Meeting | | | 1/11/2019 | | DONE |
|
|
|
emailed leslie schulz to go over the ele and plm values she provided before printing and mailing out statements (would be $3,800 & $6,100)
|
Meeting | | | 12/21/2018 | | DONE |
|
|
|
emailed leslie asking her to please provide the final value for fire alarm system
|
Third Notice | | 11/12/2018 | 12/14/2018 | | DONE |
|
|
|
mailed 12-17
|
Second Notice | | 10/22/2018 | 11/7/2018 | | DONE |
|
|
|
mailed 11-12
|
First Notice | | 9/28/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
Temporary Occupancy | 9/18/2018 | 12/17/2018 | 9/18/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok'd temp c of o extension goor for 60 days from 9/18/18
|
Permanent Occupancy | | | 9/18/2018 | | DONE |
|
|
|
parcel R0066200020 & R0066200030 & R0066200040
|
Telephone call | | | 9/18/2018 | | DONE |
|
|
|
Called Ben about the temp c of o that needs finaled or extended-he will email Jason Blais for an extension
|
BLD-Final | 9/11/2018 | 9/12/2018 | 9/12/2018 | P | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Final | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | CANC |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
FIRE-Final Inspection | 7/31/2018 | 8/1/2018 | 8/1/2018 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection complete.
Jeff Phone #: ###-####
|
Temporary Occupancy | 7/19/2018 | 10/17/2018 | 7/19/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason B ok'd ext for TCO good for 60 days
|
Telephone call | | | 7/17/2018 | | DONE |
|
|
|
called Ben to let know TCO is expired-left massge on phone
|
BLD-Aging Inspection | 5/30/2018 | 5/30/2018 | 5/30/2018 | | PEND |
Dave Hannah
|
|
|
|
Temporary Occupancy | 4/4/2018 | 7/3/2018 | 4/4/2018 | | DONE |
Candy A. Nichols
|
|
|
Jason ok a 90 day extension from 4/18/18
|
Temporary Occupancy | 4/4/2018 | 7/3/2018 | 4/4/2018 | | DONE |
Candy A. Nichols
|
|
|
put in wrong date-7-6-18 was wrong should have been 7-16-18
|
Temporary Occupancy | 4/4/2018 | 7/3/2018 | 4/4/2018 | | DONE |
Candy A. Nichols
|
|
|
7/3/18 is wrong date, should be 7/16/18
|
BLD-Aging Inspection | 3/19/2018 | 3/19/2018 | 3/23/2018 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 1/11/2018 | 1/16/2018 | 1/17/2018 | P | DONE |
Dave Hannah
|
|
|
Robert Phone #: ###-####
|
BLD-Final | 1/16/2018 | 1/17/2018 | 1/17/2018 | A | PART |
Dave Hannah
|
|
|
TCO - Robert Phone #: ###-#### ok for temp occ
|
Temporary Occupancy | 1/17/2018 | 4/17/2018 | 1/17/2018 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 1/11/2018 | 1/16/2018 | 1/16/2018 | A | PART |
Jim Page
|
|
|
Partial final inspection for TI space complete, fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Permit will remain in issued status until core/shell garage permit is complete and finaled.
|
BLD-Ceiling Grid Inspection | 1/4/2018 | 1/8/2018 | 1/9/2018 | A | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/9/2018 | 1/9/2018 | 1/9/2018 | A | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
Print Occupancy Form | | | 1/5/2018 | | DONE |
|
|
|
|
BLD-Energy code compliance | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 11/28/2017 | 11/29/2017 | 11/30/2017 | P | PART |
Dave Hannah
|
|
|
Jeff Phone #: ###-#### ok to one side walls and cover ext walls
|
Issue PAID IN FULL permit | | | 10/19/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/19/2017 | | DONE |
|
|
|
|
Routing - FIRE | 10/6/2017 | 10/6/2017 | 10/9/2017 | | PASS |
Erika Akin
|
|
|
Revised comments attached to case
|
Plan assigned to (CDM) | 8/30/2017 | 8/30/2017 | 10/9/2017 | | PASS |
Carl D Madsen
|
|
|
Parcel B Chamber of Commerce
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/9/2017 | | DONE |
Christina Prado
|
|
|
ALL MET
Need
GC Form - MET
Revised Cert of Value - MET
|
Routing - PLAN CHECK | 10/6/2017 | | 10/9/2017 | | PASS |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 10/5/2017 | 10/8/2017 | 10/5/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 10/5/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/30/2017 | | 10/5/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 8/30/2017 | 8/30/2017 | 9/15/2017 | | FAIL |
Erika Akin
|
|
|
Emailed correction items to architect and attached comments to plan
|
Routing - Design Review | 8/30/2017 | | 9/1/2017 | | PASS |
Sarah Schafer
|
|
|
|
Routing - PUBLIC WORKS | 8/30/2017 | | 8/31/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - MECHANICAL | 8/30/2017 | | 8/30/2017 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 8/30/2017 | | 8/30/2017 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 8/30/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl M completed pre screen. Alternate uploaded in e plan under agency comments
|
Application received | | | 8/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 22 2017 11:11AM
|