BLD-Final | 5/10/2018 | 5/10/2018 | 5/11/2018 | P | PASS |
Tony Young
|
|
|
Coco Phone #: ###-####
|
DOC - Permit Finaled | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/2/2018 | 5/3/2018 | 5/3/2018 | A | NR |
Tony Young
|
|
|
Coco Phone #: ###-####,, needs an address posted,, firecaulk the garage ceiling and wall
|
BLD-Energy code compliance | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Tony Young
|
|
|
Coco Phone #: ###-####
|
BLD-Wall cover | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Tony Young
|
|
|
Coco Phone #: ###-####
|
BLD-Framing/Rough-in | 1/4/2018 | 1/9/2018 | 1/9/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insilate
|
Plan Modification Accepted | | | 1/3/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 1/3/2018 | | 1/3/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 11/21/2017 | 11/24/2017 | 11/24/2017 | A | PASS |
Tony Young
|
|
|
Coco Phone #: ###-####
|
BLD-Foundation | 10/12/2017 | 10/13/2017 | 10/13/2017 | P | PASS |
Tony Young
|
|
|
Tyler Phone #: ###-####
|
BLD-Footing | 10/10/2017 | 10/12/2017 | 10/12/2017 | A | PASS |
Tony Young
|
|
|
Eric Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/6/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/5/2017 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/5/2017 | | DONE |
|
|
|
|
Telephone call | | | 10/5/2017 | | DONE |
|
|
|
called CoCo to let know permit is ready and how muich is owed-left message on her phone
|
Plan assigned to (M_H) | 10/2/2017 | | 10/5/2017 | | DONE |
Michael Hanson
|
|
|
9/07 sfd L1 paper - 1st review complete waiting for response 10/3 MDH
|
1st review completed | | | 10/5/2017 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 10/5/2017 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 10/5/2017 | | DONE |
|
|
|
All Met
|
Routing - PLAN CHECK | 8/30/2017 | | 10/5/2017 | | PASS |
Brian McGowan
|
|
|
|
Plan resubmittals received | | | 10/4/2017 | | DONE |
Christina Prado
|
|
|
Received two sest of revised roof details, as well as truss calcs; Plans stamped and taken to M_H for further review
|
Plan assigned to (BJM) | 8/25/2017 | 8/25/2017 | 10/2/2017 | | DEFR |
Brian McGowan
|
|
|
9/07 sfd L1 paper
|
Plan Reviewer's activity | | | 10/2/2017 | | DONE |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 8/28/2017 | | 8/30/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/25/2017 | | 8/28/2017 | | PASS |
Sue Cummings
|
|
|
Driveway not to exceed 33' wide in front setback
|
Route to Impact Fee Review | 8/25/2017 | 8/28/2017 | 8/27/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 8/25/2017 | | 8/25/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 8/25/2017 | | PASS |
|
|
|
|
Intake Approval | | | 8/25/2017 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/25/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/25/2017 | | DONE |
|
|
|
|
Application received | | | 8/24/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 24 2017 12:06PM //8/24/17 canclled eplan workflow, customer brought in paper plans /leg
|