Permit Information
Permit NumberBLD17-02620
StatusFinaled
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 801 W BANNOCK ST
Project NameFunky Taco
Customer NumberDEMO BLD17-02735
ePlanReviewYes
Description
(THE FUNKY TACO – RESTAURANT & BAR – TENANT IMPROVEMENT AND MEZZANINE) (DRH17-00278) This tenant space is separated from the West building by a 3-hr fire wall and from the rest of the East building by a 2-hr fire barrier wall. A fire sprinkler system will be installed throughout the fire area containing this tenant space to allow a floor level above the level of exit discharge and to allow the occupant load to exceed 100. The fire sprinkler system will NOT be installed throughout the entire building. To remodel an existing 1,879 square foot tenant space for a new restaurant tenant. The existing 762 square foot basement will be made available for occupancy and a 291 square foot mezzanine will be constructed. The entire area of this tenant space including the basement and mezzanine will be about 2,932 square feet. Mezzanine work includes concrete footings, steel columns, steel beams, steel braced frames, a steel moment frame, wood floor joists and sheathing, a stairway, guards, and handrails. Special Inspection is required for concrete, for post-installed anchors in hardened concrete, and for welding. A new stairway to the basement will also be constructed. A floor infill will be constructed at the former basement hatch opening. An exterior shear wall will be constructed at the North exterior wall to improve the lateral force resistance of this building. Other work includes three (3) Type I grease hood and duct systems (one of the three systems will be dedicated to a solid fuel burning appliance), a roof top make-up air unit, an exterior vertical uplift bi-fold door, a bar, exterior windows, exterior doors, suspended acoustical ceilings, a suspended wood plank ceiling, and interior finishes. The structural evaluation of the roof and the structure modifications needed to support the new roof top make-up air unit and the grease hoods is a deferred submittal item. The existing restrooms are required to be maintained accessible to the disabled as defined by the 2003 IBC. Interior nonstructural demolition was allowed to be done under permit BLD17-02735. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  6/19/2018 DONE
Third Notice 5/16/20186/11/2018 DONE
mailed 6-12
Second Notice 4/20/20185/11/2018 DONE
mailed 5-14
First Notice 3/17/20184/10/2018 DONE
mailed 4-11-18
Zoning Approval3/7/20183/7/20183/7/2018 PASS
DetailsKatelyn Menuge
Final Zoning/DR Approval
Permanent Occupancy  3/7/2018 DONE
DetailsChristina Prado
BLD-Final3/5/20183/6/20183/6/2018PPASS
DetailsDave Hannah
late pm please // Keegan Phone #: ###-####
BLD-Final3/1/20183/2/20183/5/2018PNR
DetailsDave Hannah
Keegan Phone #: ###-####
FIRE-Final Inspection3/1/20183/1/20183/1/2018PPASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, commercial hood fire suppression system inspection complete, fire extinguishers are in place with current inspection tags, knox box will be mounted in discussed location when recieved. Final life fire safety inspection complete.
Telephone call  2/8/2018 DONE
a gentleman called woith questions about a complaint that a hood was being installed incorectly-I believe he spoke with Adele and she went out to look at it.
BLD-Ceiling Grid Inspection2/1/20182/1/20182/2/2018PPASS
DetailsDave Hannah
Kitchen & Dining - Keegan Phone #: ###-####
BLD-Conference1/16/20181/16/20181/16/2018PDONE
DetailsDave Hannah
Keegan Phone #: ###-####
BLD-Framing/Rough-in1/2/20181/3/20181/3/2018APART
DetailsDave Hannah
Keegan Phone #: ###-#### steel suds around columns and kitchen area ok
BLD-Footing11/9/201711/13/201711/14/2017ADONE
DetailsDave Hannah
Keegan Phone #: ###-####
BLD-Footing11/13/201711/14/201711/14/2017PPASS
DetailsDave Hannah
Keegan Phone #: ###-####
Issue PAID IN FULL permit  10/13/2017 DONE
Print Occupancy Form  10/13/2017 DONE
OVERRIDE  10/2/2017  
Routing - FIRE9/25/2017 10/2/2017 PASS
DetailsScott Arellano
Attached review comments to case
PLANS/APPL TAKEN TO FRONT DESK  10/2/2017 DONE
Permit Ready to Issue  10/2/2017 DONE
Need:
RP

met
Revised value (-demo permit)
ACHD
Plan assigned to (CJW)7/31/2017 10/2/2017 PASS
DetailsCarl Westfall
(2nd done) (Aug 18 - 15 days) (35 sheets) The Funky Taco
Routing - PLUMBING9/25/2017 9/28/2017 PASS
DetailsDaryl Spivey
per plans and ISPC
Routing - Design Review9/25/2017 9/25/2017 PASS
DetailsKatelyn Menuge
Routing - MECHANICAL9/25/2017 9/25/2017 PASS
DetailsTroy James
Plan resubmittals received  9/25/2017 DONE
Routing - PLAN CHECK9/25/2017 9/25/2017 PASS
DetailsCarl Westfall
2nd review completed. Drawings approved
Route to Impact Fee Review9/8/20179/11/20179/14/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  9/8/2017 DONE
Plan resubmittals requested  9/8/2017 DONE
Routing - PLAN CHECK7/31/2017 9/8/2017 FAIL
DetailsCarl Westfall
Routing - Design Review  8/31/2017 FAIL
DetailsKatelyn Menuge
Routing PW Environmental8/1/2017 8/29/2017 PASS
DetailsRick Christenson
Approved per plumbing changes.
Routing Off Site - STRUCTURAL7/31/2017 8/14/2017 PASS
DetailsCarl Westfall
Jan Welch (Stapley)
Routing - FIRE7/31/20177/31/20178/7/2017 FAIL
DetailsScott Arellano
Attached comments to plans. Emailed applicant with resubmittal items.
Routing - MECHANICAL7/31/2017 8/7/2017 FAIL
DetailsTroy James
left message with mechanical engineer
Plan assigned to (CJW)7/31/20177/31/20178/4/2017 PASS
DetailsCarl Westfall
(Aug 18 - 15 days) (34 sheets) The Funky Taco
Routing - Erosion and Sediment7/31/2017 8/3/2017 PASS
DetailsAndy J. Long
ESC plan waiver approved. RP to be designated.
Routing - Design Review7/31/2017 8/1/2017 FAIL
DetailsKatelyn Menuge
Routing - PLUMBING7/31/2017 8/1/2017 FAIL
DetailsDaryl Spivey
1) Change 2 floor sinks and 1 floor drain in cooking area to drain to grease instead of sanitary.
2) Change drainage on island area to drain to floor sinks and not a combination waste and vent system.
Routing - Addressing7/31/2017 8/1/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS7/31/2017 8/1/2017 PASS
DetailsRachael Beierle
Intake Approval  7/31/2017 PASS
DetailsAdele J Schaffeld-Griffin
Carl M approved pre screen, CDH approval uploaded
Intake Approval  7/28/2017 FAIL
First pre-screen 7-28-17
Please provide the special inspection start-up form 310
Application received  7/27/2017 DONE
Application submitted via PDS Online on Jul 27 2017 2:46PM