Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD17-03066
StatusFinaled
Name SPECTRUM WIRELESS SOLUTIONS LLC
Site Address 1205 W BANNOCK ST
Project NameVerizon Wireless
Customer Number 
ePlanReviewYes
Description
(VERIZON WIRELESS – BOI IDAHO POWER SC) Permit to erect on existing rooftop parapet an approximately 14’ 6” steel pipe for a single Verizon antenna w/CMRO’s at base of antenna steel pipe mount. work to include: at roof (1) Commscope NH360QM-DG-2XR Omni antenna, (2) Alcatel 9768 compact metro radio outdoor (CMRO’s) antennas, (1) 2 3/8” steel pipe w/pipe mount, (1) GPS antenna, (1) Commscope CBC6926T-DL-4310 diplexer, (2) antenna cable lines and electrical work. Structural engineering and plans provided. Note: special inspection required, see attached form #310 in small documents. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/7/20183/7/20183/7/2018PPASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Josh Woodbeck,, they got a fix from the engineer to through bolt the connections per Josh,, ok
DOC - Permit Finaled3/7/20183/7/20183/7/2018PPASS
DetailsTony Young
done
Issue PAID IN FULL permit  11/21/2017 DONE
Inspection Record Card- Bld  11/21/2017 DONE
Permit Ready to Issue  9/25/2017 DONE
Need:
GC form
Revised value
Plan assigned to (JG)9/5/20179/5/20179/22/2017 PASS
DetailsJavier Guzman
1st rev comp, 9/18 L2 Verizon BOI Idaho Power SC ePlan
Routing - Design Review9/22/2017 9/22/2017 PASS
DetailsKatelyn Menuge
DRH17-00406
Routing - PLAN CHECK9/22/2017 9/22/2017 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  9/22/2017 DONE
Route to Impact Fee Review9/19/20179/22/20179/21/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE9/5/20179/5/20179/19/2017 PASS
DetailsScott Arellano
No review required for IFC
1st review completed  9/19/2017 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK9/5/2017 9/16/2017 FAIL
DetailsJavier Guzman
Routing - PLANNING9/5/2017 9/5/2017 PASS
DetailsNicolette Womack
Routing - Addressing9/5/2017 9/5/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS9/5/2017 9/5/2017 PASS
DetailsRachael Beierle
Intake Approval  9/5/2017 PASS
DetailsJavier Guzman
Routing - Design Review9/5/2017 9/5/2017 FAIL
DetailsKatelyn Menuge
Design Review currently under review. Will review building application after DR is issued and appeal period is over.
Intake Approval  8/29/2017 FAIL
DetailsMichael Hanson
Provide structural calc's
Plan Reviewer's activity  8/29/2017 DONE
DetailsMichael Hanson
Route to design review for approval
Application received  8/28/2017 DONE
Application submitted via PDS Online on Aug 28 2017 11:35AM
First Notice3/7/20183/7/2018   
DetailsTony Young