Permit Information
Permit NumberBLD17-02574
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 6156 E BARBER DR
Project NameHN 89-1
Customer Number 
ePlanReviewYes
Description
HILLSIDE, WUI ZONE "A", CLASS "A" ROOF REQUIRED. ***Grading Plan resubmitted for Hillside approval 1-22-18 *** Permit for the construction of a new 3958 sq. ft., two story (first story 2665 sq. ft., second story 1293 sq. ft.) single family dwelling with 5 bedrooms, 4.5 bathrooms, approximately 533 sq. ft. of covered patio/porch and a 933 sq. ft. attached garage per the approved plans, plan review report and any notations. ***BJM*** SP-01 zoning and setbacks per planning. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 608-7168.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/9/20183/9/20183/9/2018PPASS
DetailsBrandon Shaw
Rolo Phone #: ###-####
DOC - Permit Finaled3/9/20183/9/20183/9/2018PPASS
DetailsBrandon Shaw
OVERRIDE  2/5/2018  
Plan assigned to (BJM)1/19/20181/19/20182/5/2018 DONE
DetailsBrian McGowan
retaining wall resubmittal
Routing - PLAN CHECK2/5/2018 2/5/2018 PASS
DetailsBrian McGowan
No charge for resubmittal. Minimal Time.
Permit Ready to Issue  2/5/2018 DONE
Plan Mod Approved
DO NOT REISSUE
CHANGE STATUS TO (ISS)  2/5/2018 DONE
PLAN MOD
(F) Reprint permit  2/5/2018 DONE
PubWorks Occupancy Approval1/26/20181/26/20181/26/2018 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
Routing PW Grading-Hillside1/25/2018 1/25/2018 PASS
DetailsMelissa Jannusch
Resubmittals approved.

BLD-Other1/22/20181/22/20181/22/2018PPASS
DetailsBrandon Shaw
Sofit-
Plan Modification Accepted  1/19/2018 DONE
plan mod started in e plan-new retaining wall-assigned to Brian McGowan
BLD-Energy code compliance12/4/201712/5/201712/5/2017APASS
DetailsBrandon Shaw
Framing corrections sat
BLD-Framing/Rough-in11/28/201711/28/201711/28/2017PFAIL
DetailsBrandon Shaw
See correction notice

OK to Insulate
BLD-Wall Bracing11/2/201711/2/201711/2/2017PPASS
DetailsBrandon Shaw
Shear // Rolo Phone #: ###-####
BLD-Foundation9/26/20179/26/20179/26/2017APASS
DetailsBrandon Shaw
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
BLD-Footing9/20/20179/20/20179/20/2017PPASS
DetailsBrandon Shaw
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
PubWorks Subgrade Approval9/19/20179/19/20179/19/2017 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

OVERRIDE  9/8/2017  
Plan assigned to (BJM)9/8/20179/8/20179/8/2017 DONE
DetailsBrian McGowan
Plan assigned to (RDP)8/31/20178/31/20179/8/2017 DEFR
DetailsRob Patrick
8/11 sfd ePlan Level 2
Issue PAID IN FULL permit  9/8/2017 DONE
Inspection Record Card- Bld  9/8/2017 DONE
1st review completed  9/8/2017 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  9/8/2017 DONE
DetailsBrian McGowan
Permit Ready to Issue  9/8/2017 DONE
met
Routing - PLAN CHECK7/25/2017 9/8/2017 PASS
DetailsBrian McGowan
Plan assigned to (BJM)7/25/20177/25/20178/31/2017 DEFR
DetailsBrian McGowan
8/11 sfd ePlan Level 2
Routing PW Grading-Hillside7/25/2017 8/3/2017 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.

Routing - FIRE7/25/20177/25/20177/28/2017 PASS
DetailsScott Arellano
This plan has been reviewed for FD vehicle access, water supply proximity, and defensible space.
Routing - Erosion and Sediment7/25/2017 7/27/2017 PASS
DetailsAndy J. Long
ESC plan approved. Valid RP and PD
Route to Impact Fee Review7/25/20177/28/20177/26/2017 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL7/25/2017 7/26/2017 PASS
DetailsTroy James
Routing - PLANNING7/25/2017 7/26/2017 PASS
DetailsJeff Lowe
Routing - Addressing7/25/2017 7/26/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS7/25/2017 7/26/2017 PASS
DetailsRachael Beierle
Application received  7/25/2017 DONE
Application submitted via PDS Online on Jul 25 2017 10:20AM
Plans ACCEPTED BY PLAN TECH  7/25/2017 DONE
Intake Approval  7/25/2017 PASS
Recd Pcfee & Taken To Pln CK  7/25/2017 DONE