BLD-Framing/Rough-in | 4/13/2020 | 4/14/2020 | 4/14/2020 | P | PASS |
Mike Jordan
|
|
|
video/photo ok // John Phone #: ###-####
|
Telephone call | | | 4/14/2020 | | DONE |
|
|
|
John Rott (pronounced rote) requested an inspection. I called and left a VM letting them know that we are not scheduling inspections on occupied buildings at this time, but they may request a virtual inspection.
|
BLD-Framing/Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Rott
|
BLD-Conference | 6/14/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. WIP.
|
BLD-Framing/Rough-in | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | NR |
Mike Jordan
|
|
|
(and shear) John Rott Phone #: ###-####. Wall brCING ONLY. nEEDS TO ADD ADDITIONAL KING STUDS AND ROUGH IN ELECTRICAL
|
BLD-Wall Bracing | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Mike Jordan
|
|
|
(and shear) John Rott Phone #: ###-####
|
BLD-Footing | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | PASS |
Mike Jordan
|
|
|
patio cover footing // John Rott Phone #: ###-####. Footings for new patio cover ok.
|
BLD-Framing/Rough-in | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | PASS |
Mike Jordan
|
|
|
patio cover footing // John Rott Phone #: ###-####. Raised roof portion of garage. Ok to install siding.
|
Routing Walk-In (Zoning) | 12/20/2017 | 12/20/2017 | 12/20/2017 | A | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 12/20/2017 | 12/20/2017 | 12/20/2017 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 12/20/2017 | | 12/20/2017 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 12/20/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 12/20/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 12/20/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/20/2017 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 9/6/2017 | 9/6/2017 | 9/6/2017 | A | FAIL |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 8/16/2017 | 8/16/2017 | 8/16/2017 | A | FAIL |
Josh Bogle
|
|
|
had a conversation about needed documentation: 406 checklist, tall wall engineering for lateral & hinge points
|
1st review completed | | | 8/16/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/16/2017 | | 8/16/2017 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 8/16/2017 | | | |
|
|
|
|