | | 11/26/2018 | | DONE |
|
|
|
|
BLD-Final | 10/12/2018 | 10/12/2018 | 10/12/2018 | P | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-####
|
FIRE-Final Inspection | 10/11/2018 | 10/11/2018 | 10/12/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed on the remaining apartments. Boise fire reviewed the FDC location
Cody Phone #: ###-####
|
Temporary Occupancy | 10/12/2018 | 1/10/2019 | 10/12/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
|
BLD-Final | 9/28/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
Jim Storey
|
|
|
all units ending in 03 & 04 // Cody Phone #: ###-####
|
Temporary Occupancy | 9/28/2018 | 12/27/2018 | 9/28/2018 | | DONE |
Candy A. Nichols
|
|
|
tem c of o for 103, 104, 203, 204, 303, 304 only
|
FIRE-Final Inspection | 9/25/2018 | 9/25/2018 | 9/26/2018 | P | PART |
Troy Cobbley
|
|
|
Life safety passed in the 03 and 04 apartments
Cody Phone #: ###-####
|
BLD-Final | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-####
|
Temporary Occupancy | 9/21/2018 | 12/20/2018 | 9/21/2018 | | DONE |
Tisha Gallop
|
|
|
Temp occupancy for units 105, 106, 205, 206, 305, 306. Perm occupancy pending Zoning, fire, building, elec, plm, mech
|
FIRE-Final Inspection | 9/17/2018 | 9/17/2018 | 9/17/2018 | P | PEND |
Mike Jordan
|
|
|
Cody Phone #: ###-####. Apt. 105,106,205,206.305,307 life safety ok pending the project related fire sprinkler inspection passes for above units. Also all doors to be self closing for building final.
|
BLD-Conference | 9/6/2018 | 9/7/2018 | 9/7/2018 | A | PART |
Jim Storey
|
|
|
partial - Cody Phone #: ###-#### finals ok 6 units 07/08 123
|
Temporary Occupancy | 9/7/2018 | 12/6/2018 | 9/7/2018 | | DONE |
Tisha Gallop
|
|
|
Temporary occupany for units 107, 108, 207, 208, 307, 308. All other units still pending approvals from Fire, Buidling, Plumbing, Mechanical, Electrical.
|
BLD-Final | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | DEFR |
Jim Storey
|
|
|
partial - Cody Phone #: ###-####
|
PubWorks Occupancy Approval | 9/6/2018 | 9/6/2018 | 9/6/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 9/5/2018 | 9/5/2018 | 9/5/2018 | | PASS |
Josh Wilson
|
|
|
ok for 180 day temp occ - bond for landscaping, etc is in place
|
FIRE-Final Inspection | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PART |
Troy Cobbley
|
|
|
Life safety is passed in the 07's and 08 numbered apartments (south end)
Cody Phone #: ###-####
|
BLD-Wall cover | 8/16/2018 | 8/16/2018 | 8/16/2018 | P | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-####
|
BLD-Wall cover | 8/9/2018 | 8/9/2018 | 8/9/2018 | P | PASS |
Jim Storey
|
|
|
Dry wall // Cody Phone #: ###-####
|
BLD-Energy code compliance | 8/1/2018 | 8/2/2018 | 8/2/2018 | A | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-#### framing c/n made ok // ok to cover
|
BLD-Framing/Rough-in | 7/27/2018 | 7/27/2018 | 7/27/2018 | P | PART |
Jim Storey
|
|
|
For units 102, 102, 201, 202, 301, 302, 103, 104, 203, 204 & 303 & 304 - Pat Phone #: ###-#### short list w/pat
|
BLD-Framing/Rough-in | 7/27/2018 | 7/27/2018 | 7/27/2018 | P | PASS |
Jim Storey
|
|
|
RC1 channel for units 205 & 206 - Pat Phone #: ###-####
|
BLD-Other | 7/25/2018 | 7/26/2018 | 7/26/2018 | A | PASS |
Jim Storey
|
|
|
rc1 channel ste 105 & 106 // Pat Phone #: ###-####
|
BLD-Energy code compliance | 7/18/2018 | 7/19/2018 | 7/19/2018 | A | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-####6 center units
|
BLD-Framing/Rough-in | 7/16/2018 | 7/16/2018 | 7/16/2018 | P | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-####
|
BLD-Framing/Rough-in | 7/13/2018 | 7/13/2018 | 7/13/2018 | P | CANC |
Jim Storey
|
|
|
Cody Phone #: ###-####
|
BLD-Framing/Rough-in | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | FAIL |
Jim Storey
|
|
|
for units 105, 106, 205, 206, 305, 306 // Pat Phone #: ###-#### as noted 2hr/hangers bearing 2ply
|
BLD-Wall cover | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PART |
Jim Storey
|
|
|
RC1- STE, 107, 108, 207 and 208 Pat Phone #: ###-#### need rated gyp above fales ceillings
|
BLD-Energy code compliance | 7/3/2018 | 7/5/2018 | 7/6/2018 | P | PART |
Jim Storey
|
|
|
pat ste 106 107 206 207 306 307 Phone #: ###-#### 106 and 107 need gyp at stair exit to floor at drops
|
BLD-Framing/Rough-in | 7/2/2018 | 7/2/2018 | 7/3/2018 | P | PART |
Dave Hannah
|
|
|
Pat-ste numbers 107-107, 207-208, 307-308 Phone #: ###-#### fire cualking ok ok to insulate check draft stopping at insulation inspection
|
BLD-Framing/Rough-in | 6/28/2018 | 6/29/2018 | 6/29/2018 | P | NR |
Jim Sly
|
|
|
Pat-ste #''s 107, 108, 207, 208, 307, 308 Phone #: ###-#### Major Firecaulking issues at fir downs, rated stairway walls, and draftstops.......... Penitrations and edges.
|
BLD-Framing/Rough-in | 6/28/2018 | 6/29/2018 | 6/29/2018 | P | CANC |
Jim Sly
|
|
|
Pat Phone #: ###-####
|
BLD-Wall Bracing | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-#### exterior sheer ok
|
BLD-Framing/Rough-in | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PART |
Jim Storey
|
|
|
Cody Phone #: ###-#### pre rock ok
|
BLD-Wall Bracing | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | NR |
Jim Storey
|
|
|
Cody Phone #: ###-####
|
BLD-Wall Bracing | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | NR |
Jim Storey
|
|
|
shear-Cody Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/14/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/14/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/12/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/11/2018 | | |
|
|
|
|
Routing - PLAN CHECK | 1/11/2018 | | 1/11/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 1/11/2018 | | 1/11/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2018 | | DONE |
|
|
|
|
Extend Review Timeline | | | 1/11/2018 | | DONE |
|
|
|
1st approved 180 day extension per adele. see documents
|
Permit Ready to Issue | | | 1/11/2018 | | DONE |
|
|
|
ALL MET
Need DO NOT ISSUE WITHOUT BLD17-02477
ACHD - met
Cert of value (need one with correct address on it)
RP (which person)
Close out foundation permit Bld17-04001 when this permit is issued.
|
Routing - Design Review | 8/3/2017 | | 1/11/2018 | | PASS |
Sarah Schafer
|
|
|
|
Plan Modification Accepted | | | 12/11/2017 | | DONE |
|
|
|
new manual j reports
|
Routing - MECHANICAL | 12/11/2017 | | 12/11/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j reports
|
Plan assigned to (CDM) | 8/3/2017 | 8/3/2017 | 11/2/2017 | | PASS |
Carl D Madsen
|
|
|
Owyhee Apartments 1st Done
|
Route to Impact Fee Review | 9/11/2017 | 9/14/2017 | 9/22/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLANNING Land Div | 8/3/2017 | | 9/11/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - PUBLIC WORKS | 8/3/2017 | | 9/11/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PUBLIC WORKS | 9/11/2017 | | 9/11/2017 | | PASS |
Mike Sheppard
|
|
|
|
1st review completed | | | 9/11/2017 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/3/2017 | | 9/10/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/3/2017 | | 9/10/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Addressing | 8/3/2017 | | 8/30/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - FIRE | 8/3/2017 | 8/3/2017 | 8/10/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - Erosion and Sediment | 8/3/2017 | | 8/8/2017 | | PASS |
Andy J. Long
|
|
|
see ESC17-00936 for SWPPP review and main site permit.
|
Routing - MECHANICAL | 8/3/2017 | | 8/4/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/3/2017 | | 8/3/2017 | | PASS |
Bill VanDegrift
|
|
|
See redlines. Install per ISPC.
|
Intake Approval | | | 8/3/2017 | | PASS |
|
|
|
|
Application received | | | 7/18/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 18 2017 4:18PM
|
First Notice | | 12/6/2018 | | | |
|
|
|
|