Print Statement | | | 1/3/2018 | | DONE |
|
|
|
|
Third Notice | | 11/19/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Second Notice | | 10/22/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
First Notice | 10/11/2017 | 10/11/2017 | 10/12/2017 | | DONE |
Mike Jordan
|
|
|
Mailed 10-13-17
|
BLD-Final | 10/10/2017 | 10/11/2017 | 10/11/2017 | P | PASS |
Mike Jordan
|
|
|
Davin Phone #: ###-####
|
DOC - Permit Finaled | 10/11/2017 | 10/11/2017 | 10/11/2017 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 10/10/2017 | 10/11/2017 | 10/11/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | FAIL |
Troy Cobbley
|
|
|
I met Ben with ESI on site and discussed the previously noted correction issues
|
BLD-Conference | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | NR |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
FIRE-Conference | 10/5/2017 | 10/6/2017 | 10/6/2017 | A | DONE |
Troy Cobbley
|
|
|
Matt and I went through the life safety. Will need to test the emergency lights and exit signs. Also the existing fire alarm system will need to be extended/modified in the remodeled space as per discussion.
Matt Phone #: ###-####
|
BLD-Final | 10/5/2017 | 10/6/2017 | 10/6/2017 | P | CANC |
Mike Jordan
|
|
|
Matt Phone #: ###-#### Per Matt wanted a conference instead
|
BLD-Ceiling Grid Inspection | 9/27/2017 | 9/27/2017 | 9/27/2017 | P | CANC |
Brandon Shaw
|
|
|
OK to cover
|
BLD-Final | 9/27/2017 | 9/27/2017 | 9/27/2017 | P | CANC |
Brandon Shaw
|
|
|
Matt Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/20/2017 | 9/21/2017 | 9/21/2017 | A | NR |
Brandon Shaw
|
|
|
Need other trades ceiling
|
BLD-Framing/Rough-in | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Interior steel stud framed walls only ok.
|
Issue PAID IN FULL permit | | | 8/25/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/25/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/22/2017 | 8/25/2017 | 8/23/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 7/28/2017 | 7/28/2017 | 8/23/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 8/10 L2 Fred Meyer Clicklist ePlan, pend DR
|
Routing - PLAN CHECK | 8/23/2017 | | 8/23/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/23/2017 | | DONE |
Christina Prado
|
|
|
Need:
MET GC Form
MET Revised Cert of Value
|
1st review completed | | | 8/22/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Design Review | 8/22/2017 | | 8/22/2017 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 8/22/2017 | | 8/22/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 8/9/2017 | 8/9/2017 | 8/21/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing Off Site - C.D.H | 7/28/2017 | | 8/9/2017 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by Central District Health Department
Joe Antonucci
|
Routing - PLAN CHECK | 7/28/2017 | | 8/9/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 7/28/2017 | | 7/31/2017 | | FAIL |
Katelyn Menuge
|
|
|
Accurate overall site plan and parking count needed.
|
Routing - Addressing | 7/28/2017 | | 7/31/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/28/2017 | | 7/28/2017 | | PASS |
Beverly Mountain
|
|
|
|
Routing - MECHANICAL | 7/28/2017 | | 7/28/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 7/28/2017 | | 7/28/2017 | | PASS |
Daryl Spivey
|
|
|
|
Intake Approval | | | 7/28/2017 | | PASS |
Javier Guzman
|
|
|
|
Plan Reviewer's activity | | | 7/27/2017 | | DONE |
|
|
|
Spoke with applicant regarding CDHD approval. He said Joe at CDHD requested plans be routed to him in ePlanReview and he would approve them through ePlanReview.
|
Intake Approval | | | 7/25/2017 | | FAIL |
Julie Romig
|
|
|
Need:
1. CDHD approved plans - indicated on checklist but not provided.
|
Application received | | | 7/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2017 3:04PM
|