BLD-Final | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/3/2018 | 7/3/2018 | 7/3/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 5.3
|
BLD-Energy code compliance | 3/22/2018 | 3/26/2018 | 3/26/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 3/21/2018 | 3/22/2018 | 3/22/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 2/25/2018 | 2/26/2018 | 2/26/2018 | A | PASS |
Brandon Shaw
|
|
|
Shear Inspection Inspection requested via web by Erby Gonzales
|
BLD-Foundation | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
Frost protection required
|
BLD-Footing | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PASS |
Brandon Shaw
|
|
|
Thermal protection provided
Work in progress
|
Issue PAID IN FULL permit | | | 11/2/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/2/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/28/2017 | | |
|
|
|
|
Plan assigned to (JG) | 9/22/2017 | 9/22/2017 | 9/28/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 9/12 townhouse L2 ePlan, pend mech rev
|
Routing - PLAN CHECK | 9/28/2017 | | 9/28/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/28/2017 | | DONE |
|
|
|
|
1st review completed | | | 9/27/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/24/2017 | | 9/27/2017 | | FAIL |
Javier Guzman
|
|
|
failed Mech on sister permit BLD17-02944
|
Routing - MECHANICAL | 8/24/2017 | | 9/27/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/24/2017 | | 9/27/2017 | | PASS |
Sue Cummings
|
|
|
signed off in ePlan by Front Desk Planning Sue Cummings
|
Plan assigned to (BJM) | 8/24/2017 | 8/24/2017 | 9/22/2017 | | DEFR |
Brian McGowan
|
|
|
9/12 townhouse L2 ePlan
|
Route to Impact Fee Review | 8/24/2017 | 8/27/2017 | 8/25/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Flood Plain | 8/24/2017 | | 8/25/2017 | | PASS |
Jason C. Taylor
|
|
|
Project has approved LOMR on File. JCT
|
Plans ACCEPTED BY PLAN TECH | | | 8/24/2017 | | DONE |
|
|
|
|
Intake Approval | | | 8/24/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/24/2017 | | DONE |
|
|
|
|
Routing - Addressing | 8/24/2017 | | 8/24/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/24/2017 | | 8/24/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 8/15/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2017 12:47PM
|