(F) Reprint permit | | | 11/3/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/30/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/8/2017 | 9/11/2017 | 9/11/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 9/11/2017 | | DONE |
|
|
|
ALL MET
Need:
GC
Revised value
|
Plan assigned to (RMH) | 9/7/2017 | 9/7/2017 | 9/8/2017 | | PASS |
Ron Hill
|
|
|
|
1st review completed | | | 9/8/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/8/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/7/2017 | | 9/8/2017 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (JG) | 9/7/2017 | 9/7/2017 | 9/7/2017 | | DEFR |
Javier Guzman
|
|
|
9/13 L1 BWW Kitchen AC ePlan
Deferred to Ron Hill
|
Intake Approval | | | 9/7/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 9/7/2017 | | 9/7/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 9/1/2017 | | FAIL |
Rob Patrick
|
|
|
Please provide structural dwg showing how new unit is attached to existing buildings "Auxiliary Support Members" as called out in detail 1 on sheet M102A.
|
Application received | | | 8/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2017 2:15PM
|
BLD-Final | 9/14/2018 | 9/17/2018 | | A | |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Brandon Sorensen
|