First Notice | | 2/8/2020 | 2/12/2020 | | DONE |
|
|
|
This permit finaled on the web by Neil Smart
|
Print Occupancy Form | | | 1/29/2020 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/29/2020 | | DONE |
|
|
|
|
BLD-Final | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Tell Riley
|
|
|
Sherry Phone #: ###-####//no inspection card to sign//final complete per scope of work for infill and wall//door hardware was changed//
|
FIRE-Final Inspection | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
call ahead -Sherry Phone #: ###-####
|
FIRE-Final Inspection | 10/3/2019 | 10/4/2019 | 10/4/2019 | P | FAIL |
Troy Cobbley
|
|
|
Remove the thumbturn deadbolt at the main exit (keyed ok), provide annual inspection for the fire extinguishers, mount the fire extinguishers no higher than 5', remove the chain/padlock from door as per discussion.
Sherry Phone #: ###-####
|
FIRE-Final Inspection | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide city approved package/drawings. I noted thumbturn deadbolt on main exit and expired fire extinguishers.
SHERRY Phone #: ###-####
|
BLD-Final | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PART |
Tell Riley
|
|
|
NO ELE WORK PER JULIE R // cheri Phone #: ###-####//need fire life safety//
|
Issue PAID IN FULL permit | | | 2/13/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/13/2019 | | DONE |
|
|
|
|
Meeting | | | 2/12/2019 | | DONE |
|
|
|
Informed sherry the GC will need to send in a 306 form for both units since they are on the same set of plans and will have to be issued together
|
Meeting | | | 2/5/2019 | | DONE |
|
|
|
informed sherry that this permit is going to expire in 11 days and has already been granted to two extensions allowed. informed her that this permit will need to be paid for, along with BLD18-02473, or voided and reapply at a later date.
|
Expiration Notice | 1/24/2019 | 2/14/2019 | 1/24/2019 | | DONE |
Brittany Hill
|
|
|
|
Routing - PLANNING | 11/15/2017 | | 11/16/2018 | | PASS |
Brent Moore
|
|
|
|
Extend Review Timeline | | | 8/6/2018 | | DONE |
|
|
|
Final approved 180 day extension per Adele. See documents
|
Expiration Notice | 7/24/2018 | 8/14/2018 | 7/24/2018 | | DONE |
Brittany Hill
|
|
|
|
Permit Ready to Issue | | | 7/16/2018 | | DONE |
|
|
|
(Do not issue without Bld18-02473)
MET
Need:
Cert of value form GC
MET
reviesed application showing correct applicant,
GC from
|
Plan assigned to (JAR) | 11/15/2017 | 11/15/2017 | 7/13/2018 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 07/13 3rd Rec'd- L3 Escape This Live Boise Suite 104
|
Routing - PLAN CHECK | 7/13/2018 | | 7/13/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/5/2018 | | 7/11/2018 | | FAIL |
Julie Romig
|
|
|
|
Extend Review Timeline | | | 2/8/2018 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
Route to Impact Fee Review | 12/12/2017 | 12/15/2017 | 12/14/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 12/12/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 11/15/2017 | | 12/12/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required. Plan Review report emailed to architect.
|
Routing - PLANNING Land Div | 11/15/2017 | | 11/27/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - FIRE | 11/15/2017 | 11/15/2017 | 11/17/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing - PUBLIC WORKS | 11/15/2017 | | 11/16/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 11/15/2017 | | PASS |
|
|
|
|
Routing - Addressing | 11/15/2017 | | 11/15/2017 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 10/26/2017 | | FAIL |
Julie Romig
|
|
|
Need
1. Planning and Zoning letters of approval for CUP.
2. Checklist indicates Modification to Code. Provide alternate request letter approved by building official.
3. Update Code Analysis on to reflect project - currently states project is an "I-3 Condition" Occupancy.
|
Application received | | | 8/25/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 25 2017 2:54PM
|