Plan Reviewer's activity | | | 4/3/2018 | | DONE |
Jason Blais
|
|
|
Work outlined in the Upgrade Agreement under permit BLD14-00374 completed under this permit.
|
Zoning Approval | 3/14/2018 | 3/14/2018 | 3/14/2018 | | DONE |
Andrea Tuning
|
|
|
|
First Notice | 3/9/2018 | 3/9/2018 | 3/14/2018 | | DONE |
Dave Hannah
|
|
|
Mailed 3-15-18
|
BLD-Final | 3/8/2018 | 3/9/2018 | 3/9/2018 | A | PASS |
Dave Hannah
|
|
|
Kelly Phone #: ###-####
|
DOC - Permit Finaled | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 12/18/2017 | 12/18/2017 | 12/19/2017 | P | DONE |
Dave Hannah
|
|
|
Kelly-cmu wall Phone #: ###-####
|
BLD-Framing/Rough-in | 12/18/2017 | 12/18/2017 | 12/19/2017 | P | PASS |
Dave Hannah
|
|
|
Kelly-cmu wall-please call 30 mintues prior to meet Phone #: ###-####
|
OVERRIDE | | | 8/30/2017 | | |
|
|
|
|
Plan assigned to (AJS) | 8/8/2017 | 8/8/2017 | 8/30/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st reveiw completed Jefferson Vet Clinic
|
Routing - PLAN CHECK | 8/30/2017 | | 8/30/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/30/2017 | | DONE |
|
|
|
Need
RP
Met
GC Rev cert of val
GC Form
|
Routing - PLAN CHECK | 8/28/2017 | | 8/28/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 8/23/2017 | | 8/23/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
spoke with Andrea she did not need DR to review change to parapet
|
Route to Impact Fee Review | 8/14/2017 | 8/17/2017 | 8/17/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - Erosion and Sediment | 8/8/2017 | | 8/14/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Minor exterior work and interior work; no RP designated on permit application
|
1st review completed | | | 8/14/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 8/8/2017 | | 8/11/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Design Review | 8/8/2017 | | 8/9/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Addressing | 8/8/2017 | | 8/8/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/8/2017 | | 8/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 8/8/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl M completed pre screen
|
Intake Approval | | | 8/3/2017 | | FAIL |
|
|
|
1st Pre-Screen 8/3/17
1. Please review the submittal requirements. Each plan sheet is required to be uploaded individually.
2. Provide the architectural stamp on all sheets.
3. Provide the verification of legal lot and parcel form signed and completed by a planning staff member.
4. Provide the registered design professional form 304.
5. Please provide the fire flow letter.
6. Provide handrail details adjacent to the new CMU walls and include termination details.
|
Intake Approval | | | 8/3/2017 | | FAIL |
|
|
|
Second Pre-Screen 8/3/17
1. Form 304 is required to be signed by the owner.
2. The handrail detail are still required.
3. When sheet A110 was re-uploaded the required engineers stamp was not include as it was on the original sheet.
|
Application received | | | 8/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 1 2017 2:57PM
|
BLD-Conference | 10/12/2017 | 10/12/2017 | | P | |
Dave Hannah
|
|
|
Kelly Phone #: ###-####-please call 30 mintues prior to meet
|