Print Statement | | | 1/18/2018 | | DONE |
|
|
|
|
First Notice | | 12/22/2017 | 1/11/2018 | | DONE |
|
|
|
Mailed 1-12-18
|
Permanent Occupancy | | | 12/12/2017 | | DONE |
|
|
|
|
BLD-Final | 12/11/2017 | 12/11/2017 | 12/11/2017 | P | PASS |
Jim Storey
|
|
|
We are scheduled to get our last signature needed before you can sign off early this afternoon (Electrical). Just giving you a heads up in case you can''t make it behind the electrical inspection and we have to do it in the morning tomorrow.Call me if you need too. Thx Phone #: ###-#### Inspection requested via web by Mike Beeson
|
FIRE-Final Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete to include mag-lock interface and release with fire alarm activation, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
|
BLD-Conference | 11/15/2017 | 11/16/2017 | 11/16/2017 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson exit signage/ occ/loading chair tables
|
FIRE-Final Inspection | 11/6/2017 | 11/7/2017 | 11/7/2017 | P | FAIL |
Jim Page
|
|
|
Doors with mag locks need to release under general fire alarm. Ceiling tiles need to be in place for fire sprinkler heat collection. Fire alarm permit needs to be in finaled status for life fire safety inspection to be completed.
|
BLD-Ceiling Grid Inspection | 10/25/2017 | 10/25/2017 | 10/25/2017 | P | PASS |
Jim Storey
|
|
|
Meet with Charlie please. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Ceiling Grid Inspection | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | FAIL |
Jim Storey
|
|
|
Meet with Charlie please. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Ceiling Grid Inspection | 10/20/2017 | 10/20/2017 | 10/20/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson 2nd floor east side
|
BLD-Ceiling Grid Inspection | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson 1st floor east 2 bays
|
BLD-Ceiling Grid Inspection | 10/9/2017 | 10/10/2017 | 10/10/2017 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson need primiter clips
|
BLD-Framing/Rough-in | 10/2/2017 | 10/3/2017 | 10/3/2017 | A | PASS |
Jim Storey
|
|
|
Mike Beeson Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 10/2/2017 | | DONE |
|
|
|
paid for plan mod
|
Plan assigned to (CDM) | 9/22/2017 | 9/22/2017 | 9/29/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/29/2017 | | 9/29/2017 | | PASS |
Carl D Madsen
|
|
|
|
Permit Ready to Issue | | | 9/29/2017 | | DONE |
|
|
|
DO NOT REISSUE - PLAN MOD
|
BLD-Framing/Rough-in | 9/25/2017 | 9/26/2017 | 9/26/2017 | A | PASS |
Jim Storey
|
|
|
2nd floor framing - Mike Phone #: ###-####
|
Route to Impact Fee Review | 9/22/2017 | 9/25/2017 | 9/22/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 9/22/2017 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Jim Storey
|
|
|
Framing Phone #: ###-#### Inspection requested via web by Mike Beeson first floor wall framing ok/ remove top plate screws to grid ceilling
|
BLD-Framing/Rough-in | 9/11/2017 | 9/12/2017 | 9/12/2017 | A | PART |
Jim Storey
|
|
|
Soffit framing and review site. Enter site from west side roll up door, temp field office inside building on 1st floor Phone #: ###-#### Inspection requested via web by Mike Beeson framing ok vertacal supports to be seen at ceilling insp/ arch. to address rated ceilling north west quadrant first floor.
|
Issue PAID IN FULL permit | | | 9/6/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/6/2017 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 8/8/2017 | 8/8/2017 | 9/1/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/8/2017 | | 9/1/2017 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/1/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/1/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/1/2017 | | DONE |
Christina Prado
|
|
|
Need:
GC Form - MET
Revised Certificate of Value - MET
|
Routing - FIRE | 8/8/2017 | 8/8/2017 | 8/15/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Intake Approval | | | 8/8/2017 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/8/2017 | | 8/8/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/8/2017 | | 8/8/2017 | | PASS |
Bill VanDegrift
|
|
|
1) see redline remarks for hubdrain 1st floor waste.
2) per plan and ISPC.
|
Routing - Addressing | 8/8/2017 | | 8/8/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/8/2017 | | 8/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 8/3/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2017 8:55AM
|