First Notice | 7/19/2018 | 7/19/2018 | 8/8/2018 | | DONE |
Jim Storey
|
|
|
mailed 8-10-18
|
BLD-Final | 7/18/2018 | 7/19/2018 | 7/19/2018 | A | PASS |
Jim Storey
|
|
|
Tim Brewer Phone #: ###-####
|
DOC - Permit Finaled | 7/19/2018 | 7/19/2018 | 7/19/2018 | P | PASS |
Jim Storey
|
|
|
|
PubWorks Occupancy Approval | 7/19/2018 | 7/19/2018 | 7/19/2018 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is located by the fire pump/riser room. Final life fire safety inspection complete.
Tim Phone #: ###-####
|
Zoning Approval | 7/17/2018 | 7/17/2018 | 7/17/2018 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Ceiling Grid Inspection | 7/2/2018 | 7/3/2018 | 7/3/2018 | P | PASS |
Brandon Shaw
|
|
|
Requests 1PM - John Phone #: ###-####
|
Plan assigned to (CJW) | 5/21/2018 | 5/21/2018 | 6/6/2018 | | PASS |
Carl Westfall
|
|
|
x Plan Modification - Gowen Industrial Park
|
Routing - PLAN CHECK | 6/4/2018 | | 6/6/2018 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 6/6/2018 | | PASS |
|
|
|
Approved the 3rd plan mod
|
Permit Ready to Issue | | | 6/6/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
CHANGE STATUS TO (ISS) | | | 6/6/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/6/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/4/2018 | | FAIL |
Julie Romig
|
|
|
Plan Mod #3: 1. Sheets G102, A701, E001 are listed as revised in the application, but new sheets were not found. Please upload.
2. Re-upload sheets A102, A901, M001 with the same file name as the sheet it is replacing. Sheets named differently and uploaded on 6/1 have been deleted.
|
Intake Approval | | | 6/4/2018 | | PASS |
|
|
|
|
Plan Modification Accepted | | | 6/1/2018 | | DONE |
|
|
|
Workflow in ePlanReview received
|
BLD-Framing/Rough-in | 5/24/2018 | 5/25/2018 | 5/25/2018 | A | PASS |
Jim Storey
|
|
|
John-south office-customer says this is not for the plan mod that''s in for review Phone #: ###-####
|
Plan Modification Accepted | | | 5/21/2018 | | DONE |
|
|
|
Plan modification to modified south office to only have two offices and no break room.
|
BLD-Conference | 5/15/2018 | 5/15/2018 | 5/15/2018 | P | PASS |
Jim Storey
|
|
|
|
Extend Permit 90/180 days | 5/15/2018 | 5/15/2018 | 5/15/2018 | P | PASS |
Jim Storey
|
|
|
to keep permit from exp.
|
CHANGE STATUS TO (ISS) | | | 5/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/14/2018 | | DONE |
|
|
|
|
Meeting | | | 5/11/2018 | | |
|
|
|
sent an email to david recommending to send in a request for an extension if permit is not going to be paid for and picked up in ten days
|
Plan assigned to (CJW) | 4/26/2018 | 4/26/2018 | 5/10/2018 | | PASS |
Carl Westfall
|
|
|
x plan mod (1st IBC done - routed back to applicant)
|
Routing - PLAN CHECK | 5/9/2018 | | 5/10/2018 | | PASS |
Carl Westfall
|
|
|
|
Routing - Design Review | 5/10/2018 | | 5/10/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH17-00215
|
Plan Reviewer's activity | | | 5/10/2018 | | PASS |
|
|
|
2nd plan mod approved
|
Permit Ready to Issue | | | 5/10/2018 | | DONE |
|
|
|
plan mod please do not re issue
|
BLD-Conference | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Jim Storey
|
|
|
John-fire riser room-fire rated walls penetration-as per John this has nothing to do with the plan mod in for review Phone #: ###-####
|
BLD-Other | 5/8/2018 | 5/9/2018 | 5/9/2018 | A | NR |
Jim Storey
|
|
|
John-fire riser room-fire rated walls penetration-as per John this has nothing to do with the plan mod in for review Phone #: ###-####
|
Plan resubmittals received | | | 5/9/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/3/2018 | | DONE |
|
|
|
|
Routing PW Drainage | 4/27/2018 | | 5/2/2018 | | PASS |
Jason C. Taylor
|
|
|
see odi grading approval
|
Routing PW Solid Waste | 5/1/2018 | | 5/2/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Sewer Design | 5/1/2018 | | 5/2/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Street Lights | 5/1/2018 | | 5/2/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - PUBLIC WORKS | 5/1/2018 | | 5/1/2018 | | PASS |
Rachael Beierle
|
|
|
Routed Only
|
Routing - MECHANICAL | 4/27/2018 | | 5/1/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing PW Sewer Rating | 5/1/2018 | | 5/1/2018 | | PASS |
Morgan Webb
|
|
|
NO PLUMBING FIXTURES IN BREAK ROOM
|
Routing - Design Review | 4/27/2018 | | 4/30/2018 | | FAIL |
Katelyn Menuge
|
|
|
Provide the additional required accessible parking stalls, bicycle stalls, and an updated Building B planting plan. Landscape planters shall be a minimum of 8 feet wide measured inside of curb and provide one Class II tree if serving a single row of parking or two Class II trees if serving a double row of parking.
|
Routing - PLAN CHECK | 4/26/2018 | | 4/27/2018 | | PASS |
Carl Westfall
|
|
|
2nd plan mod approved
|
Plan Modification Accepted | | | 4/26/2018 | | DONE |
|
|
|
modified south office to include 2 offices and a break room.
Modified east parking lot to have more spaces.
|
Plan assigned to (CJW) | 3/27/2018 | 3/27/2018 | 4/4/2018 | | PASS |
Carl Westfall
|
|
|
x Gowan Industrial Park Plan Mod
|
Routing - PLAN CHECK | 3/27/2018 | | 4/4/2018 | | PASS |
Carl Westfall
|
|
|
1st plan mod approved
|
Plan Reviewer's activity | | | 4/4/2018 | | DONE |
|
|
|
1st plan mod approved
|
Permit Ready to Issue | | | 4/4/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
Plan Modification Accepted | | | 3/27/2018 | | DONE |
|
|
|
Remove 1 hour rarted ceiling access hatch
|
BLD-Footing | 11/21/2017 | 11/22/2017 | 11/22/2017 | A | PASS |
Jim Storey
|
|
|
around 11 please- John Phone #: ###-#### mti si pending report
|
Inspection Record Card- Bld | | | 11/20/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/20/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/21/2017 | 8/21/2017 | 11/17/2017 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Sept 22 - 25 days) (93 sheets) Gowen Industrial Bldg C
|
Routing - Design Review | 11/16/2017 | | 11/17/2017 | | PASS |
Sarah Schafer
|
|
|
Re-routed to Sarah - Record of Survey was completed and building permit was approved through DR.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/17/2017 | | DONE |
|
|
|
NEED
ACHD
MET
RP
GC FORM
REVISE CERT
|
Routing PW Sewer Design | 11/7/2017 | | 11/14/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing Off Site - STRUCTURAL | 11/7/2017 | | 11/10/2017 | | PASS |
Carl Westfall
|
|
|
Chris Holladay
|
Routing - Design Review | 11/7/2017 | | 11/8/2017 | | FAIL |
Katelyn Menuge
|
|
|
Need ROS completed.
|
Plan resubmittals received | | | 11/7/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/7/2017 | | 11/7/2017 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Routing PW Sewer Design | 10/24/2017 | | 10/31/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Update utility plans using approved utility drawings from GRD17-00045.
|
Plan resubmittals requested | | | 10/31/2017 | | DONE |
|
|
|
|
Routing - FIRE | 10/24/2017 | | 10/30/2017 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to case
|
Routing Off Site - STRUCTURAL | 10/24/2017 | | 10/27/2017 | | FAIL |
Carl Westfall
|
|
|
Chris Holladay
|
Routing - PLAN CHECK | 10/23/2017 | | 10/24/2017 | | PASS |
Carl Westfall
|
|
|
pending structural
|
Routing - PLANNING Land Div | 10/24/2017 | | 10/24/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Design Review | 10/24/2017 | | 10/24/2017 | | FAIL |
Katelyn Menuge
|
|
|
Corrections Required and need ROS completed prior to building permit issuance
|
Plan resubmittals received | | | 10/23/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/20/2017 | 10/23/2017 | 10/20/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing PW Drainage | 8/22/2017 | | 10/20/2017 | | PASS |
Jason C. Taylor
|
|
|
|
1st review completed | | | 10/20/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/20/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/21/2017 | | 10/13/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing PW Environmental | 8/22/2017 | | 9/21/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Sewer Design | 8/22/2017 | | 9/6/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
|
Routing - FIRE | 8/21/2017 | 8/21/2017 | 9/1/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed architect correction item and plan review report. Attached report to case.
|
Routing Off Site - STRUCTURAL | 8/21/2017 | | 8/31/2017 | | FAIL |
Carl Westfall
|
|
|
Chris Holladay
|
Routing - PLUMBING | 8/21/2017 | | 8/24/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing PW Street Lights | 8/22/2017 | | 8/24/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 8/22/2017 | | 8/22/2017 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 8/22/2017 | | 8/22/2017 | | CANC |
Brian Murphy
|
|
|
JASON TAYLOR WILL REVIEW
|
Routing - PUBLIC WORKS | 8/21/2017 | | 8/22/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 8/21/2017 | | 8/22/2017 | | CANC |
Andy J. Long
|
|
|
No ESC plan review for this building, part of larger project. Need to have ESC plan submitted with GRD17-00045 approved before this permit can be issued. If buildings to be built seperately, each BLD will need an individual ESC permit.
|
Routing - MECHANICAL | 8/21/2017 | | 8/22/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - Design Review | 8/21/2017 | | 8/22/2017 | | FAIL |
Katelyn Menuge
|
|
|
Other planning approvals required and corrections needed to landscape.
|
Intake Approval | | | 8/21/2017 | | PASS |
|
|
|
|
Routing - PLANNING | 8/21/2017 | | 8/21/2017 | | CANC |
Cody Riddle
|
|
|
No review required
|
Routing - PLANNING Land Div | 8/21/2017 | | 8/21/2017 | | FAIL |
Todd Tucker
|
|
|
The Building Permit cannot be issued until the parcels are combined into one parcel.
|
Routing - Addressing | 8/21/2017 | | 8/21/2017 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 8/12/2017 | | FAIL |
|
|
|
2nd Pre-screen 8/12/17
Please provide a site plan, landscape plans and plant schedule that do not indicate for reference only as the building and landscape approvals occur under the building permit and not the GRD permit.
Provide an interior and exterior lighting compliance per IECC Comcheck.
|
Intake Approval | | | 8/11/2017 | | FAIL |
|
|
|
Please provide the completed form 502 checklist with all applicable items.
|
Application received | | | 8/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 8 2017 8:20PM
|