Second Notice | | 4/20/2018 | 5/11/2018 | | DONE |
|
|
|
mailed 5-14
|
First Notice | | 4/1/2018 | 4/10/2018 | | DONE |
|
|
|
mailed 4-11-18
|
BLD-Final | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | PASS |
Jim Sly
|
|
|
Julio Phone #: ###-####
|
Print Occupancy Form | | | 3/22/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/22/2018 | | DONE |
|
|
|
|
BLD-Final | 3/9/2018 | 3/12/2018 | 3/14/2018 | P | PASS |
Jim Sly
|
|
|
after zoning/lunch hour - Julio Phone #: ###-####
|
Zoning Approval | 3/14/2018 | 3/14/2018 | 3/14/2018 | | DONE |
Andrea Tuning
|
|
|
|
PubWorks Occupancy Approval | 3/14/2018 | 3/14/2018 | 3/14/2018 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | PASS |
Jim Page
|
|
|
No fire alarm, no fire sprinklers, fire extinguishers are in place with current inspection tags. Final life fire safety inspection complete.
|
BLD-Final | 3/7/2018 | 3/9/2018 | 3/9/2018 | A | CANC |
Jim Sly
|
|
|
Julio Phone #: ###-####-still needs a P & Z final
|
FIRE-Final Inspection | 3/8/2018 | 3/9/2018 | 3/9/2018 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents on site. No inspection performed.
Julio Phone #: ###-####
|
PubWorks Temp Occupancy Appr | 2/28/2018 | 2/28/2018 | 2/28/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Print Occupancy Form | | | 2/26/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/3/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/3/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/29/2017 | | |
|
|
|
|
Plan assigned to (JG) | 8/4/2017 | 8/4/2017 | 9/29/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 8/30 Dennis Dillon Storage Building ePlan
|
Routing - PLANNING | 9/28/2017 | | 9/29/2017 | | PASS |
Leon Letson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/29/2017 | | DONE |
Christina Prado
|
|
|
Need
GC Form - MET
Revised Cert of Value - MET
RP - MET
|
Routing - Design Review | 9/28/2017 | | 9/28/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 9/21/2017 | | 9/27/2017 | | FAIL |
Leon Letson
|
|
|
Failed in ePlan by Current Planning Leon Letson
|
Routing - FIRE | 9/21/2017 | 9/21/2017 | 9/26/2017 | | PASS |
Scott Arellano
|
|
|
Attached updated comments to plans and case.
|
Routing - PLAN CHECK | 9/21/2017 | | 9/23/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Drainage | 9/21/2017 | | 9/22/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 9/21/2017 | | 9/21/2017 | | FAIL |
Andrea Tuning
|
|
|
Provide on bicycle parking space.
|
Route to Impact Fee Review | 8/30/2017 | 9/2/2017 | 8/31/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 8/4/2017 | | 8/30/2017 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 8/30/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 8/4/2017 | | 8/29/2017 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers Chris Holladay
|
Routing PW Environmental | 8/4/2017 | | 8/29/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Drainage | 8/4/2017 | | 8/16/2017 | | FAIL |
Brian Murphy
|
|
|
NO APPDX J DELETE NOT FOR CONSTRUCTION STAMP-
|
Routing - FIRE | 8/4/2017 | 8/4/2017 | 8/14/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed architect correction items. Attached plan review report to case.
|
Routing - Erosion and Sediment | 8/4/2017 | | 8/8/2017 | | PASS |
Andy J. Long
|
|
|
ESC site map and project narrative approved. Valid PD, RP to be decided upon contract reward. ESC site preparation inspection required prior to construction.
|
Routing - PLANNING Land Div | 8/4/2017 | | 8/7/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 8/4/2017 | | 8/4/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/4/2017 | | 8/4/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 8/4/2017 | | 8/4/2017 | | FAIL |
Leon Letson
|
|
|
See DR comment concerning bike parking.
|
Routing - Design Review | 8/4/2017 | | 8/4/2017 | | FAIL |
Andrea Tuning
|
|
|
Provide one bicycle parking space taht meets the dimensional requirements.
Do not utiilze gravel wtihin the planter beds.
|
Intake Approval | | | 8/4/2017 | | PASS |
|
|
|
|
Routing PW Street Lights | 8/4/2017 | | 8/4/2017 | | PASS |
Tom Marshall
|
|
|
|
Intake Approval | | | 7/28/2017 | | FAIL |
|
|
|
Pre-screen #1 7-28-17
Please provide the required lighting compliance.
Please comply with the stamping area requirement on all plans including the prefabricated building plan sheets.
If mechanical is being provided please provide the mechanical plans. Design Build is not allowed.
Lighting is not a design build option please provide a lighting plan.
The building code analysis indicates no fire sprinklers, however the building fire area is over 12,000 sq. ft. and per section 903.2.9 the building is required to be fully fire sprinklered.
|
Application received | | | 7/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2017 5:06PM
|