BLD-Footing | 10/17/2017 | 10/18/2017 | 10/18/2017 | A | PART |
Jim Sly
|
|
|
footing/conference // call for directions // Joe Phone #: ###-#### OK pending MTI special inspection, tests and approvals Rick Cummings Public Works also overseeing progress.
|
(F) Reprint permit | | | 10/2/2017 | | DONE |
|
|
|
|
Issue & PRINT to be Invoiced | | | 9/29/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/28/2017 | | |
|
|
|
|
Route to Impact Fee Review | 9/25/2017 | 9/28/2017 | 9/28/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 9/28/2017 | | DONE |
|
|
|
Need:
GC form
Revised value
|
Plan assigned to (JAR) | 9/14/2017 | 9/14/2017 | 9/27/2017 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - L3 City of Boise Sewer Treatment
|
Routing - PLAN CHECK | 9/27/2017 | | 9/27/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2017 | | DONE |
|
|
|
|
1st review completed | | | 9/25/2017 | | FAIL |
Julie Romig
|
|
|
Need stamped drawings.
|
Routing - Erosion and Sediment | 9/22/2017 | | 9/22/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid PD and RP desingated. ESC site preparation inspection is required prior to starting construction.
|
Routing - PLAN CHECK | 9/14/2017 | | 9/22/2017 | | FAIL |
Julie Romig
|
|
|
Need stamped drawings.
|
Routing - PLUMBING | 9/14/2017 | | 9/18/2017 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing - PLANNING Land Div | 9/14/2017 | | 9/15/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 9/14/2017 | | 9/15/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/14/2017 | | 9/15/2017 | | PASS |
Rachael Beierle
|
|
|
NO NEW PLUMBING.
|
Print Statement | | | 9/15/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 9/14/2017 | | 9/14/2017 | | PASS |
Nicolette Womack
|
|
|
|
Plan Reviewer's activity | | | 9/14/2017 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 9/14/2017 | | PASS |
|
|
|
|
Intake Approval | | | 9/12/2017 | | FAIL |
|
|
|
(9-12-17) Please refer to the circled items in the Plan Intake Checklist. Please resolve each item as directed.
|
Intake Approval | | | 9/12/2017 | | FAIL |
|
|
|
(9-12-17) Please refer to the circled items in the Plan Intake Checklist. Some were resolved some were not. Please resolve each item as directed.
|
Application received | | | 8/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2017 10:26AM
|