BLD-Aging Inspection | 7/12/2018 | 7/12/2018 | 7/12/2018 | | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Mike Jordan
|
|
|
Kitchen walls Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Energy code compliance | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | PART |
Mike Jordan
|
|
|
Only need upstairs master bedroom addition inspected. We would like to start sheetrocking master bedroom. Phone #: ###-#### Inspection requested via web by Andrew Clark. Framing in master bedroom ok, pending mech rough in inspection for vent. fans. Also discussed hard wiring provisions for the smoke detectors.
|
BLD-Framing/Rough-in | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Mike Jordan
|
|
|
We have new engineering for lvl beams. Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Framing/Rough-in | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need mech rough in, Not as per plans- (3) 2x8 DF beams at front porch, (2) 5x9 Glue Lams at back porch with attachment bracket, LvLs used, instead- provide engineering and fastener schedule for as built.
|
Issue PAID IN FULL permit | | | 1/8/2018 | | DONE |
|
|
|
|
Telephone call | | | 1/5/2018 | | DONE |
|
|
|
called Victor to let know there were still fees due-once they're paid we will have him sign the permits and release e plan so they can print them out
|
Expiration Notice | 1/2/2018 | 1/23/2018 | 1/2/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 9/21/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 8/2/2017 | 8/2/2017 | 9/21/2017 | | PASS |
Josh Bogle
|
|
|
1st done - need uplift engineering & wall sections
|
Routing - PLAN CHECK | 9/21/2017 | | 9/21/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 9/21/2017 | | DONE |
|
|
|
Need RP
|
Routing - PLAN CHECK | 9/8/2017 | | 9/8/2017 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 8/3/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/2/2017 | | 8/3/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 8/2/2017 | | 8/2/2017 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/2/2017 | | DONE |
|
|
|
|
Intake Approval | | | 8/2/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/2/2017 | | DONE |
|
|
|
|
Application received | | | 7/28/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 28 2017 12:22PM
|