BLD-Final | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####
|
DOC - Permit Finaled | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
FIRE-Final Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | CANC |
Troy Cobbley
|
|
|
No life safety sign off required per the project details
AS LATE AS POSSIBLE // Mark Phone #: ###-####
|
BLD-Final | 3/19/2018 | 3/20/2018 | 3/20/2018 | A | NR |
Tony Young
|
|
|
Mark Phone #: ###-####
|
BLD-Final | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | NR |
Tony Young
|
|
|
Mark Phone #: ###-####,, need trades
|
BLD-Wall cover | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####,, interior shear ok after more nailing in master
|
BLD-Energy code compliance | 1/10/2018 | 1/10/2018 | 1/10/2018 | P | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 1/8/2018 | 1/9/2018 | 1/9/2018 | A | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 1/2/2018 | 1/2/2018 | 1/2/2018 | P | NR |
Tony Young
|
|
|
Mark and air seal Phone #: ###-####,, walk through only,, needs mechanical 1st
|
BLD-Wall Bracing | 12/22/2017 | 12/22/2017 | 12/22/2017 | P | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####,, exterior ok
|
BLD-Wall Bracing | 12/21/2017 | 12/22/2017 | 12/22/2017 | A | PASS |
Tony Young
|
|
|
Shear // Mark Phone #: ###-####
|
BLD-Wall Bracing | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | FAIL |
Tony Young
|
|
|
Shear // Mark Phone #: ###-####,, re-nail,, see paint,, re-call inspection
|
BLD-Footing | 10/20/2017 | 10/23/2017 | 10/23/2017 | P | PART |
Tony Young
|
|
|
Matt Phone #: ###-####,, work in progress
|
Issue PAID IN FULL permit | | | 10/10/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/10/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/9/2017 | | |
|
|
|
|
Plan assigned to (RDP) | 10/9/2017 | 10/9/2017 | 10/9/2017 | | DONE |
Rob Patrick
|
|
|
|
Plan Reviewer's activity | | | 10/9/2017 | | DONE |
Rob Patrick
|
|
|
|
1st review completed | | | 10/9/2017 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2017 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 10/9/2017 | | DONE |
|
|
|
all met
|
Routing - PLAN CHECK | 8/18/2017 | | 10/9/2017 | | PASS |
Brian McGowan
|
|
|
Sent to Brian for review.
|
Routing - MECHANICAL | 8/18/2017 | | 8/25/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/18/2017 | 8/21/2017 | 8/23/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 8/18/2017 | | 8/21/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan assigned to (BJM) | 8/18/2017 | 8/18/2017 | 8/18/2017 | | DEFR |
Brian McGowan
|
|
|
9/31 sfd ePlan
|
Routing - PLANNING | 8/18/2017 | | 8/18/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 8/18/2017 | | 8/18/2017 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/18/2017 | | DONE |
|
|
|
|
Intake Approval | | | 8/18/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/18/2017 | | DONE |
|
|
|
|
Application received | | | 8/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 17 2017 12:36PM
|
Intake Approval | | | 8/17/2017 | | FAIL |
|
|
|
drawings need to go in the drawings folder,,,indivually uploaded, facing the correct way and named appropriately
|