Permit Information
Permit NumberBLD17-03005
StatusFinaled
Name HAMMETT HOMES
Site Address 2171 W BENT BOW CT
Project Name2-4 Eyrie Canyon
Customer Number 
ePlanReviewYes
Description
***Plan Modification 8-2-18 - Adding exterior gas fireplace. Approved of by Ron Hill. ***BJM*** HILLSIDE, WUI FOOTHILLS, ZONE "A" REQUIREMENTS, CLASS "A" ROOF REQUIRED. Permit for the construction of a new 2773 sq. ft., two story (first story 2308 sq. ft., second story 465 sq. ft.) single family dwelling with 3 bedrooms, 3.5 bathrooms, approximately 240 sq. ft. of covered patio/porch and a 944 sq. ft. attached garage per the approved plans and any notations. A-1 zoning and setbacks per planning. ***BJM***..A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor 208-608-7171.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Jason Taylor 208-608-7171.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/28/20188/29/20188/29/2018APASS
DetailsTony Young
call for access info // Craig Hammett Phone #: ###-####
DOC - Permit Finaled8/29/20188/29/20188/29/2018PPASS
DetailsTony Young
BLD-Final8/27/20188/28/20188/28/2018APART
DetailsTony Young
call for access info // Craig Hammett Phone #: ###-####,, ok pending hillside
PubWorks Occupancy Approval8/28/20188/28/20188/28/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Conference8/16/20188/16/20188/16/2018PPART
DetailsTony Young
Craig-call for access code Phone #: ###-####,, walk through for final,, most ok,, needs hillside
BLD-Final8/15/20188/16/20188/16/2018ANR
DetailsTony Young
Craig-call for access code Phone #: ###-####,, needs trades, hillside
BLD-Wall Bracing5/25/20185/25/20185/25/2018PPASS
DetailsTony Young
interior shear ok
BLD-Other5/24/20185/25/20185/25/2018APASS
DetailsTony Young
Soffits - Joel Phone #: ###-####,, base layer ok
BLD-Framing/Rough-in5/16/20185/17/20185/17/2018APASS
DetailsTony Young
Framing Re-inspection. Thank you! Phone #: ###-#### Inspection requested via web by Craig Hammett
BLD-Framing/Rough-in5/11/20185/14/20185/14/2018AFAIL
DetailsTony Young
Framing re-inspection. Thank you! Phone #: ###-#### Inspection requested via web by Craig Hammett,, fixes not complete,, see correction notice,, truss braces,, truss fix
BLD-Energy code compliance5/11/20185/14/20185/14/2018APART
DetailsTony Young
Framing re-inspection and energy inspection. Thank you! Phone #: ###-#### Inspection requested via web by Craig Hammett,, still needs framing fixes
BLD-Framing/Rough-in5/9/20185/10/20185/10/2018AFAIL
DetailsTony Young
Thank you! Phone #: ###-#### Inspection requested via web by Craig Hammett,, correction posted on truss engineering sheet,, ok to insulate
BLD-Wall Bracing3/28/20183/30/20183/30/2018APASS
DetailsJim Storey
Craig Phone #: ###-####
BLD-Foundation3/9/20183/12/20183/12/2018APASS
DetailsTony Young
Early as possible - John Phone #: ###-####
BLD-Footing3/7/20183/7/20183/7/2018PPASS
DetailsTony Young
John Phone #: ###-####
PubWorks Subgrade Approval2/14/20182/14/20182/14/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
Issue PAID IN FULL permit  12/21/2017 DONE
Inspection Record Card- Bld  12/21/2017 DONE
OVERRIDE  12/11/2017  
Plan assigned to (BJM)10/5/201710/5/201712/11/2017 DONE
DetailsBrian McGowan
Hillside needs to final-1st review complete - FAIL - No WUI Details or notes. 10/24 sfd L2 ePlan
Routing PW Grading-Hillside12/11/2017 12/11/2017 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor ###-####.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Jason Taylor ###-####.
PLANS/APPL TAKEN TO FRONT DESK  12/11/2017 DONE
DetailsBrian McGowan
Permit Ready to Issue  12/11/2017 DONE
met
Routing - PLAN CHECK12/7/2017 12/7/2017 PASS
DetailsBrian McGowan
Routing PW Grading-Hillside11/6/2017 11/7/2017 FAIL
DetailsMelissa Jannusch
Corrections required:

Remove not for construction
Add details for:
Drainage swale
Down spout connections
Foundation drains
Add a clean out and indicate location
1st review completed  11/6/2017 FAIL
DetailsBrian McGowan
No WUI Details or notes.
Routing - PLAN CHECK10/5/2017 11/6/2017 FAIL
DetailsBrian McGowan
No WUI Details or notes.
Routing - PLANNING10/5/2017 11/6/2017 PASS
DetailsDavid Moser
Approved as per the redline. The driveway shall not exceed 33 ft wide in front setback
Routing - MECHANICAL10/5/2017 10/10/2017 PASS
DetailsTroy James
Route to Impact Fee Review10/5/201710/8/201710/6/2017 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - FIRE10/5/201710/5/201710/6/2017 PASS
DetailsErika Akin
Plans were reviewed for FD access, availability of hydrants and defensible space.
Routing - Addressing10/5/2017 10/5/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS10/5/2017 10/5/2017 PASS
DetailsMorgan Webb
ROUTED TO HILLSIDE
Routing - Erosion and Sediment10/5/2017 10/5/2017 PASS
DetailsAndy J. Long
ESC plan approved. Certified PD and RP designated. ESC site preparation inspection is required before excavation and after BMP installation, call ###-####.
Plans ACCEPTED BY PLAN TECH  10/5/2017 DONE
Recd Pcfee & Taken To Pln CK  10/5/2017 DONE
Intake Approval  10/5/2017 PASS
Intake Approval  9/11/2017 FAIL
foundation plan aren't not stamped & signed, plans are facing the wrong way and 8.5x11
Intake Approval  8/24/2017 FAIL
DetailsChristina Prado
See checklist report under ePlanReview project reports
Application received  8/22/2017 DONE
Application submitted via PDS Online on Aug 22 2017 4:22PM