Print Occupancy Form | | | 5/24/2018 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 5/24/2018 | | DONE |
|
|
|
|
First Notice | 4/18/2018 | 4/18/2018 | 5/10/2018 | | DONE |
Mike Jordan
|
|
|
mailed 5-11-18
|
BLD-Final | 4/18/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Mike Jordan
|
|
|
Please call Eric 30 minutes in advance for access. Thank you! Phone #: ###-#### Inspection requested via web by Eric Murphy
|
DOC - Permit Finaled | 4/18/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 4/16/2018 | 4/16/2018 | 4/16/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, fire alarm inspection is complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
|
BLD-Final | 4/14/2018 | 4/16/2018 | 4/16/2018 | A | FAIL |
Mike Jordan
|
|
|
Please call Joe 30 minutes in advance for access. Phone #: ###-#### Inspection requested via web by Eric Murphy. Install the required occupancy sensors. Needs fire/life/safety final as well.
|
FIRE-Final Inspection | 4/14/2018 | 4/16/2018 | 4/16/2018 | A | FAIL |
Jim Page
|
|
|
Phone number provided was not for Joe, drove to inspection location and space was locked with no access, inspection request will need to be rescheduled and a correct phone number provided.
This inspection is for fire / life / safety. Please call Joe 30 minutes in advance for access. Phone #: ###-#### Inspection requested via web by Eric Murphy
|
BLD-Ceiling Grid Inspection | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | PART |
Mike Jordan
|
|
|
Please call 30 minutes in advance for access Phone #: ###-#### Inspection requested via web by Eric Murphy. grid ok. Need to patch and fire caulk above grid at corridor wall.
|
BLD-Framing/Rough-in | 12/18/2017 | 12/18/2017 | 12/18/2017 | P | PART |
Mike Jordan
|
|
|
Please call 1 hour ahead for access. Phone #: ###-#### Inspection requested via web by Eric Murphy. Interior steel stud framed walls only. Noted adiitional work needed to protect membrane and through penetrarions on corridor wall.
|
Inspection Record Card- Bld | | | 10/20/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/20/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 8/25/2017 | 8/25/2017 | 9/6/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 8/31 L1 Medical Office Tenant Improvement ePlan
|
Routing - PLAN CHECK | 9/5/2017 | | 9/6/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/6/2017 | | DONE |
|
|
|
Need GC
Need revised cert of value
|
Route to Impact Fee Review | 8/31/2017 | 9/3/2017 | 9/1/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 8/25/2017 | | 8/31/2017 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 8/31/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 8/25/2017 | | 8/28/2017 | | PASS |
Laura Hunter
|
|
|
Ste 302
|
Routing - PUBLIC WORKS | 8/25/2017 | | 8/25/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 8/25/2017 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 8/22/2017 | | FAIL |
Julie Romig
|
|
|
Need:
1. Complete Level 3 Floor plan showing exiting and restrooms.
2. Wall bracing detail
3. Door hardware schedule for existing doors.
|
Application received | | | 8/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 20 2017 11:01AM
|