DOC - Permit Finaled | | | 10/5/2017 | | DONE |
|
|
|
|
BLD-Final | 9/6/2017 | 9/6/2017 | 9/7/2017 | P | DONE |
Bob Archibald
|
|
|
Dale Phone #: ###-####. Scope of work completed. Ok for bond release.
|
Fees Due Hold | 8/19/2017 | | 9/6/2017 | | DONE |
Christina Prado
|
|
|
fees paid
|
OVERRIDE | | | 8/18/2017 | | |
|
|
|
|
Issue & PRINT to be Invoiced | | | 8/18/2017 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 8/18/2017 | | DONE |
Christina Prado
|
|
|
All requirements met, fees to be JV'd
|
Routing - Erosion and Sediment | 8/11/2017 | | 8/11/2017 | | PASS |
Andy J. Long
|
|
|
General ESC permit issued to cover demolition. Post demolition, City of Boise ESC will assist in inspecting stabilization requirements.
|
Routing PW Grading-Hillside | 8/11/2017 | | 8/11/2017 | | PASS |
Jason C. Taylor
|
|
|
Site stabilization will be required as per the Hillside Ordinance. Public Works approval of stabilization will be required prior to permit final. Jason Taylor ###-####.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2017 | | DONE |
|
|
|
|
Application received | | 8/11/2017 | | | |
|
|
|
|