BLD-Framing/Rough-in | 9/27/2017 | 9/28/2017 | 9/28/2017 | A | PASS |
Tony Young
|
|
|
Call when you are on your way....Thanks, Ben Phone #: ###-#### Inspection requested via web by Ben Bade,, ok pending trades
|
Issue PAID IN FULL permit | | | 9/22/2017 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 8/14/2017 | 8/14/2017 | 9/21/2017 | | PASS |
Josh Bogle
|
|
|
1st done - need more information
|
Routing - PLANNING | 9/21/2017 | | 9/21/2017 | | PASS |
Sue Cummings
|
|
|
Site plan received
|
Routing - PLAN CHECK | 9/21/2017 | | 9/21/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2017 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy yes
|
Permit Ready to Issue | | | 9/21/2017 | | DONE |
|
|
|
all met
|
Routing - PLAN CHECK | 8/14/2017 | | 8/18/2017 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 8/18/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 8/14/2017 | | 8/14/2017 | | FAIL |
Sue Cummings
|
|
|
All buiding permits require a site plan
|
Plans ACCEPTED BY PLAN TECH | | | 8/14/2017 | | DONE |
|
|
|
|
Intake Approval | | | 8/14/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/14/2017 | | DONE |
|
|
|
no fees received at submittal
|
Application received | | | 8/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 12 2017 10:47AM
|